Work Sanctioned
श्री केदारनाथ धाम परिक्षेत्रान्तर्गत प्रशासनिक कार्यालय व अस्पताल भवन का निर्माण कार्य (आर०ई०सी०)
on Wednesday, November 25th 2020, 6:30:00 pm
0.26%
Financial Progress
1st Expenditure
of ₹ 590000 (5.90 Lacs ) done.
Cummulative ₹ 5.90Lacs ( against 2265.16Lacs )
on Sunday, April 11th 2021, 6:30:00 pm
0.52%
Financial Progress
2nd Expenditure
of ₹ 590000 (5.90 Lacs ) done.
Cummulative ₹ 11.80Lacs ( against 2265.16Lacs )
on Tuesday, May 25th 2021, 7:52:27 am
Technical Sanction
of ₹ 1999.12 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1455/ 07(51) याता - पौड़ी/21
on Tuesday, July 6th 2021, 6:30:00 pm
0.53%
Financial Progress
3rd Expenditure
of ₹ 28668 (0.29 Lacs ) done.
Cummulative ₹ 12.09Lacs ( against 2265.16Lacs )
on Wednesday, July 7th 2021, 6:30:00 pm
0.66%
Financial Progress
10th Expenditure
of ₹ 27900 (0.28 Lacs ) done.
Cummulative ₹ 15.02Lacs ( against 2265.16Lacs )
on Wednesday, July 7th 2021, 6:30:00 pm
0.65%
Financial Progress
9th Expenditure
of ₹ 24800 (0.25 Lacs ) done.
Cummulative ₹ 14.74Lacs ( against 2265.16Lacs )
on Wednesday, July 7th 2021, 6:30:00 pm
0.64%
Financial Progress
8th Expenditure
of ₹ 24000 (0.24 Lacs ) done.
Cummulative ₹ 14.49Lacs ( against 2265.16Lacs )
on Wednesday, July 7th 2021, 6:30:00 pm
0.63%
Financial Progress
7th Expenditure
of ₹ 27000 (0.27 Lacs ) done.
Cummulative ₹ 14.25Lacs ( against 2265.16Lacs )
on Wednesday, July 7th 2021, 6:30:00 pm
0.62%
Financial Progress
6th Expenditure
of ₹ 8376 (0.08 Lacs ) done.
Cummulative ₹ 13.98Lacs ( against 2265.16Lacs )
on Wednesday, July 7th 2021, 6:30:00 pm
0.61%
Financial Progress
5th Expenditure
of ₹ 7930 (0.08 Lacs ) done.
Cummulative ₹ 13.90Lacs ( against 2265.16Lacs )
on Wednesday, July 7th 2021, 6:30:00 pm
0.61%
Financial Progress
4th Expenditure
of ₹ 173460 (1.73 Lacs ) done.
Cummulative ₹ 13.82Lacs ( against 2265.16Lacs )
on Thursday, July 22nd 2021, 6:30:00 pm
0.68%
Financial Progress
11th Expenditure
of ₹ 33182 (0.33 Lacs ) done.
Cummulative ₹ 15.35Lacs ( against 2265.16Lacs )
on Thursday, July 22nd 2021, 6:30:00 pm
0.69%
Financial Progress
12th Expenditure
of ₹ 35025 (0.35 Lacs ) done.
Cummulative ₹ 15.70Lacs ( against 2265.16Lacs )
on Thursday, July 29th 2021, 6:30:00 pm
0.75%
Financial Progress
13th Expenditure
of ₹ 134585 (1.35 Lacs ) done.
Cummulative ₹ 17.05Lacs ( against 2265.16Lacs )
on Thursday, August 5th 2021, 6:30:00 pm
2%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, August 11th 2021, 6:30:00 pm
0.79%
Financial Progress
17th Expenditure
of ₹ 19995 (0.20 Lacs ) done.
