on Thursday, October 13th 2022, 6:30:00 pm
Work Sanctioned
श्री बद्रीनाथ धाम में सी0एस0आर0 मद के अन्तर्गत श्री बद्रीनाथ धाम परिक्षेत्रान्तर्गत देवदर्शनी स्थल का निर्माण कार्य।
on Thursday, May 4th 2023, 9:29:00 am
Technical Sanction
of ₹ 1355.8 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 3491/07(221) yata-pauri/2021
on Friday, September 29th 2023, 6:30:00 pm
3.37%
Financial Progress
1st Expenditure
of ₹ 4572750 (45.73 Lacs ) done.
Cummulative ₹ 45.73Lacs ( against 1355.8Lacs )
on Friday, September 29th 2023, 6:30:00 pm
3.55%
Financial Progress
2nd Expenditure
of ₹ 236000 (2.36 Lacs ) done.
Cummulative ₹ 48.09Lacs ( against 1355.8Lacs )
on Wednesday, October 4th 2023, 6:30:00 pm
3%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, November 29th 2023, 6:30:00 pm
4.04%
Financial Progress
3rd Expenditure
of ₹ 671432 (6.71 Lacs ) done.
Cummulative ₹ 54.80Lacs ( against 1355.8Lacs )
on Saturday, December 30th 2023, 6:30:00 pm
10.35%
Financial Progress
4th Expenditure
of ₹ 8554449 (85.54 Lacs ) done.
Cummulative ₹ 140.35Lacs ( against 1355.8Lacs )
on Friday, February 23rd 2024, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 2nd time
on Monday, July 1st 2024, 6:30:00 pm
17%
Physical Progress
Physical Progress Reported at 3rd time
on Wednesday, October 30th 2024, 6:30:00 pm
15.93%
Financial Progress
5th Expenditure
of ₹ 7563146 (75.63 Lacs ) done.
Cummulative ₹ 215.98Lacs ( against 1355.8Lacs )
on Friday, November 29th 2024, 6:30:00 pm
55%
Physical Progress
Physical Progress Reported at 4th time
on Wednesday, May 21st 2025, 6:30:00 pm
58%
Physical Progress
Physical Progress Reported at 5th time