Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पिथौरागढ के विधानसभा क्षेत्र डीडीहाट में बुगाछीना धौनखोला रसैपाटा मोटर मार्ग का नव निर्माण ।
on Wednesday, December 14th 2022, 6:30:00 pm
49.44%
Financial Progress
1st Expenditure
of ₹ 4702355 (47.02 Lacs ) done.
Cummulative ₹ 47.02Lacs ( against 95.12Lacs )
on Monday, January 30th 2023, 6:30:00 pm
49.95%
Financial Progress
2nd Expenditure
of ₹ 49077 (0.49 Lacs ) done.
Cummulative ₹ 47.51Lacs ( against 95.12Lacs )
on Wednesday, November 29th 2023, 6:30:00 pm
52.52%
Financial Progress
3rd Expenditure
of ₹ 244260 (2.44 Lacs ) done.
Cummulative ₹ 49.96Lacs ( against 95.12Lacs )
on Wednesday, February 28th 2024, 6:30:00 pm
52.63%
Financial Progress
4th Expenditure
of ₹ 10152 (0.10 Lacs ) done.
Cummulative ₹ 50.06Lacs ( against 95.12Lacs )
on Tuesday, March 19th 2024, 6:30:00 pm
54.50%
Financial Progress
5th Expenditure
of ₹ 177952 (1.78 Lacs ) done.
Cummulative ₹ 51.84Lacs ( against 95.12Lacs )
on Tuesday, September 10th 2024, 6:30:00 pm
79.50%
Financial Progress
6th Expenditure
of ₹ 2378608 (23.79 Lacs ) done.
Cummulative ₹ 75.62Lacs ( against 95.12Lacs )
on Wednesday, April 9th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, June 19th 2025, 6:30:00 pm
98.81%
Financial Progress
7th Expenditure
of ₹ 1836085 (18.36 Lacs ) done.
Cummulative ₹ 93.98Lacs ( against 95.12Lacs )