Cummulative ₹ 17.83Lacs ( against 2265.16Lacs )
on Wednesday, August 11th 2021, 6:30:00 pm
0.76%
Financial Progress
14th Expenditure
of ₹ 9235 (0.09 Lacs ) done.
Cummulative ₹ 17.14Lacs ( against 2265.16Lacs )
on Wednesday, August 11th 2021, 6:30:00 pm
0.77%
Financial Progress
15th Expenditure
of ₹ 33639 (0.34 Lacs ) done.
Cummulative ₹ 17.48Lacs ( against 2265.16Lacs )
on Wednesday, August 11th 2021, 6:30:00 pm
0.78%
Financial Progress
16th Expenditure
of ₹ 15284 (0.15 Lacs ) done.
Cummulative ₹ 17.63Lacs ( against 2265.16Lacs )
on Sunday, August 15th 2021, 10:29:05 am
PWD UttarakahndPhoto (ID 1372) from Site Received
Uploader : Jagmohan Singh, JE Civil (Samvida) ,NH Div Srinagar
Landmark : Hospital building
Remark : Collum bar banding & shuttering work
on Monday, August 16th 2021, 3:29:11 am
PWD UttarakahndPhoto (ID 702) from Site Received
Uploader : Jagmohan Singh, JE Civil (Samvida) ,NH Div Srinagar
Landmark : Hospital building
Remark : Raft layout work
on Wednesday, August 18th 2021, 4:11:30 am
PWD UttarakahndPhoto (ID 947) from Site Received
Uploader : Lokesh Kumar Saraswat, Executive Engineer Civil ,CD Baijro
Landmark : REC Hospital building Foundation Raft reinforcement checking and column orientation verification
Remark : Hospital building foundation raft column orientation checking and reinforcement checking by Assistant engineer
on Wednesday, August 18th 2021, 4:12:14 am
PWD UttarakahndPhoto (ID 993) from Site Received
Uploader : Jagmohan Singh, JE Civil (Samvida) ,NH Div Srinagar
Landmark : Hospital building
Remark : Raft work
on Thursday, August 19th 2021, 6:22:27 am
PWD UttarakahndPhoto (ID 997) from Site Received
Uploader : Lokesh Kumar Saraswat, Executive Engineer Civil ,CD Baijro
Landmark : REC Hospital building
Remark : REC.HOSPITAL.FOUNDATION LEG 2 LAYOUT FOR REINFORCEMENT
on Friday, August 20th 2021, 1:42:17 pm
PWD UttarakahndPhoto (ID 1035) from Site Received
Uploader : Jagmohan Singh, JE Civil (Samvida) ,NH Div Srinagar
Landmark : Hospital building night work
Remark : Hospital building raft concert work
on Friday, August 20th 2021, 3:46:42 pm
PWD UttarakahndPhoto (ID 1036) from Site Received
Uploader : Lokesh Kumar Saraswat, Executive Engineer Civil ,CD Baijro
Landmark : REC_HOSPITAL RAFT
Remark : REC HOSPITAL FOUNDATION CONCRETING
on Monday, August 23rd 2021, 4:51:39 am
PWD UttarakahndPhoto (ID 1046) from Site Received
Uploader : Jagmohan Singh, JE Civil (Samvida) ,NH Div Srinagar
Landmark : Hospital building
Remark : Slump testing 95
on Monday, August 23rd 2021, 3:39:39 pm
PWD UttarakahndPhoto (ID 1051) from Site Received
Uploader : Lokesh Kumar Saraswat, Executive Engineer Civil ,CD Baijro
Landmark : REC_HOSPOTAL
Remark : Hospital foundation_leg 2_concreting
on Tuesday, August 24th 2021, 3:44:26 am
PWD UttarakahndPhoto (ID 1052) from Site Received
Uploader : Lokesh Kumar Saraswat, Executive Engineer Civil ,CD Baijro
Landmark : REC_HOSPITAL
Remark : Concreting of foundation footing leg 2 in progress
on Wednesday, August 25th 2021, 5:00:18 am
PWD UttarakahndPhoto (ID 1078) from Site Received
Uploader : Lokesh Kumar Saraswat, Executive Engineer Civil ,CD Baijro
Landmark : Rec. Hospital
Remark : REC_HOSPITAL_INSPECTION VISIT_DM SIR
on Wednesday, September 1st 2021, 6:30:00 pm
0.84%
Financial Progress
18th Expenditure
of ₹ 124166 (1.24 Lacs ) done.
