on Tuesday, June 8th 2021, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद चम्पावत के विधानसभा क्षेत्र लोहाघाट के अन्तर्गत पाटी छत्तरद्यर गूम मोटर मार्ग के चै0 0.750 से 3.000 तक मोटर मार्ग का पुनः निर्माण व सुधारीकरण का कार्य।
on Saturday, August 28th 2021, 5:17:28 am
Technical Sanction
of ₹ 113.68 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 3372/232C-03/2021
on Thursday, May 5th 2022, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, August 2nd 2022, 1:14:41 am
PWD UttarakahndPhoto (ID 6991) from Site Received
Uploader : Shivakar Chaurasiya, Assistant Engineer Civil ,CD Lohaghat
Landmark : Chainage 1.100 CHARARDAYAR
Remark : INTER COAT COMPLETED
on Tuesday, August 2nd 2022, 1:26:15 am
PWD UttarakahndPhoto (ID 6992) from Site Received
Uploader : Shivakar Chaurasiya, Assistant Engineer Civil ,CD Lohaghat
Landmark : Chainage 2.200km near Dhura
Remark : Soling coat completed collection of intercoat
on Friday, September 2nd 2022, 1:58:27 am
PWD UttarakahndPhoto (ID 7671) from Site Received
Uploader : Shivakar Chaurasiya, Assistant Engineer Civil ,CD Lohaghat
Landmark : Chainage 1.200 NEAR DHURA TOK
Remark : Inter coat work in progress
on Thursday, September 29th 2022, 6:30:00 pm
13.06%
Financial Progress
1st Expenditure
of ₹ 1500000 (15.00 Lacs ) done.
Cummulative ₹ 15.00Lacs ( against 114.87Lacs )
on Sunday, October 30th 2022, 6:30:00 pm
26.71%
Financial Progress
2nd Expenditure
of ₹ 1568000 (15.68 Lacs ) done.
Cummulative ₹ 30.68Lacs ( against 114.87Lacs )
on Monday, January 2nd 2023, 6:30:00 pm
65%
Physical Progress
Physical Progress Reported at 2nd time
on Monday, January 30th 2023, 6:30:00 pm
35.75%
Financial Progress
3rd Expenditure
of ₹ 1039069 (10.39 Lacs ) done.
Cummulative ₹ 41.07Lacs ( against 114.87Lacs )
on Monday, February 27th 2023, 6:30:00 pm
36.06%
Financial Progress
5th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 41.42Lacs ( against 114.87Lacs )
on Monday, February 27th 2023, 6:30:00 pm
36.06%
Financial Progress
4th Expenditure
of ₹ 35326 (0.35 Lacs ) done.
Cummulative ₹ 41.42Lacs ( against 114.87Lacs )
on Thursday, March 30th 2023, 6:30:00 pm
49.32%
Financial Progress
6th Expenditure
of ₹ 1522758 (15.23 Lacs ) done.
Cummulative ₹ 56.65Lacs ( against 114.87Lacs )
on Tuesday, April 18th 2023, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 3rd time
on Friday, June 2nd 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 4th time
on Sunday, June 18th 2023, 1:19:53 am
PWD UttarakahndPhoto (ID 21389) from Site Received
Uploader : Shivakar Chaurasiya, Assistant Engineer Civil ,CD Lohaghat
Landmark : nirasan bhawan paati
Remark : PC thickness checking by ce sir
on Sunday, June 18th 2023, 1:27:40 am
PWD UttarakahndPhoto (ID 21390) from Site Received
Uploader : Shivakar Chaurasiya, Assistant Engineer Civil ,CD Lohaghat
Landmark : near pwd guest house
Remark : WBM THICKNESS CHECKING BY CE SIR
on Sunday, June 18th 2023, 1:30:39 am
PWD UttarakahndPhoto (ID 21392) from Site Received
Uploader : Shivakar Chaurasiya, Assistant Engineer Civil ,CD Lohaghat
Landmark : 1.300 n
Remark : wbm thickness checking by ce sir
on Thursday, June 29th 2023, 6:30:00 pm
75.57%
Financial Progress
7th Expenditure
of ₹ 3015064 (30.15 Lacs ) done.
Cummulative ₹ 86.80Lacs ( against 114.87Lacs )
on Wednesday, August 30th 2023, 6:30:00 pm
79.19%
Financial Progress
8th Expenditure
of ₹ 416514 (4.17 Lacs ) done.
Cummulative ₹ 90.97Lacs ( against 114.87Lacs )
on Monday, October 30th 2023, 6:30:00 pm
80.27%
Financial Progress
9th Expenditure
of ₹ 124350 (1.24 Lacs ) done.
Cummulative ₹ 92.21Lacs ( against 114.87Lacs )
on Saturday, December 30th 2023, 6:30:00 pm
80.80%
Financial Progress
10th Expenditure
of ₹ 60214 (0.60 Lacs ) done.
Cummulative ₹ 92.81Lacs ( against 114.87Lacs )
on Wednesday, February 21st 2024, 6:30:00 pm
93.07%
Financial Progress
11th Expenditure
of ₹ 1409587 (14.10 Lacs ) done.
Cummulative ₹ 106.91Lacs ( against 114.87Lacs )
on Wednesday, March 27th 2024, 6:30:00 pm
94.08%
Financial Progress
12th Expenditure
of ₹ 116293 (1.16 Lacs ) done.
Cummulative ₹ 108.07Lacs ( against 114.87Lacs )