a year ago

on Wednesday, June 5th 2024, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा संख्या 400/2023 के अन्तर्गत जनपद पिथौरागढ़ के विधानसभा क्षेत्र डीडीहाट में डिगोटी से घसाड़ मोटर मार्ग का सुधारीकरण व डामरीकरण का कार्य।

a year ago

on Sunday, August 4th 2024, 11:06:23 am
<span class="4">Picture Id:51582</span>
PWD Uttarakahnd
Photo (ID 51582) from Site Received
Uploader : Amir Siddiqui, JE Civil (Samvida) ,CD Ramnagar
Landmark : Ch-2.125
Remark : Retaining wall work satisfactory

a year ago

on Wednesday, August 14th 2024, 6:30:00 pm
2%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Sunday, September 8th 2024, 6:30:00 pm
5%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Friday, September 20th 2024, 6:30:00 pm
12.98%
Financial Progress

1st Expenditure
of ₹ 2297440 (22.97 Lacs ) done.
Cummulative ₹ 22.97Lacs ( against 176.97Lacs )

a year ago

on Sunday, September 29th 2024, 6:30:00 pm
25.96%
Financial Progress

2nd Expenditure
of ₹ 2297440 (22.97 Lacs ) done.
Cummulative ₹ 45.95Lacs ( against 176.97Lacs )

a year ago

on Monday, October 21st 2024, 6:30:00 pm
36.64%
Financial Progress

3rd Expenditure
of ₹ 1889293 (18.89 Lacs ) done.
Cummulative ₹ 64.84Lacs ( against 176.97Lacs )

a year ago

on Friday, October 25th 2024, 6:30:00 pm
15%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Sunday, October 27th 2024, 6:30:00 pm
46.14%
Financial Progress

4th Expenditure
of ₹ 1680480 (16.80 Lacs ) done.
Cummulative ₹ 81.65Lacs ( against 176.97Lacs )

10 months ago

on Sunday, December 1st 2024, 6:30:00 pm
25%

Physical Progress
Physical Progress Reported at 4th time

9 months ago

on Monday, December 9th 2024, 6:30:00 pm
35%

Physical Progress
Physical Progress Reported at 5th time

9 months ago

on Wednesday, December 25th 2024, 6:30:00 pm
69.44%
Financial Progress

5th Expenditure
of ₹ 4123537 (41.24 Lacs ) done.
Cummulative ₹ 122.88Lacs ( against 176.97Lacs )

9 months ago

on Wednesday, December 25th 2024, 6:30:00 pm
91.80%
Financial Progress

6th Expenditure
of ₹ 3958389 (39.58 Lacs ) done.
Cummulative ₹ 162.47Lacs ( against 176.97Lacs )

8 months ago

on Monday, February 3rd 2025, 6:30:00 pm
92.36%
Financial Progress

7th Expenditure
of ₹ 98235 (0.98 Lacs ) done.
Cummulative ₹ 163.45Lacs ( against 176.97Lacs )

7 months ago

on Thursday, February 27th 2025, 6:30:00 pm
92.36%
Financial Progress

8th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 163.45Lacs ( against 176.97Lacs )

7 months ago

on Friday, February 28th 2025, 6:30:00 pm
104.22%
Financial Progress

9th Expenditure
of ₹ 2099293 (20.99 Lacs ) done.
Cummulative ₹ 184.44Lacs ( against 176.97Lacs )

6 months ago

on Tuesday, March 11th 2025, 6:30:00 pm
104.30%
Financial Progress

10th Expenditure
of ₹ 14160 (0.14 Lacs ) done.
Cummulative ₹ 184.58Lacs ( against 176.97Lacs )

6 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
118.74%
Financial Progress

11th Expenditure
of ₹ 2554570 (25.55 Lacs ) done.
Cummulative ₹ 210.13Lacs ( against 176.97Lacs )

6 months ago

on Wednesday, March 26th 2025, 6:30:00 pm
74.10%
Financial Progress

12th Expenditure
of ₹ -7900000 (-79.00 Lacs ) done.
Cummulative ₹ 131.13Lacs ( against 176.97Lacs )

6 months ago

on Saturday, March 29th 2025, 6:30:00 pm
74.15%
Financial Progress

13th Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 131.23Lacs ( against 176.97Lacs )

6 months ago

on Monday, April 7th 2025, 6:30:00 pm
65%

Physical Progress
Physical Progress Reported at 6th time

4 months ago

on Wednesday, May 14th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 7th time

3 months ago

on Thursday, June 26th 2025, 6:30:00 pm
85.19%
Financial Progress

14th Expenditure
of ₹ 1953549 (19.54 Lacs ) done.
Cummulative ₹ 150.76Lacs ( against 176.97Lacs )

2 months ago

on Monday, July 21st 2025, 6:30:00 pm
93.72%
Financial Progress

15th Expenditure
of ₹ 1509437 (15.09 Lacs ) done.
Cummulative ₹ 165.86Lacs ( against 176.97Lacs )

a month ago

on Sunday, August 24th 2025, 6:30:00 pm
93.90%
Financial Progress

16th Expenditure
of ₹ 31000 (0.31 Lacs ) done.
Cummulative ₹ 166.17Lacs ( against 176.97Lacs )