Work Sanctioned
सडक सुरक्षा के अन्तर्गत सूखीढांग-धूरा-रीठासाहिब मोटर मार्ग(राज्य मार्ग-109) के किमी00.000 से 20.000 में आवशेष लम्बाई में तक क्रैश बैरियर लगाने का कार्य।
on Sunday, March 30th 2025, 6:30:00 pm
41.35%
Financial Progress
1st Expenditure
of ₹ 17970242 (179.70 Lacs ) done.
Cummulative ₹ 179.70Lacs ( against 434.55Lacs )
on Monday, April 7th 2025, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 1st time
on Friday, May 30th 2025, 6:30:00 pm
65.53%
Financial Progress
2nd Expenditure
of ₹ 10504384 (105.04 Lacs ) done.
Cummulative ₹ 284.75Lacs ( against 434.55Lacs )
on Monday, June 30th 2025, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 2nd time
on Saturday, August 30th 2025, 6:30:00 pm
73.04%
Financial Progress
3rd Expenditure
of ₹ 3263284 (32.63 Lacs ) done.
Cummulative ₹ 317.38Lacs ( against 434.55Lacs )
on Monday, September 1st 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time