19 years ago

on Monday, March 27th 2006, 6:30:00 pm
Work Sanctioned
छीड़ाखान से हाईस्कूल तल्ली-पोखरी तक सम्र्पक मार्ग का निर्माण।

16 years ago

on Saturday, February 28th 2009, 6:30:00 pm
0.04%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 283.93Lacs )

9 years ago

on Saturday, April 30th 2016, 6:30:00 pm
0.65%
Financial Progress

2nd Expenditure
of ₹ 173565 (1.74 Lacs ) done.
Cummulative ₹ 1.84Lacs ( against 283.93Lacs )

9 years ago

on Thursday, June 30th 2016, 6:30:00 pm
0.66%
Financial Progress

3rd Expenditure
of ₹ 3100 (0.03 Lacs ) done.
Cummulative ₹ 1.87Lacs ( against 283.93Lacs )

9 years ago

on Monday, October 31st 2016, 6:30:00 pm
0.68%
Financial Progress

4th Expenditure
of ₹ 5140 (0.05 Lacs ) done.
Cummulative ₹ 1.92Lacs ( against 283.93Lacs )

8 years ago

on Sunday, April 30th 2017, 6:30:00 pm
0.75%
Financial Progress

5th Expenditure
of ₹ 20650 (0.21 Lacs ) done.
Cummulative ₹ 2.12Lacs ( against 283.93Lacs )

8 years ago

on Saturday, September 30th 2017, 6:30:00 pm
0.77%
Financial Progress

6th Expenditure
of ₹ 5000 (0.05 Lacs ) done.
Cummulative ₹ 2.17Lacs ( against 283.93Lacs )

7 years ago

on Thursday, June 28th 2018, 6:30:00 pm

Technical Sanction
of ₹ 103.5 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2411/576C-02/2017

6 years ago

on Monday, December 31st 2018, 6:30:00 pm
4.50%
Financial Progress

7th Expenditure
of ₹ 1058960 (10.59 Lacs ) done.
Cummulative ₹ 12.76Lacs ( against 283.93Lacs )

6 years ago

on Thursday, January 31st 2019, 6:30:00 pm
4.58%
Financial Progress

8th Expenditure
of ₹ 23386 (0.23 Lacs ) done.
Cummulative ₹ 13.00Lacs ( against 283.93Lacs )

6 years ago

on Thursday, February 28th 2019, 6:30:00 pm
4.59%
Financial Progress

9th Expenditure
of ₹ 4750 (0.05 Lacs ) done.
Cummulative ₹ 13.05Lacs ( against 283.93Lacs )

6 years ago

on Friday, May 31st 2019, 6:30:00 pm
6.27%
Financial Progress

10th Expenditure
of ₹ 474455 (4.74 Lacs ) done.
Cummulative ₹ 17.79Lacs ( against 283.93Lacs )

6 years ago

on Sunday, June 30th 2019, 6:30:00 pm
9.24%
Financial Progress

11th Expenditure
of ₹ 843910 (8.44 Lacs ) done.
Cummulative ₹ 26.23Lacs ( against 283.93Lacs )

6 years ago

on Saturday, August 31st 2019, 6:30:00 pm
9.58%
Financial Progress

12th Expenditure
of ₹ 97244 (0.97 Lacs ) done.
Cummulative ₹ 27.20Lacs ( against 283.93Lacs )

6 years ago

on Monday, September 30th 2019, 6:30:00 pm
9.90%
Financial Progress

13th Expenditure
of ₹ 91210 (0.91 Lacs ) done.
Cummulative ₹ 28.11Lacs ( against 283.93Lacs )

5 years ago

on Saturday, November 30th 2019, 6:30:00 pm
12.57%
Financial Progress

14th Expenditure
of ₹ 756748 (7.57 Lacs ) done.
Cummulative ₹ 35.68Lacs ( against 283.93Lacs )

5 years ago

on Tuesday, December 31st 2019, 6:30:00 pm
13.44%
Financial Progress

15th Expenditure
of ₹ 246678 (2.47 Lacs ) done.
Cummulative ₹ 38.15Lacs ( against 283.93Lacs )

5 years ago

on Friday, January 31st 2020, 6:30:00 pm
13.44%
Financial Progress

16th Expenditure
of ₹ 980 (0.01 Lacs ) done.
Cummulative ₹ 38.16Lacs ( against 283.93Lacs )

5 years ago

on Sunday, May 31st 2020, 6:30:00 pm
13.76%
Financial Progress

17th Expenditure
of ₹ 92500 (0.93 Lacs ) done.
Cummulative ₹ 39.08Lacs ( against 283.93Lacs )

