Refresh data
on Thursday, February 28th 2013, 6:30:00 pm
0.09%
Financial Progress
1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 115.52Lacs )
on Thursday, March 21st 2013, 6:30:00 pm
Work Sanctioned
जनपद चम्पावत के विधानसभा क्षेत्र लोहाघाट में जी0आई0सी0 लोहाघाट से राईकोट मरोड़ाखान मोटर मार्ग का पुनः निर्माण एवं सुधार कार्य
on Friday, May 31st 2013, 6:30:00 pm
0.81%
Financial Progress
2nd Expenditure
of ₹ 83000 (0.83 Lacs ) done.
Cummulative ₹ 0.93Lacs ( against 115.52Lacs )
on Monday, September 23rd 2013, 6:30:00 pm
Technical Sanction
of ₹ 115.52 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 5627/759C-03/2013
on Thursday, October 31st 2013, 6:30:00 pm
2.55%
Financial Progress
3rd Expenditure
of ₹ 202000 (2.02 Lacs ) done.
Cummulative ₹ 2.95Lacs ( against 115.52Lacs )
on Friday, February 28th 2014, 6:30:00 pm
18.91%
Financial Progress
4th Expenditure
of ₹ 1889277 (18.89 Lacs ) done.
Cummulative ₹ 21.84Lacs ( against 115.52Lacs )
on Sunday, August 31st 2014, 6:30:00 pm
19.00%
Financial Progress
5th Expenditure
of ₹ 11141 (0.11 Lacs ) done.
Cummulative ₹ 21.95Lacs ( against 115.52Lacs )
on Friday, October 31st 2014, 6:30:00 pm
35.85%
Financial Progress
6th Expenditure
of ₹ 1945877 (19.46 Lacs ) done.
Cummulative ₹ 41.41Lacs ( against 115.52Lacs )
on Sunday, November 30th 2014, 6:30:00 pm
36.30%
Financial Progress
7th Expenditure
of ₹ 52400 (0.52 Lacs ) done.
Cummulative ₹ 41.94Lacs ( against 115.52Lacs )
on Wednesday, December 31st 2014, 6:30:00 pm
36.33%
Financial Progress
8th Expenditure
of ₹ 3000 (0.03 Lacs ) done.
Cummulative ₹ 41.97Lacs ( against 115.52Lacs )
on Saturday, January 31st 2015, 6:30:00 pm
64.58%
Financial Progress
9th Expenditure
of ₹ 3263519 (32.64 Lacs ) done.
Cummulative ₹ 74.60Lacs ( against 115.52Lacs )
on Thursday, April 30th 2015, 6:30:00 pm
78.33%
Financial Progress
10th Expenditure
of ₹ 1588894 (15.89 Lacs ) done.
Cummulative ₹ 90.49Lacs ( against 115.52Lacs )
on Friday, July 31st 2015, 6:30:00 pm
86.52%
Financial Progress
11th Expenditure
of ₹ 945738 (9.46 Lacs ) done.
Cummulative ₹ 99.95Lacs ( against 115.52Lacs )
on Monday, August 31st 2015, 6:30:00 pm
99.42%
Financial Progress
12th Expenditure
of ₹ 1490276 (14.90 Lacs ) done.
Cummulative ₹ 114.85Lacs ( against 115.52Lacs )
on Monday, February 29th 2016, 6:30:00 pm
99.16%
Financial Progress
13th Expenditure
of ₹ -30643 (-0.31 Lacs ) done.
Cummulative ₹ 114.54Lacs ( against 115.52Lacs )
on Sunday, July 31st 2016, 6:30:00 pm
99.20%
Financial Progress
14th Expenditure
of ₹ 5000 (0.05 Lacs ) done.
Cummulative ₹ 114.59Lacs ( against 115.52Lacs )
on Saturday, December 31st 2016, 6:30:00 pm
99.20%
Financial Progress
15th Expenditure
of ₹ 471 (0.00 Lacs ) done.
Cummulative ₹ 114.60Lacs ( against 115.52Lacs )
on Saturday, May 28th 2022, 3:50:33 am
PWD UttarakahndPhoto (ID 5706) from Site Received
Uploader : Rajendra Giri, Assistant Engineer Civil ,CD Nainital
Landmark : NH link
Remark : P C.work is in progress