on Thursday, March 30th 2023, 6:30:00 pm
Work Sanctioned
वित्तीय वर्ष 2022-23 में राज्य योजना के अन्तर्गत जनपद पिथौरागढ़ के विधानसभा क्षेत्र डीडीहाट में बांकू पुल से बांकू मोटर मार्ग के किमी0 1 व 2 में सुधारीकरण का कार्य (विस्तृत आगणन)
on Wednesday, October 18th 2023, 6:30:00 pm
0.28%
Financial Progress
1st Expenditure
of ₹ 8305 (0.08 Lacs ) done.
Cummulative ₹ 0.08Lacs ( against 29.6Lacs )
on Saturday, December 16th 2023, 3:40:25 am
PWD UttarakahndPhoto (ID 32399) from Site Received
Uploader : Himanshu Joshi, Junior Engineer Civil ,PD Almora
Landmark : Km 1 drain construction work
Remark : Site visit
on Wednesday, December 20th 2023, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, February 20th 2024, 6:30:00 pm
89.94%
Financial Progress
2nd Expenditure
of ₹ 2654058 (26.54 Lacs ) done.
Cummulative ₹ 26.62Lacs ( against 29.6Lacs )
on Tuesday, April 9th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Saturday, June 29th 2024, 2:50:46 am
PWD UttarakahndPhoto (ID 48685) from Site Received
Uploader : Amir Siddiqui, JE Civil (Samvida) ,CD Ramnagar
Landmark : Ch- 0.050
Remark : Protection work satisfactory
on Tuesday, July 23rd 2024, 6:30:00 pm
91.88%
Financial Progress
3rd Expenditure
of ₹ 57301 (0.57 Lacs ) done.
Cummulative ₹ 27.20Lacs ( against 29.6Lacs )
on Sunday, July 28th 2024, 6:30:00 pm
93.82%
Financial Progress
4th Expenditure
of ₹ 57301 (0.57 Lacs ) done.
Cummulative ₹ 27.77Lacs ( against 29.6Lacs )