5 years ago

on Tuesday, June 30th 2020, 6:30:00 pm
14.99%
Financial Progress

18th Expenditure
of ₹ 348785 (3.49 Lacs ) done.
Cummulative ₹ 42.57Lacs ( against 283.93Lacs )

5 years ago

on Friday, July 31st 2020, 6:30:00 pm
15.01%
Financial Progress

19th Expenditure
of ₹ 3400 (0.03 Lacs ) done.
Cummulative ₹ 42.60Lacs ( against 283.93Lacs )

5 years ago

on Monday, August 31st 2020, 6:30:00 pm
20.48%
Financial Progress

20th Expenditure
of ₹ 1554000 (15.54 Lacs ) done.
Cummulative ₹ 58.14Lacs ( against 283.93Lacs )

4 years ago

on Sunday, January 31st 2021, 6:30:00 pm
21.17%
Financial Progress

21st Expenditure
of ₹ 196873 (1.97 Lacs ) done.
Cummulative ₹ 60.11Lacs ( against 283.93Lacs )

4 years ago

on Sunday, February 28th 2021, 6:30:00 pm
25.55%
Financial Progress

22nd Expenditure
of ₹ 1243374 (12.43 Lacs ) done.
Cummulative ₹ 72.55Lacs ( against 283.93Lacs )

4 years ago

on Tuesday, June 22nd 2021, 6:30:00 pm
28.70%
Financial Progress

23rd Expenditure
of ₹ 895265 (8.95 Lacs ) done.
Cummulative ₹ 81.50Lacs ( against 283.93Lacs )

3 years ago

on Friday, June 24th 2022, 6:30:00 pm
25%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Friday, June 24th 2022, 6:30:00 pm
42.41%
Financial Progress

24th Expenditure
of ₹ 3891027 (38.91 Lacs ) done.
Cummulative ₹ 120.41Lacs ( against 283.93Lacs )

3 years ago

on Wednesday, June 29th 2022, 6:30:00 pm
48.13%
Financial Progress

25th Expenditure
of ₹ 1625000 (16.25 Lacs ) done.
Cummulative ₹ 136.66Lacs ( against 283.93Lacs )

3 years ago

on Thursday, July 28th 2022, 3:58:58 am
<span class="4">Picture Id:6930</span>
PWD Uttarakahnd
Photo (ID 6930) from Site Received
Uploader : Vishwa Mohan Giri, Assistant Engineer Civil ,TD Bhawali
Landmark : 4.850
Remark : Const of scupper

3 years ago

on Thursday, July 28th 2022, 4:26:04 am
<span class="4">Picture Id:6931</span>
PWD Uttarakahnd
Photo (ID 6931) from Site Received
Uploader : Ganesh Chandra, Additional Assistant Engineer Civil ,CD Almora
Landmark : 5.400
Remark : Chirakhan highschool talli pokhari m road construction of scuppers

3 years ago

on Thursday, July 28th 2022, 4:39:51 am
<span class="4">Picture Id:6932</span>
PWD Uttarakahnd
Photo (ID 6932) from Site Received
Uploader : Ganesh Chandra, Additional Assistant Engineer Civil ,CD Almora
Landmark : 5.625
Remark : Chirakhan pokhari m road construction of scuppers

3 years ago

on Thursday, July 28th 2022, 5:23:55 am
<span class="4">Picture Id:6935</span>
PWD Uttarakahnd
Photo (ID 6935) from Site Received
Uploader : Vishwa Mohan Giri, Assistant Engineer Civil ,TD Bhawali
Landmark : 5.200
Remark : B/W and Protection wall for house

3 years ago

on Friday, August 19th 2022, 11:55:26 pm
<span class="4">Picture Id:7243</span>
PWD Uttarakahnd
Photo (ID 7243) from Site Received
Uploader : Ganesh Chandra, Additional Assistant Engineer Civil ,CD Almora
Landmark : 3.400
Remark : Foundation excavating work for scupper

3 years ago

on Wednesday, August 24th 2022, 6:30:00 pm
40%

Physical Progress
Physical Progress Reported at 2nd time

3 years ago

on Saturday, September 3rd 2022, 1:50:07 am
<span class="4">Picture Id:7698</span>
PWD Uttarakahnd
Photo (ID 7698) from Site Received
Uploader : Ganesh Chandra, Additional Assistant Engineer Civil ,CD Almora
Landmark : 3.200
Remark : Construction of scuppers

