Refresh data
on Monday, January 2nd 2017, 6:30:00 pm
Work Sanctioned
fवकासखण्ड पोखरी के अन्तर्गत मैठाणा-स्यालतरी मोटर मार्ग का नव fनर्माण कार्य (प्रथम चरण)।
on Friday, June 30th 2017, 6:30:00 pm
0.39%
Financial Progress
1st Expenditure
of ₹ 19000 (0.19 Lacs ) done.
Cummulative ₹ 0.19Lacs ( against 48.35Lacs )
on Monday, July 31st 2017, 6:30:00 pm
0.00%
Financial Progress
2nd Expenditure
of ₹ -19000 (-0.19 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 48.35Lacs )
on Monday, November 30th 2020, 6:30:00 pm
0.14%
Financial Progress
3rd Expenditure
of ₹ 7000 (0.07 Lacs ) done.
Cummulative ₹ 0.07Lacs ( against 48.35Lacs )
on Monday, October 31st 2022, 6:30:00 pm
1.54%
Financial Progress
4th Expenditure
of ₹ 67340 (0.67 Lacs ) done.
Cummulative ₹ 0.74Lacs ( against 48.35Lacs )
on Sunday, April 14th 2024, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, May 1st 2024, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 2nd time
on Monday, February 17th 2025, 6:30:00 pm
1.95%
Financial Progress
5th Expenditure
of ₹ 19983 (0.20 Lacs ) done.
Cummulative ₹ 0.94Lacs ( against 48.35Lacs )
on Monday, February 17th 2025, 6:30:00 pm
2.47%
Financial Progress
6th Expenditure
of ₹ 24978 (0.25 Lacs ) done.
Cummulative ₹ 1.19Lacs ( against 48.35Lacs )
on Monday, February 24th 2025, 6:30:00 pm
4.48%
Financial Progress
7th Expenditure
of ₹ 97500 (0.97 Lacs ) done.
Cummulative ₹ 2.17Lacs ( against 48.35Lacs )