9 years ago

on Tuesday, September 20th 2016, 6:30:00 pm
Work Sanctioned
widening of existing single lane road to 2 lane with paved shoulder configuration from km 235.00 to km 268.00 oh NH 58 including 560m marine drive viaduct portion near bypass in the state of uttarakhand under EPC mode

7 years ago

on Tuesday, March 26th 2019
<span class="4">Picture Id: doc245</span>
PWD Uttarakahnd
Photo (ID 245) from Site Received
Foundation Viaduct

7 years ago

on Saturday, March 30th 2019
<span class="4">Picture Id: doc269</span>
PWD Uttarakahnd
Photo (ID 269) from Site Received
Minor Bridge at Malakhunti

6 years ago

on Tuesday, April 30th 2019
<span class="4">Picture Id: doc272</span>
PWD Uttarakahnd
Photo (ID 272) from Site Received
Bitumen Content Test By ME Rajesh Yadav

6 years ago

on Tuesday, April 30th 2019
<span class="4">Picture Id: doc271</span>
PWD Uttarakahnd
Photo (ID 271) from Site Received
Viaduct A1 Casting in Progress

6 years ago

on Thursday, May 9th 2019
<span class="4">Picture Id: doc273</span>
PWD Uttarakahnd
Photo (ID 273) from Site Received
Water Sprinkling. Photo Collected By Sanjay Garg RE

6 years ago

on Wednesday, May 15th 2019
<span class="4">Picture Id: doc274</span>
PWD Uttarakahnd
Photo (ID 274) from Site Received
Minor Bridge Reinforcement Work Complete Photo Collected by Satweer Singh Bridge Engineer

6 years ago

on Friday, May 17th 2019
<span class="4">Picture Id: doc275</span>
PWD Uttarakahnd
Photo (ID 275) from Site Received
Slab Casting in Progress at Minor Bridge

5 years ago

on Friday, October 30th 2020
PWD Uttarakahnd
Photo (ID 270) from Site Received
Viaduct work in Progress

5 years ago

on Saturday, October 31st 2020
PWD Uttarakahnd
Photo (ID 277) from Site Received
viaduct part2

5 years ago

on Tuesday, March 30th 2021, 6:30:00 pm
60.98%
Financial Progress

1st Expenditure
of ₹ 1513672851 (15136.73 Lacs ) done.
Cummulative ₹ 15136.73Lacs ( against 24822Lacs )

4 years ago

on Tuesday, June 29th 2021, 6:30:00 pm
65.09%
Financial Progress

2nd Expenditure
of ₹ 101990704 (1019.91 Lacs ) done.
Cummulative ₹ 16156.64Lacs ( against 24822Lacs )

4 years ago

on Wednesday, July 14th 2021, 6:30:00 pm
95%

Physical Progress
Physical Progress Reported at 1st time

4 years ago

on Tuesday, September 21st 2021
<span class="4">Picture Id: doc353</span>
PWD Uttarakahnd
Photo (ID 353) from Site Received
560 m Viaduct structure work completed bearing coat left.

4 years ago

on Tuesday, September 21st 2021
<span class="4">Picture Id: doc354</span>
PWD Uttarakahnd
Photo (ID 354) from Site Received
Km 249.6 (goolar bridge) work completed

4 years ago

on Saturday, October 9th 2021, 8:29:28 am
<span class="4">Picture Id:2330</span>
PWD Uttarakahnd
Photo (ID 2330) from Site Received
Uploader : Bhrigunath Dwivedi, Executive Engineer Civil ,TD Rishikesh
Landmark : Km 252.8
Remark : Viaduct

4 years ago

on Saturday, October 9th 2021, 8:45:26 am
<span class="4">Picture Id:2331</span>
PWD Uttarakahnd
Photo (ID 2331) from Site Received
Uploader : Bhrigunath Dwivedi, Executive Engineer Civil ,TD Rishikesh
Landmark : Km252.8
Remark : Viaduct bridge work

4 years ago

on Friday, April 1st 2022, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

3 years ago

on Saturday, April 30th 2022, 6:46:52 am
<span class="4">Picture Id:5471</span>
PWD Uttarakahnd
Photo (ID 5471) from Site Received
Uploader : Mahabir Lal, Additional Assistant Engineer Civil ,NH Div Dehradun
Landmark : 222+700
Remark : Construction of Breast Wall

2 years ago

on Sunday, September 17th 2023, 2:15:28 pm
<span class="4">Picture Id: doc242</span>
PWD Uttarakahnd
Photo (ID 242) from Site Received
RVNL bridge of 90M span at byasi completed. black toping at final finishing in progress. target date proposed for opening of traffic is 30.08.21

2 years ago

on Sunday, September 17th 2023, 2:15:28 pm
<span class="4">Picture Id: doc241</span>
PWD Uttarakahnd
Photo (ID 241) from Site Received
completed road work at km 248.8.

2 years ago

on Sunday, September 17th 2023, 2:15:28 pm
<span class="4">Picture Id: doc240</span>
PWD Uttarakahnd
Photo (ID 240) from Site Received
over head sign board fixed at km 235.65

2 years ago

on Sunday, September 17th 2023, 2:15:28 pm
<span class="4">Picture Id: doc239</span>
PWD Uttarakahnd
Photo (ID 239) from Site Received
560M viaduct at km 252.807 to 253.367. structure work completed, testing after completion in process

6 months ago

on Sunday, March 30th 2025, 6:30:00 pm
96.89%
Financial Progress

3rd Expenditure
of ₹ 789453684 (7894.54 Lacs ) done.
Cummulative ₹ 24051.17Lacs ( against 24822Lacs )