3 years ago

on Saturday, September 3rd 2022, 2:20:55 am
<span class="4">Picture Id:7705</span>
PWD Uttarakahnd
Photo (ID 7705) from Site Received
Uploader : Ganesh Chandra, Additional Assistant Engineer Civil ,CD Almora
Landmark : 4.700
Remark : C/o scuppers

3 years ago

on Thursday, September 15th 2022, 6:30:00 pm
34.43%
Financial Progress

26th Expenditure
of ₹ -3891027 (-38.91 Lacs ) done.
Cummulative ₹ 97.75Lacs ( against 283.93Lacs )

3 years ago

on Monday, September 26th 2022, 3:34:08 am
<span class="4">Picture Id:8148</span>
PWD Uttarakahnd
Photo (ID 8148) from Site Received
Uploader : Ganesh Chandra, Additional Assistant Engineer Civil ,CD Almora
Landmark : 4.900
Remark : Scupper slab casting

3 years ago

on Thursday, September 29th 2022, 6:30:00 pm
39.50%
Financial Progress

27th Expenditure
of ₹ 1439213 (14.39 Lacs ) done.
Cummulative ₹ 112.14Lacs ( against 283.93Lacs )

3 years ago

on Friday, October 14th 2022, 2:49:40 am
<span class="4">Picture Id:8541</span>
PWD Uttarakahnd
Photo (ID 8541) from Site Received
Uploader : Ganesh Chandra, Additional Assistant Engineer Civil ,CD Almora
Landmark : 4.375
Remark : Scupper slab curring preparation

3 years ago

on Friday, October 14th 2022, 3:19:16 am
<span class="4">Picture Id:8830</span>
PWD Uttarakahnd
Photo (ID 8830) from Site Received
Uploader : Ganesh Chandra, Additional Assistant Engineer Civil ,CD Almora
Landmark : 3.950
Remark : Scupper retaining walls construction on progress

3 years ago

on Sunday, October 30th 2022, 6:30:00 pm
50.40%
Financial Progress

28th Expenditure
of ₹ 3095804 (30.96 Lacs ) done.
Cummulative ₹ 143.10Lacs ( against 283.93Lacs )

3 years ago

on Saturday, November 12th 2022, 11:16:49 pm
<span class="4">Picture Id:9149</span>
PWD Uttarakahnd
Photo (ID 9149) from Site Received
Uploader : Ganesh Chandra, Additional Assistant Engineer Civil ,CD Almora
Landmark : 4.800
Remark : Muck disposal

2 years ago

on Tuesday, November 29th 2022, 6:30:00 pm
50.58%
Financial Progress

29th Expenditure
of ₹ 52121 (0.52 Lacs ) done.
Cummulative ₹ 143.62Lacs ( against 283.93Lacs )

2 years ago

on Thursday, December 1st 2022, 3:23:02 am
<span class="4">Picture Id:12315</span>
PWD Uttarakahnd
Photo (ID 12315) from Site Received
Uploader : Ganesh Chandra, Additional Assistant Engineer Civil ,CD Almora
Landmark : 4.325
Remark : House protection and village path

2 years ago

on Friday, December 30th 2022, 6:30:00 pm
55.08%
Financial Progress

30th Expenditure
of ₹ 1275422 (12.75 Lacs ) done.
Cummulative ₹ 156.38Lacs ( against 283.93Lacs )

2 years ago

on Saturday, December 31st 2022, 6:25:54 am
<span class="4">Picture Id:15335</span>
PWD Uttarakahnd
Photo (ID 15335) from Site Received
Uploader : Ganesh Chandra, Additional Assistant Engineer Civil ,CD Almora
Landmark : 4.150
Remark : Walls for house safty

2 years ago

on Wednesday, January 11th 2023, 2:50:51 am
<span class="4">Picture Id:15417</span>
PWD Uttarakahnd
Photo (ID 15417) from Site Received
Uploader : Vishwa Mohan Giri, Assistant Engineer Civil ,TD Bhawali
Landmark : 2.450
Remark : Collection of G1

2 years ago

on Wednesday, January 11th 2023, 2:53:33 am
<span class="4">Picture Id:15418</span>
PWD Uttarakahnd
Photo (ID 15418) from Site Received
Uploader : Vishwa Mohan Giri, Assistant Engineer Civil ,TD Bhawali
Landmark : 2.500
Remark : General view of the road

