Refresh data
on Thursday, November 17th 2022, 6:30:00 pm
Work Sanctioned
श्री बद्रीनाथ धाम में मास्टर प्लान के अन्तर्गत Temple Precinct निर्माण हेतु मन्दिर परिसर के आस-पास भवनो का ध्वस्तीकरण का कार्य।
on Monday, November 21st 2022, 6:30:00 pm
Technical Sanction
of ₹ 136.35 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. अधीक्षण अभियन्ता कार्यालय 7वाॅ वृत्त गोपेश्वर के पत्रांक-5921/544 यातायात-7/2022 Dt-22.11.2022
on Tuesday, January 10th 2023, 6:30:00 pm
11.75%
Financial Progress
1st Expenditure
of ₹ 1602381 (16.02 Lacs ) done.
Cummulative ₹ 16.02Lacs ( against 136.35Lacs )
on Sunday, January 22nd 2023, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Monday, January 23rd 2023, 6:30:00 pm
23.63%
Financial Progress
2nd Expenditure
of ₹ 1619798 (16.20 Lacs ) done.
Cummulative ₹ 32.22Lacs ( against 136.35Lacs )
on Wednesday, April 12th 2023, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, April 18th 2023, 6:30:00 pm
45%
Physical Progress
Physical Progress Reported at 3rd time
on Wednesday, April 19th 2023, 6:30:00 pm
39.47%
Financial Progress
3rd Expenditure
of ₹ 2159730 (21.60 Lacs ) done.
Cummulative ₹ 53.82Lacs ( against 136.35Lacs )
on Monday, September 4th 2023, 6:30:00 pm
47%
Physical Progress
Physical Progress Reported at 4th time
on Wednesday, October 4th 2023, 6:30:00 pm
48%
Physical Progress
Physical Progress Reported at 5th time
on Saturday, December 30th 2023, 6:30:00 pm
48.31%
Financial Progress
4th Expenditure
of ₹ 1205550 (12.06 Lacs ) done.
Cummulative ₹ 65.87Lacs ( against 136.35Lacs )
on Saturday, March 30th 2024, 6:30:00 pm
54.27%
Financial Progress
5th Expenditure
of ₹ 812541 (8.13 Lacs ) done.
Cummulative ₹ 74.00Lacs ( against 136.35Lacs )
on Wednesday, May 28th 2025, 6:30:00 pm
70%
Physical Progress
Physical Progress Reported at 6th time