Refresh data
on Thursday, August 22nd 2024, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद हरिद्वार के विधानसभा क्षेत्र लक्सर के ग्राम बुक्कनपुर में इसम सिंह पुत्र श्री अतर सिंह के खेत से खाली व रामपाल के खेत की ओर मार्ग का इंटरलोकिंग टाईल्स द्वारा मार्ग का निर्माण कार्य।
on Thursday, November 21st 2024, 6:30:00 pm
28.48%
Financial Progress
1st Expenditure
of ₹ 1203490 (12.03 Lacs ) done.
Cummulative ₹ 12.03Lacs ( against 42.25Lacs )
on Wednesday, November 27th 2024, 6:30:00 pm
56.00%
Financial Progress
2nd Expenditure
of ₹ 1162660 (11.63 Lacs ) done.
Cummulative ₹ 23.66Lacs ( against 42.25Lacs )
on Friday, January 24th 2025, 6:30:00 pm
58.14%
Financial Progress
3rd Expenditure
of ₹ 90270 (0.90 Lacs ) done.
Cummulative ₹ 24.56Lacs ( against 42.25Lacs )
on Thursday, January 30th 2025, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, February 5th 2025, 6:30:00 pm
63.98%
Financial Progress
4th Expenditure
of ₹ 246627 (2.47 Lacs ) done.
Cummulative ₹ 27.03Lacs ( against 42.25Lacs )
on Monday, February 10th 2025, 6:30:00 pm
68.63%
Financial Progress
5th Expenditure
of ₹ 196378 (1.96 Lacs ) done.
Cummulative ₹ 28.99Lacs ( against 42.25Lacs )
on Monday, March 10th 2025, 6:30:00 pm
68.86%
Financial Progress
6th Expenditure
of ₹ 10101 (0.10 Lacs ) done.
Cummulative ₹ 29.10Lacs ( against 42.25Lacs )
on Monday, March 24th 2025, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, May 1st 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time
on Wednesday, May 14th 2025, 6:30:00 pm
69.27%
Financial Progress
7th Expenditure
of ₹ 17110 (0.17 Lacs ) done.
Cummulative ₹ 29.27Lacs ( against 42.25Lacs )
on Thursday, May 15th 2025, 6:30:00 pm
92.57%
Financial Progress
8th Expenditure
of ₹ 984474 (9.84 Lacs ) done.
Cummulative ₹ 39.11Lacs ( against 42.25Lacs )
on Sunday, August 3rd 2025, 6:30:00 pm
93.03%
Financial Progress
9th Expenditure
of ₹ 19500 (0.20 Lacs ) done.
Cummulative ₹ 39.31Lacs ( against 42.25Lacs )
on Wednesday, August 13th 2025, 6:30:00 pm
93.99%
Financial Progress
10th Expenditure
of ₹ 40300 (0.40 Lacs ) done.
Cummulative ₹ 39.71Lacs ( against 42.25Lacs )