2 years ago

on Wednesday, January 11th 2023, 2:55:05 am
<span class="4">Picture Id:15419</span>
PWD Uttarakahnd
Photo (ID 15419) from Site Received
Uploader : Vishwa Mohan Giri, Assistant Engineer Civil ,TD Bhawali
Landmark : 2.550
Remark : Const of cathpit

2 years ago

on Wednesday, January 11th 2023, 4:23:37 am
<span class="4">Picture Id:15424</span>
PWD Uttarakahnd
Photo (ID 15424) from Site Received
Uploader : Ganesh Chandra, Additional Assistant Engineer Civil ,CD Almora
Landmark : 5.750
Remark : C/ओ scupper

2 years ago

on Wednesday, January 11th 2023, 4:25:17 am
<span class="4">Picture Id:15425</span>
PWD Uttarakahnd
Photo (ID 15425) from Site Received
Uploader : Vishwa Mohan Giri, Assistant Engineer Civil ,TD Bhawali
Landmark : 5.825
Remark : Protection of HT line

2 years ago

on Wednesday, January 11th 2023, 4:29:51 am
<span class="4">Picture Id:15426</span>
PWD Uttarakahnd
Photo (ID 15426) from Site Received
Uploader : Vishwa Mohan Giri, Assistant Engineer Civil ,TD Bhawali
Landmark : 6.000
Remark : End point of the road

2 years ago

on Wednesday, January 11th 2023, 5:21:04 am
<span class="4">Picture Id:15539</span>
PWD Uttarakahnd
Photo (ID 15539) from Site Received
Uploader : Vishwa Mohan Giri, Assistant Engineer Civil ,TD Bhawali
Landmark : 5.475
Remark : Const 0f scupper

2 years ago

on Wednesday, January 11th 2023, 6:25:11 am
<span class="4">Picture Id:15540</span>
PWD Uttarakahnd
Photo (ID 15540) from Site Received
Uploader : Vishwa Mohan Giri, Assistant Engineer Civil ,TD Bhawali
Landmark : 0.100
Remark : Starting point

2 years ago

on Monday, January 30th 2023, 6:30:00 pm
55.08%
Financial Progress

31st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 156.38Lacs ( against 283.93Lacs )

2 years ago

on Monday, January 30th 2023, 6:30:00 pm
62.56%
Financial Progress

32nd Expenditure
of ₹ 2125556 (21.26 Lacs ) done.
Cummulative ₹ 177.63Lacs ( against 283.93Lacs )

2 years ago

on Saturday, March 4th 2023, 4:03:19 am
<span class="4">Picture Id:17664</span>
PWD Uttarakahnd
Photo (ID 17664) from Site Received
Uploader : Ganesh Chandra, Additional Assistant Engineer Civil ,CD Almora
Landmark : 5.150
Remark : Road work is going to final

2 years ago

on Thursday, March 23rd 2023, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
84.35%
Financial Progress

33rd Expenditure
of ₹ 6185428 (61.85 Lacs ) done.
Cummulative ₹ 239.49Lacs ( against 283.93Lacs )

2 years ago

on Sunday, April 16th 2023, 11:16:09 pm
<span class="4">Picture Id:19198</span>
PWD Uttarakahnd
Photo (ID 19198) from Site Received
Uploader : Ganesh Chandra, Additional Assistant Engineer Civil ,CD Almora
Landmark : 5.900
Remark : Inspection by ee sir

2 years ago

on Tuesday, May 30th 2023, 6:30:00 pm
86.90%
Financial Progress

34th Expenditure
of ₹ 725178 (7.25 Lacs ) done.
Cummulative ₹ 246.74Lacs ( against 283.93Lacs )

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
87.42%
Financial Progress

35th Expenditure
of ₹ 147713 (1.48 Lacs ) done.
Cummulative ₹ 248.21Lacs ( against 283.93Lacs )

4 months ago

on Tuesday, January 28th 2025, 6:30:00 pm
87.94%
Financial Progress

36th Expenditure
of ₹ 147527 (1.48 Lacs ) done.
Cummulative ₹ 249.69Lacs ( against 283.93Lacs )

3 months ago

on Tuesday, February 25th 2025, 6:30:00 pm
88.16%
Financial Progress

37th Expenditure
of ₹ 62000 (0.62 Lacs ) done.
Cummulative ₹ 250.31Lacs ( against 283.93Lacs )

a month ago

on Sunday, March 30th 2025, 6:30:00 pm
90.26%
Financial Progress

38th Expenditure
of ₹ 597178 (5.97 Lacs ) done.
Cummulative ₹ 256.28Lacs ( against 283.93Lacs )