on Thursday, September 15th 2016, 6:30:00 pm
Work Sanctioned
reconstruction with geometric improvement to 2 lane with paved shoulder from km 268.00 to km 300 of NH 58 ( length 29.915)
on Friday, September 16th 2016, 3:45:18 am
Technical Sanction
of ₹ 20034 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. Job No.58-UR-2016-17-476 dated 16.09.16
on Tuesday, March 30th 2021, 6:30:00 pm
69.84%
Financial Progress
1st Expenditure
of ₹ 1399082995 (13990.83 Lacs ) done.
Cummulative ₹ 13990.83Lacs ( against 20034Lacs )
on Thursday, April 29th 2021, 6:30:00 pm
72.14%
Financial Progress
2nd Expenditure
of ₹ 46146963 (461.47 Lacs ) done.
Cummulative ₹ 14452.30Lacs ( against 20034Lacs )
on Sunday, June 27th 2021, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, July 14th 2021, 6:30:00 pm
92.59%
Physical Progress
Physical Progress Reported at 2nd time
on Friday, July 30th 2021, 6:30:00 pm
73.75%
Financial Progress
3rd Expenditure
of ₹ 32233496 (322.33 Lacs ) done.
Cummulative ₹ 14774.63Lacs ( against 20034Lacs )
on Tuesday, August 3rd 2021, 6:30:00 pm
75.30%
Financial Progress
4th Expenditure
of ₹ 31048325 (310.48 Lacs ) done.
Cummulative ₹ 15085.12Lacs ( against 20034Lacs )
on Monday, August 16th 2021, 11:31:59 pm
PWD UttarakahndPhoto (ID 856) from Site Received
Uploader : Bhrigunath Dwivedi, Executive Engineer Civil ,TD Rishikesh
Landmark : Km284.1 teendhara
Remark : Road work completed,black spot rectified under all weather project
on Monday, August 16th 2021, 11:37:26 pm
PWD UttarakahndPhoto (ID 858) from Site Received
Uploader : Bhrigunath Dwivedi, Executive Engineer Civil ,TD Rishikesh
Landmark : Km282.1
Remark : Work completed. safety, signages, drain,super elevation etc ensured
on Monday, August 16th 2021, 11:46:31 pm
PWD UttarakahndPhoto (ID 862) from Site Received
Uploader : Bhrigunath Dwivedi, Executive Engineer Civil ,TD Rishikesh
Landmark : Km 267.9
Remark : Removal of slip and restoration work in progress. rock fall prone areas, proposed for special treatment
on Tuesday, August 17th 2021, 12:07:48 am
PWD UttarakahndPhoto (ID 864) from Site Received
Uploader : Bhrigunath Dwivedi, Executive Engineer Civil ,TD Rishikesh
Landmark : Km266.4
Remark : Restoration of R/W in progress damaged due to land slide . Cronic land slide zone
on Wednesday, September 22nd 2021, 12:37:31 am
PWD UttarakahndPhoto (ID 1536) from Site Received
Uploader : Vikas Kashyap, JE Civil (Samvida) ,NH Div Srinagar
Landmark : 290+600 Shiv Murti pant gown
Remark :
Slip Removal in progress
on Wednesday, September 22nd 2021, 12:51:32 am
PWD UttarakahndPhoto (ID 1540) from Site Received
Uploader : Vikas Kashyap, JE Civil (Samvida) ,NH Div Srinagar
Landmark : 284+250 teen Dhara
Remark :
Slip has been removed from the road
on Wednesday, September 22nd 2021, 1:18:55 am
PWD UttarakahndPhoto (ID 1542) from Site Received
Uploader : Vikas Kashyap, JE Civil (Samvida) ,NH Div Srinagar
Landmark : 277+410 hot mix plant
Remark : Slip has been removed from the road
on Wednesday, September 22nd 2021, 4:28:09 am
PWD UttarakahndPhoto (ID 1549) from Site Received
Uploader : Vikas Kashyap, JE Civil (Samvida) ,NH Div Srinagar
Landmark : 272+890 soad Pani
Remark : Slip Removal in progress
on Wednesday, September 22nd 2021, 5:36:56 am
PWD UttarakahndPhoto (ID 1550) from Site Received
Uploader : Vikas Kashyap, JE Civil (Samvida) ,NH Div Srinagar
Landmark : 286+820 bharpur
Remark : Slip Removal in progress
on Wednesday, September 22nd 2021, 5:47:59 am
PWD UttarakahndPhoto (ID 1551) from Site Received
Uploader : Vikas Kashyap, JE Civil (Samvida) ,NH Div Srinagar
Landmark : 291+880
Remark : Slip Removal in progress
on Friday, September 24th 2021, 12:56:36 am
PWD UttarakahndPhoto (ID 1583) from Site Received
Uploader : Vikas Kashyap, JE Civil (Samvida) ,NH Div Srinagar
Landmark : 289+650
Remark :
Slip Removal in progress
on Friday, September 24th 2021, 1:49:23 am
PWD UttarakahndPhoto (ID 1587) from Site Received
Uploader : Vikas Kashyap, JE Civil (Samvida) ,NH Div Srinagar
Landmark : 270+200
Remark : Slip removal in Progress
on Friday, April 1st 2022, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time