Cummulative ₹ 19.07Lacs ( against 2265.16Lacs )
on Tuesday, September 7th 2021, 6:30:00 pm
0.89%
Financial Progress
19th Expenditure
of ₹ 105846 (1.06 Lacs ) done.
Cummulative ₹ 20.13Lacs ( against 2265.16Lacs )
on Monday, September 13th 2021, 6:30:00 pm
0.91%
Financial Progress
20th Expenditure
of ₹ 50820 (0.51 Lacs ) done.
Cummulative ₹ 20.64Lacs ( against 2265.16Lacs )
on Tuesday, September 14th 2021, 5:38:55 am
PWD UttarakahndPhoto (ID 1375) from Site Received
Uploader : Lokesh Kumar Saraswat, Executive Engineer Civil ,CD Baijro
Landmark : Hospital
Remark : Visit of Administrative officer
on Wednesday, September 15th 2021, 11:15:36 am
PWD UttarakahndPhoto (ID 1390) from Site Received
Uploader : Lokesh Kumar Saraswat, Executive Engineer Civil ,CD Baijro
Landmark : Hospital building
Remark : Column casting in progress
on Wednesday, September 15th 2021, 6:30:00 pm
5%
Physical Progress
Physical Progress Reported at 2nd time
on Saturday, September 18th 2021, 3:42:28 am
PWD UttarakahndPhoto (ID 1415) from Site Received
Uploader : Lokesh Kumar Saraswat, Executive Engineer Civil ,CD Baijro
Landmark : Hospital
Remark : RRM & column casting in progress
on Friday, September 24th 2021, 6:30:00 pm
0.94%
Financial Progress
21st Expenditure
of ₹ 58863 (0.59 Lacs ) done.
Cummulative ₹ 21.23Lacs ( against 2265.16Lacs )
on Friday, September 24th 2021, 6:30:00 pm
0.96%
Financial Progress
22nd Expenditure
of ₹ 59525 (0.60 Lacs ) done.
Cummulative ₹ 21.82Lacs ( against 2265.16Lacs )
on Friday, September 24th 2021, 6:30:00 pm
1.00%
Financial Progress
23rd Expenditure
of ₹ 80240 (0.80 Lacs ) done.
Cummulative ₹ 22.63Lacs ( against 2265.16Lacs )
on Monday, September 27th 2021, 6:30:00 pm
6.5%
Physical Progress
Physical Progress Reported at 3rd time
on Thursday, October 21st 2021, 6:30:00 pm
1.06%
Financial Progress
24th Expenditure
of ₹ 127260 (1.27 Lacs ) done.
Cummulative ₹ 23.90Lacs ( against 2265.16Lacs )
on Thursday, October 21st 2021, 6:30:00 pm
1.17%
Financial Progress
25th Expenditure
of ₹ 254694 (2.55 Lacs ) done.
Cummulative ₹ 26.44Lacs ( against 2265.16Lacs )
on Tuesday, October 26th 2021, 6:30:00 pm
1.25%
Financial Progress
26th Expenditure
of ₹ 182000 (1.82 Lacs ) done.
Cummulative ₹ 28.26Lacs ( against 2265.16Lacs )
on Tuesday, October 26th 2021, 6:30:00 pm
1.26%
Financial Progress
27th Expenditure
of ₹ 27375 (0.27 Lacs ) done.
