Work Sanctioned
चारधाम परियोजना के अन्तर्गत रा0मा0 सं0 107 के कि0मी0 57.975 से 68.600 (डिजाइन चैनेज 63.700 से 73.600) में मार्ग चौड़ीकरण एवं सुदृढ़ीकरण का कार्य।

9 years ago

on Monday, August 22nd 2016, 9:04:58 am

Technical Sanction
of ₹ 9557 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. NH-109-UR-2016-17-472

4 years ago

on Tuesday, March 30th 2021, 6:30:00 pm
42.49%
Financial Progress

1st Expenditure
of ₹ 406095577 (4060.96 Lacs ) done.
Cummulative ₹ 4060.96Lacs ( against 9557Lacs )

4 years ago

on Wednesday, May 12th 2021, 6:30:00 pm
46.63%
Financial Progress

2nd Expenditure
of ₹ 39503347 (395.03 Lacs ) done.
Cummulative ₹ 4455.99Lacs ( against 9557Lacs )

4 years ago

on Wednesday, July 14th 2021, 6:30:00 pm
48.87%
Financial Progress

3rd Expenditure
of ₹ 21413470 (214.13 Lacs ) done.
Cummulative ₹ 4670.12Lacs ( against 9557Lacs )

4 years ago

on Monday, July 26th 2021, 6:30:00 pm
74.07%

Physical Progress
Physical Progress Reported at 1st time

4 years ago

on Friday, July 30th 2021, 6:30:00 pm
78.14%

Physical Progress
Physical Progress Reported at 2nd time

4 years ago

on Tuesday, August 17th 2021, 2:37:52 am
<span class="4">Picture Id:914</span>
PWD Uttarakahnd
Photo (ID 914) from Site Received
Uploader : Lokesh Kumar, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 70.450
Remark : Installing crash barrier

4 years ago

on Tuesday, August 17th 2021, 6:30:00 pm
50.88%
Financial Progress

4th Expenditure
of ₹ 19239881 (192.40 Lacs ) done.
Cummulative ₹ 4862.52Lacs ( against 9557Lacs )

4 years ago

on Tuesday, August 24th 2021, 2:27:51 am
<span class="4">Picture Id:2058</span>
PWD Uttarakahnd
Photo (ID 2058) from Site Received
Uploader : Kumari Vandita, Assistant Engineer Civil ,NH Div Rudraprayag
Landmark : 69.170
Remark : Excavation for R/w.

4 years ago

on Monday, September 20th 2021, 6:30:00 pm
55.48%
Financial Progress

5th Expenditure
of ₹ 43934997 (439.35 Lacs ) done.
Cummulative ₹ 5301.87Lacs ( against 9557Lacs )

4 years ago

on Wednesday, September 29th 2021, 6:30:00 pm
82.53%

Physical Progress
Physical Progress Reported at 3rd time

3 years ago

on Thursday, December 2nd 2021, 6:30:00 pm
84%

Physical Progress
Physical Progress Reported at 4th time

3 years ago

on Thursday, December 23rd 2021, 6:30:00 pm
58.12%
Financial Progress

6th Expenditure
of ₹ 25232391 (252.32 Lacs ) done.
Cummulative ₹ 5554.20Lacs ( against 9557Lacs )

3 years ago

on Wednesday, January 19th 2022, 6:30:00 pm
85%

Physical Progress
Physical Progress Reported at 5th time

3 years ago

on Wednesday, February 16th 2022, 6:30:00 pm
87%

Physical Progress
Physical Progress Reported at 6th time

3 years ago

on Thursday, March 31st 2022, 6:30:00 pm
85.68%

Physical Progress
Physical Progress Reported at 7th time

3 years ago

on Monday, May 9th 2022, 6:30:00 pm
58.77%
Financial Progress

7th Expenditure
of ₹ 6274009 (62.74 Lacs ) done.
Cummulative ₹ 5616.94Lacs ( against 9557Lacs )

3 years ago

on Tuesday, June 14th 2022, 6:30:00 pm
60.14%
Financial Progress

8th Expenditure
of ₹ 13026853 (130.27 Lacs ) done.
Cummulative ₹ 5747.21Lacs ( against 9557Lacs )

3 years ago

on Wednesday, June 29th 2022, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 8th time

3 years ago

on Wednesday, June 29th 2022, 6:30:00 pm
62.61%
Financial Progress

9th Expenditure
of ₹ 23627527 (236.28 Lacs ) done.
Cummulative ₹ 5983.48Lacs ( against 9557Lacs )

3 years ago

on Wednesday, October 19th 2022, 6:30:00 pm
64.68%
Financial Progress

10th Expenditure
of ₹ 19795999 (197.96 Lacs ) done.
Cummulative ₹ 6181.44Lacs ( against 9557Lacs )

2 years ago

on Monday, December 5th 2022, 6:30:00 pm
93.96%

Physical Progress
Physical Progress Reported at 9th time

2 years ago

on Tuesday, October 17th 2023, 6:30:00 pm
65.65%
Financial Progress

11th Expenditure
of ₹ 9311256 (93.11 Lacs ) done.
Cummulative ₹ 6274.55Lacs ( against 9557Lacs )

2 years ago

on Thursday, November 9th 2023, 6:30:00 pm
95.94%

Physical Progress
Physical Progress Reported at 10th time

2 years ago

on Thursday, November 9th 2023, 6:30:00 pm
66.78%
Financial Progress

12th Expenditure
of ₹ 10782668 (107.83 Lacs ) done.
Cummulative ₹ 6382.38Lacs ( against 9557Lacs )

a year ago

on Monday, February 12th 2024, 6:30:00 pm
97%

Physical Progress
Physical Progress Reported at 11th time

a year ago

on Wednesday, March 6th 2024, 6:30:00 pm
68.13%
Financial Progress

13th Expenditure
of ₹ 12900725 (129.01 Lacs ) done.
Cummulative ₹ 6511.39Lacs ( against 9557Lacs )

a year ago

on Wednesday, March 27th 2024, 6:30:00 pm
98%

Physical Progress
Physical Progress Reported at 12th time