Refresh data
Refresh data

10 months ago

on Tuesday, November 5th 2024, 6:30:00 pm
Work Sanctioned
सडक सुरक्षा के अन्तर्गत सूखीढांग-धूरा-रीठासाहिब मोटर मार्ग(राज्य मार्ग-109) के किमी00.000 से 20.000 में आवशेष लम्बाई में तक क्रैश बैरियर लगाने का कार्य।

5 months ago

on Sunday, March 30th 2025, 6:30:00 pm
41.35%
Financial Progress

1st Expenditure
of ₹ 17970242 (179.70 Lacs ) done.
Cummulative ₹ 179.70Lacs ( against 434.55Lacs )

5 months ago

on Monday, April 7th 2025, 6:30:00 pm
40%

Physical Progress
Physical Progress Reported at 1st time

3 months ago

on Friday, May 30th 2025, 6:30:00 pm
65.53%
Financial Progress

2nd Expenditure
of ₹ 10504384 (105.04 Lacs ) done.
Cummulative ₹ 284.75Lacs ( against 434.55Lacs )

2 months ago

on Monday, June 30th 2025, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 2nd time

7 days ago

on Saturday, August 30th 2025, 6:30:00 pm
73.04%
Financial Progress

3rd Expenditure
of ₹ 3263284 (32.63 Lacs ) done.
Cummulative ₹ 317.38Lacs ( against 434.55Lacs )

5 days ago

on Monday, September 1st 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time
Loading...

AI layer

AI Road
AI Bridge
5000 km
3000 mi
Unavailable
refresh data by PWD Uttarakhand Engineeres | View code by HandsOnDataViz with Leaflet | © OpenStreetMap contributors