Cummulative ₹ 28.54Lacs ( against 2265.16Lacs )
on Tuesday, October 26th 2021, 6:30:00 pm
1.35%
Financial Progress
28th Expenditure
of ₹ 200000 (2.00 Lacs ) done.
Cummulative ₹ 30.54Lacs ( against 2265.16Lacs )
on Thursday, October 28th 2021, 6:30:00 pm
1.37%
Financial Progress
29th Expenditure
of ₹ 50000 (0.50 Lacs ) done.
Cummulative ₹ 31.04Lacs ( against 2265.16Lacs )
on Thursday, October 28th 2021, 6:30:00 pm
1.41%
Financial Progress
30th Expenditure
of ₹ 100000 (1.00 Lacs ) done.
Cummulative ₹ 32.04Lacs ( against 2265.16Lacs )
on Friday, October 29th 2021, 6:30:00 pm
1.44%
Financial Progress
31st Expenditure
of ₹ 59600 (0.60 Lacs ) done.
Cummulative ₹ 32.63Lacs ( against 2265.16Lacs )
on Friday, October 29th 2021, 6:30:00 pm
1.47%
Financial Progress
32nd Expenditure
of ₹ 59600 (0.60 Lacs ) done.
Cummulative ₹ 33.23Lacs ( against 2265.16Lacs )
on Monday, November 22nd 2021, 6:30:00 pm
6.07%
Financial Progress
33rd Expenditure
of ₹ 10416788 (104.17 Lacs ) done.
Cummulative ₹ 137.40Lacs ( against 2265.16Lacs )
on Tuesday, November 23rd 2021, 6:30:00 pm
6.57%
Financial Progress
34th Expenditure
of ₹ 1137520 (11.38 Lacs ) done.
Cummulative ₹ 148.77Lacs ( against 2265.16Lacs )
on Sunday, December 26th 2021, 6:30:00 pm
6.60%
Financial Progress
35th Expenditure
of ₹ 66080 (0.66 Lacs ) done.
Cummulative ₹ 149.43Lacs ( against 2265.16Lacs )
on Sunday, December 26th 2021, 6:30:00 pm
6.69%
Financial Progress
36th Expenditure
of ₹ 202720 (2.03 Lacs ) done.
Cummulative ₹ 151.46Lacs ( against 2265.16Lacs )
on Monday, January 3rd 2022, 6:30:00 pm
6.70%
Financial Progress
37th Expenditure
of ₹ 20060 (0.20 Lacs ) done.
Cummulative ₹ 151.66Lacs ( against 2265.16Lacs )
on Sunday, January 16th 2022, 6:30:00 pm
6.72%
Financial Progress
39th Expenditure
of ₹ 27900 (0.28 Lacs ) done.
Cummulative ₹ 152.19Lacs ( against 2265.16Lacs )
on Sunday, January 16th 2022, 6:30:00 pm
6.71%
Financial Progress
38th Expenditure
of ₹ 24800 (0.25 Lacs ) done.
Cummulative ₹ 151.91Lacs ( against 2265.16Lacs )
on Sunday, January 16th 2022, 6:30:00 pm
6.80%
Financial Progress
40th Expenditure
of ₹ 179242 (1.79 Lacs ) done.
Cummulative ₹ 153.98Lacs ( against 2265.16Lacs )
on Thursday, January 20th 2022, 6:30:00 pm
6.81%
Financial Progress
41st Expenditure
of ₹ 17700 (0.18 Lacs ) done.
Cummulative ₹ 154.16Lacs ( against 2265.16Lacs )
on Thursday, January 20th 2022, 6:30:00 pm
6.85%
Financial Progress
44th Expenditure
of ₹ 38350 (0.38 Lacs ) done.
Cummulative ₹ 155.23Lacs ( against 2265.16Lacs )
on Thursday, January 20th 2022, 6:30:00 pm
6.84%
Financial Progress
43rd Expenditure
of ₹ 34810 (0.35 Lacs ) done.
