on Wednesday, January 31st 2024, 6:30:00 pm
Work Sanctioned
माननीय मुख्यमंत्री घोषणा संख्या 132/2023 के अन्तर्गत जनपद चम्पावत के विधानसभा क्षेत्र - लोहाघाट में लोहाघाट - पंचेश्वर मोटर मार्ग के खीडी गांव से धौनी शिलिंग मोटर मार्ग में पुनःनिर्माण एवं सुधारीकरण का कार्य।

a year ago

on Friday, March 29th 2024, 6:30:00 pm
0.02%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 482.88Lacs )

a year ago

on Tuesday, June 25th 2024, 6:30:00 pm
5%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Monday, July 1st 2024, 10:33:24 am
<span class="4">Picture Id:49745</span>
PWD Uttarakahnd
Photo (ID 49745) from Site Received
Uploader : Suraj Shah, JE Civil (Samvida) ,CD Lohaghat
Landmark : 0.250
Remark : Defect cutting work in progress

a year ago

on Monday, July 1st 2024, 10:37:49 am
<span class="4">Picture Id:49750</span>
PWD Uttarakahnd
Photo (ID 49750) from Site Received
Uploader : Suraj Shah, JE Civil (Samvida) ,CD Lohaghat
Landmark : 0.350
Remark : Defect cutting work in progress

a year ago

on Monday, July 1st 2024, 10:40:41 am
<span class="4">Picture Id:49753</span>
PWD Uttarakahnd
Photo (ID 49753) from Site Received
Uploader : Suraj Shah, JE Civil (Samvida) ,CD Lohaghat
Landmark : 0.700
Remark : Defect cutting work in progress

a year ago

on Monday, July 1st 2024, 10:45:14 am
<span class="4">Picture Id:49763</span>
PWD Uttarakahnd
Photo (ID 49763) from Site Received
Uploader : Suraj Shah, JE Civil (Samvida) ,CD Lohaghat
Landmark : 1.100
Remark : Defect cutting in progress

a year ago

on Tuesday, August 20th 2024, 6:30:00 pm
6.68%
Financial Progress

2nd Expenditure
of ₹ 3213958 (32.14 Lacs ) done.
Cummulative ₹ 32.24Lacs ( against 482.88Lacs )

a year ago

on Thursday, August 22nd 2024, 6:30:00 pm
6.68%
Financial Progress

3rd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 32.24Lacs ( against 482.88Lacs )

a year ago

on Tuesday, September 3rd 2024, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Sunday, October 27th 2024, 6:30:00 pm
6.68%
Financial Progress

4th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 32.24Lacs ( against 482.88Lacs )

a year ago

on Sunday, October 27th 2024, 6:30:00 pm
20%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Monday, October 28th 2024, 6:30:00 pm
15.02%
Financial Progress

5th Expenditure
of ₹ 4030349 (40.30 Lacs ) done.
Cummulative ₹ 72.54Lacs ( against 482.88Lacs )

10 months ago

on Sunday, November 17th 2024, 6:30:00 pm
15.06%
Financial Progress

6th Expenditure
of ₹ 17700 (0.18 Lacs ) done.
Cummulative ₹ 72.72Lacs ( against 482.88Lacs )

9 months ago

on Tuesday, December 10th 2024, 6:30:00 pm
15.06%
Financial Progress

7th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 72.72Lacs ( against 482.88Lacs )

9 months ago

on Monday, December 16th 2024, 6:30:00 pm
17.99%
Financial Progress

8th Expenditure
of ₹ 1414315 (14.14 Lacs ) done.
Cummulative ₹ 86.86Lacs ( against 482.88Lacs )

9 months ago

on Thursday, December 19th 2024, 6:30:00 pm
17.99%
Financial Progress

9th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 86.86Lacs ( against 482.88Lacs )

9 months ago

on Thursday, December 26th 2024, 6:30:00 pm
31.74%
Financial Progress

10th Expenditure
of ₹ 6640493 (66.40 Lacs ) done.
Cummulative ₹ 153.27Lacs ( against 482.88Lacs )

9 months ago

on Saturday, December 28th 2024, 6:30:00 pm
31.74%
Financial Progress

11th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 153.27Lacs ( against 482.88Lacs )

9 months ago

on Sunday, December 29th 2024, 6:30:00 pm
39.92%
Financial Progress

12th Expenditure
of ₹ 3950442 (39.50 Lacs ) done.
Cummulative ₹ 192.77Lacs ( against 482.88Lacs )

7 months ago

on Tuesday, February 11th 2025, 6:30:00 pm
40.69%
Financial Progress

13th Expenditure
of ₹ 371558 (3.72 Lacs ) done.
Cummulative ₹ 196.49Lacs ( against 482.88Lacs )

7 months ago

on Tuesday, March 4th 2025, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 4th time

6 months ago

on Tuesday, March 11th 2025, 6:30:00 pm
52.40%
Financial Progress

14th Expenditure
of ₹ 5652221 (56.52 Lacs ) done.
Cummulative ₹ 253.01Lacs ( against 482.88Lacs )

6 months ago

on Monday, March 17th 2025, 6:30:00 pm
57.08%
Financial Progress

15th Expenditure
of ₹ 2263763 (22.64 Lacs ) done.
Cummulative ₹ 275.65Lacs ( against 482.88Lacs )

4 months ago

on Thursday, May 29th 2025, 6:30:00 pm
61.18%
Financial Progress

16th Expenditure
of ₹ 1978757 (19.79 Lacs ) done.
Cummulative ₹ 295.44Lacs ( against 482.88Lacs )

3 months ago

on Saturday, June 28th 2025, 6:30:00 pm
61.18%
Financial Progress

17th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 295.44Lacs ( against 482.88Lacs )

3 months ago

on Sunday, June 29th 2025, 6:30:00 pm
73.55%
Financial Progress

18th Expenditure
of ₹ 5974002 (59.74 Lacs ) done.
Cummulative ₹ 355.18Lacs ( against 482.88Lacs )

3 months ago

on Thursday, July 3rd 2025, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 5th time

2 months ago

on Friday, July 18th 2025, 6:30:00 pm
74.07%
Financial Progress

19th Expenditure
of ₹ 250000 (2.50 Lacs ) done.
Cummulative ₹ 357.68Lacs ( against 482.88Lacs )