Work Sanctioned
राज्य योजना के अन्तर्गत जनपद नैनीताल के विधानसभा क्षेत्र भीमताल के धारी ब्लाक मुख्यालय से कौल धानाचूली होते हुए मोटर मार्ग का निर्माण कार्य। (द्वितीय चरण)

3 years ago

on Friday, June 24th 2022, 6:30:00 pm
0.07%
Financial Progress

1st Expenditure
of ₹ 7000 (0.07 Lacs ) done.
Cummulative ₹ 0.07Lacs ( against 106.25Lacs )

3 years ago

on Friday, August 26th 2022, 6:30:00 pm
1%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Thursday, September 15th 2022, 6:30:00 pm
0.00%
Financial Progress

2nd Expenditure
of ₹ -7000 (-0.07 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 106.25Lacs )

3 years ago

on Wednesday, November 2nd 2022, 2:34:06 am
<span class="4">Picture Id:10401</span>
PWD Uttarakahnd
Photo (ID 10401) from Site Received
Uploader : Lalit Mohan Sharma, Additional Assistant Engineer Civil ,NH Div Ranikhet
Landmark : 1.925
Remark : Road cutting progress

3 years ago

on Wednesday, November 2nd 2022, 2:34:38 am
<span class="4">Picture Id:8909</span>
PWD Uttarakahnd
Photo (ID 8909) from Site Received
Uploader : Vishwa Mohan Giri, Assistant Engineer Civil ,TD Bhawali
Landmark : 1.525
Remark : Hill side cutting work in progress

3 years ago

on Wednesday, November 2nd 2022, 3:55:13 am
<span class="4">Picture Id:9899</span>
PWD Uttarakahnd
Photo (ID 9899) from Site Received
Uploader : Vishwa Mohan Giri, Assistant Engineer Civil ,TD Bhawali
Landmark : 1.200
Remark : Hill side cutting work in progress

2 years ago

on Thursday, December 15th 2022, 12:19:47 am
<span class="4">Picture Id:14087</span>
PWD Uttarakahnd
Photo (ID 14087) from Site Received
Uploader : Vishwa Mohan Giri, Assistant Engineer Civil ,TD Bhawali
Landmark : 0.925
Remark : Hill side cutting at HP bend

2 years ago

on Thursday, December 15th 2022, 12:21:00 am
<span class="4">Picture Id:14088</span>
PWD Uttarakahnd
Photo (ID 14088) from Site Received
Uploader : Lalit Mohan Sharma, Additional Assistant Engineer Civil ,NH Div Ranikhet
Landmark : 0.975
Remark : Hill side cutting on progress

2 years ago

on Thursday, December 15th 2022, 12:38:17 am
<span class="4">Picture Id:14090</span>
PWD Uttarakahnd
Photo (ID 14090) from Site Received
Uploader : Vishwa Mohan Giri, Assistant Engineer Civil ,TD Bhawali
Landmark : 0.825
Remark : Hill side cutting in progress at HP bend no1

2 years ago

on Thursday, December 15th 2022, 12:44:07 am
<span class="4">Picture Id:14091</span>
PWD Uttarakahnd
Photo (ID 14091) from Site Received
Uploader : Lalit Mohan Sharma, Additional Assistant Engineer Civil ,NH Div Ranikhet
Landmark : 0.0.350
Remark : Hill side cutting

2 years ago

on Friday, December 30th 2022, 6:30:00 pm
6.32%
Financial Progress

3rd Expenditure
of ₹ 672000 (6.72 Lacs ) done.
Cummulative ₹ 6.72Lacs ( against 106.25Lacs )

2 years ago

on Monday, January 30th 2023, 6:30:00 pm
12.65%
Financial Progress

4th Expenditure
of ₹ 672000 (6.72 Lacs ) done.
Cummulative ₹ 13.44Lacs ( against 106.25Lacs )

2 years ago

on Monday, February 27th 2023, 6:30:00 pm
13.18%
Financial Progress

5th Expenditure
of ₹ 56000 (0.56 Lacs ) done.
Cummulative ₹ 14.00Lacs ( against 106.25Lacs )

2 years ago

on Wednesday, August 30th 2023, 6:30:00 pm
26.00%
Financial Progress

6th Expenditure
of ₹ 1362497 (13.62 Lacs ) done.
Cummulative ₹ 27.62Lacs ( against 106.25Lacs )

2 years ago

on Friday, September 29th 2023, 6:30:00 pm
30.96%
Financial Progress

7th Expenditure
of ₹ 526649 (5.27 Lacs ) done.
Cummulative ₹ 32.89Lacs ( against 106.25Lacs )

a year ago

on Sunday, December 17th 2023, 6:30:00 pm
33.29%
Financial Progress

8th Expenditure
of ₹ 247426 (2.47 Lacs ) done.
Cummulative ₹ 35.37Lacs ( against 106.25Lacs )

a year ago

on Thursday, January 11th 2024, 6:30:00 pm
41.14%
Financial Progress

9th Expenditure
of ₹ 834236 (8.34 Lacs ) done.
Cummulative ₹ 43.71Lacs ( against 106.25Lacs )

a year ago

on Sunday, February 11th 2024, 6:30:00 pm
41.43%
Financial Progress

10th Expenditure
of ₹ 31000 (0.31 Lacs ) done.
Cummulative ₹ 44.02Lacs ( against 106.25Lacs )

a year ago

on Monday, April 1st 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

10 months ago

on Tuesday, July 30th 2024, 6:30:00 pm
50.51%
Financial Progress

11th Expenditure
of ₹ 965101 (9.65 Lacs ) done.
Cummulative ₹ 53.67Lacs ( against 106.25Lacs )

5 months ago

on Monday, December 30th 2024, 6:30:00 pm
53.59%
Financial Progress

12th Expenditure
of ₹ 326556 (3.27 Lacs ) done.
Cummulative ₹ 56.93Lacs ( against 106.25Lacs )

4 months ago

on Tuesday, January 28th 2025, 6:30:00 pm
57.24%
Financial Progress

13th Expenditure
of ₹ 388498 (3.88 Lacs ) done.
Cummulative ₹ 60.82Lacs ( against 106.25Lacs )

3 months ago

on Tuesday, February 25th 2025, 6:30:00 pm
57.53%
Financial Progress

14th Expenditure
of ₹ 31000 (0.31 Lacs ) done.
Cummulative ₹ 61.13Lacs ( against 106.25Lacs )

2 months ago

on Sunday, March 30th 2025, 6:30:00 pm
58.85%
Financial Progress

16th Expenditure
of ₹ -409000 (-4.09 Lacs ) done.
Cummulative ₹ 62.53Lacs ( against 106.25Lacs )

2 months ago

on Sunday, March 30th 2025, 6:30:00 pm
62.70%
Financial Progress

15th Expenditure
of ₹ 548756 (5.49 Lacs ) done.
Cummulative ₹ 66.62Lacs ( against 106.25Lacs )