Cummulative ₹ 154.84Lacs ( against 2265.16Lacs )
on Thursday, January 20th 2022, 6:30:00 pm
6.82%
Financial Progress
42nd Expenditure
of ₹ 33630 (0.34 Lacs ) done.
Cummulative ₹ 154.50Lacs ( against 2265.16Lacs )
on Friday, January 21st 2022, 6:30:00 pm
7.03%
Financial Progress
46th Expenditure
of ₹ 189235 (1.89 Lacs ) done.
Cummulative ₹ 159.22Lacs ( against 2265.16Lacs )
on Friday, January 21st 2022, 6:30:00 pm
6.95%
Financial Progress
45th Expenditure
of ₹ 210450 (2.10 Lacs ) done.
Cummulative ₹ 157.33Lacs ( against 2265.16Lacs )
on Monday, January 24th 2022, 6:30:00 pm
7.03%
Financial Progress
47th Expenditure
of ₹ 5000 (0.05 Lacs ) done.
Cummulative ₹ 159.27Lacs ( against 2265.16Lacs )
on Tuesday, March 8th 2022, 6:30:00 pm
7.06%
Financial Progress
48th Expenditure
of ₹ 64033 (0.64 Lacs ) done.
Cummulative ₹ 159.91Lacs ( against 2265.16Lacs )
on Thursday, March 10th 2022, 6:30:00 pm
7.20%
Financial Progress
52nd Expenditure
of ₹ 13580 (0.14 Lacs ) done.
Cummulative ₹ 163.10Lacs ( against 2265.16Lacs )
on Thursday, March 10th 2022, 6:30:00 pm
7.19%
Financial Progress
51st Expenditure
of ₹ 14000 (0.14 Lacs ) done.
Cummulative ₹ 162.96Lacs ( against 2265.16Lacs )
on Thursday, March 10th 2022, 6:30:00 pm
7.19%
Financial Progress
50th Expenditure
of ₹ 130260 (1.30 Lacs ) done.
Cummulative ₹ 162.82Lacs ( against 2265.16Lacs )
on Thursday, March 10th 2022, 6:30:00 pm
7.13%
Financial Progress
49th Expenditure
of ₹ 160440 (1.60 Lacs ) done.
Cummulative ₹ 161.52Lacs ( against 2265.16Lacs )
on Thursday, March 24th 2022, 6:30:00 pm
7.21%
Financial Progress
54th Expenditure
of ₹ 4910 (0.05 Lacs ) done.
Cummulative ₹ 163.22Lacs ( against 2265.16Lacs )
on Thursday, March 24th 2022, 6:30:00 pm
7.20%
Financial Progress
53rd Expenditure
of ₹ 7033 (0.07 Lacs ) done.
Cummulative ₹ 163.17Lacs ( against 2265.16Lacs )
on Sunday, October 30th 2022, 6:30:00 pm
8.93%
Financial Progress
55th Expenditure
of ₹ 3913807 (39.14 Lacs ) done.
Cummulative ₹ 202.35Lacs ( against 2265.16Lacs )
on Monday, December 19th 2022, 6:30:00 pm
18%
Physical Progress
Physical Progress Reported at 4th time
on Thursday, March 30th 2023, 6:30:00 pm
17.22%
Financial Progress
56th Expenditure
of ₹ 18767825 (187.68 Lacs ) done.
Cummulative ₹ 390.03Lacs ( against 2265.16Lacs )
on Sunday, July 2nd 2023, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 5th time
on Wednesday, February 28th 2024, 6:30:00 pm
40.94%
Financial Progress
57th Expenditure
of ₹ 53735000 (537.35 Lacs ) done.
Cummulative ₹ 927.38Lacs ( against 2265.16Lacs )
on Tuesday, April 9th 2024, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 6th time