17 years ago

on Thursday, July 24th 2008, 6:30:00 pm
Work Sanctioned
जनपद अल्मोड़ा में क्वारब से कोसी तक (कोसी नदी के किनारे) बाईपास मोटर मार्ग का निर्माण

16 years ago

on Saturday, February 28th 2009, 6:30:00 pm
0.02%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 525Lacs )

16 years ago

on Tuesday, June 30th 2009, 6:30:00 pm
0.09%
Financial Progress

2nd Expenditure
of ₹ 35000 (0.35 Lacs ) done.
Cummulative ₹ 0.45Lacs ( against 525Lacs )

16 years ago

on Friday, July 31st 2009, 6:30:00 pm
0.09%
Financial Progress

3rd Expenditure
of ₹ 1000 (0.01 Lacs ) done.
Cummulative ₹ 0.46Lacs ( against 525Lacs )

15 years ago

on Sunday, January 31st 2010, 6:30:00 pm
0.11%
Financial Progress

4th Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.56Lacs ( against 525Lacs )

15 years ago

on Sunday, February 28th 2010, 6:30:00 pm
0.17%
Financial Progress

5th Expenditure
of ₹ 31000 (0.31 Lacs ) done.
Cummulative ₹ 0.87Lacs ( against 525Lacs )

15 years ago

on Friday, April 30th 2010, 6:30:00 pm
0.19%
Financial Progress

6th Expenditure
of ₹ 14000 (0.14 Lacs ) done.
Cummulative ₹ 1.01Lacs ( against 525Lacs )

15 years ago

on Monday, May 31st 2010, 6:30:00 pm
0.20%
Financial Progress

7th Expenditure
of ₹ 5000 (0.05 Lacs ) done.
Cummulative ₹ 1.06Lacs ( against 525Lacs )

15 years ago

on Wednesday, June 30th 2010, 6:30:00 pm
0.21%
Financial Progress

8th Expenditure
of ₹ 5000 (0.05 Lacs ) done.
Cummulative ₹ 1.11Lacs ( against 525Lacs )

15 years ago

on Sunday, October 31st 2010, 6:30:00 pm
0.22%
Financial Progress

9th Expenditure
of ₹ 5000 (0.05 Lacs ) done.
Cummulative ₹ 1.16Lacs ( against 525Lacs )

9 years ago

on Friday, March 4th 2016, 6:30:00 pm

Technical Sanction
of ₹ 427.98 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1005(1)/101Yata-Ku/2015

9 years ago

on Saturday, April 30th 2016, 6:30:00 pm
7.49%
Financial Progress

10th Expenditure
of ₹ 3816041 (38.16 Lacs ) done.
Cummulative ₹ 39.32Lacs ( against 525Lacs )

9 years ago

on Thursday, June 30th 2016, 6:30:00 pm
7.64%
Financial Progress

11th Expenditure
of ₹ 80947 (0.81 Lacs ) done.
Cummulative ₹ 40.13Lacs ( against 525Lacs )

9 years ago

on Sunday, July 31st 2016, 6:30:00 pm
24.79%
Financial Progress

12th Expenditure
of ₹ 9000024 (90.00 Lacs ) done.
Cummulative ₹ 130.13Lacs ( against 525Lacs )

9 years ago

on Wednesday, August 31st 2016, 6:30:00 pm
24.82%
Financial Progress

13th Expenditure
of ₹ 19978 (0.20 Lacs ) done.
Cummulative ₹ 130.33Lacs ( against 525Lacs )

9 years ago

on Friday, September 30th 2016, 6:30:00 pm
25.62%
Financial Progress

14th Expenditure
of ₹ 417130 (4.17 Lacs ) done.
Cummulative ₹ 134.50Lacs ( against 525Lacs )

9 years ago

on Monday, October 31st 2016, 6:30:00 pm
25.66%
Financial Progress

15th Expenditure
of ₹ 21000 (0.21 Lacs ) done.
Cummulative ₹ 134.71Lacs ( against 525Lacs )

8 years ago

on Saturday, December 31st 2016, 6:30:00 pm
25.82%
Financial Progress

16th Expenditure
of ₹ 86562 (0.87 Lacs ) done.
Cummulative ₹ 135.58Lacs ( against 525Lacs )

8 years ago

on Tuesday, February 28th 2017, 6:30:00 pm
25.85%
Financial Progress

17th Expenditure
of ₹ 11195 (0.11 Lacs ) done.
Cummulative ₹ 135.69Lacs ( against 525Lacs )

8 years ago

on Sunday, April 30th 2017, 6:30:00 pm
36.81%
Financial Progress

18th Expenditure
of ₹ 5755312 (57.55 Lacs ) done.
Cummulative ₹ 193.24Lacs ( against 525Lacs )

8 years ago

on Monday, July 31st 2017, 6:30:00 pm
48.24%
Financial Progress

19th Expenditure
of ₹ 6000000 (60.00 Lacs ) done.
Cummulative ₹ 253.24Lacs ( against 525Lacs )

7 years ago

on Wednesday, January 31st 2018, 6:30:00 pm
61.46%
Financial Progress

20th Expenditure
of ₹ 6941009 (69.41 Lacs ) done.
Cummulative ₹ 322.65Lacs ( against 525Lacs )

6 years ago

on Friday, November 30th 2018, 6:30:00 pm
61.59%
Financial Progress

21st Expenditure
of ₹ 69112 (0.69 Lacs ) done.
Cummulative ₹ 323.34Lacs ( against 525Lacs )

6 years ago

on Thursday, February 28th 2019, 6:30:00 pm
79.83%
Financial Progress

22nd Expenditure
of ₹ 9574808 (95.75 Lacs ) done.
Cummulative ₹ 419.09Lacs ( against 525Lacs )

6 years ago

on Monday, September 30th 2019, 6:30:00 pm
79.85%
Financial Progress

23rd Expenditure
of ₹ 12285 (0.12 Lacs ) done.
Cummulative ₹ 419.21Lacs ( against 525Lacs )

5 years ago

on Tuesday, June 30th 2020, 6:30:00 pm
79.88%
Financial Progress

24th Expenditure
of ₹ 16400 (0.16 Lacs ) done.
Cummulative ₹ 419.38Lacs ( against 525Lacs )

5 years ago

on Monday, October 19th 2020, 6:30:00 pm

Technical Sanction
of ₹ 97.02 Lacs

2nd Technical Sanction of Work after survey,detailed design and analysis by Latter No. 6432/Yata-A/2020

4 years ago

on Thursday, December 31st 2020, 6:30:00 pm
80.55%
Financial Progress

25th Expenditure
of ₹ 351050 (3.51 Lacs ) done.
Cummulative ₹ 422.89Lacs ( against 525Lacs )

4 years ago

on Wednesday, September 29th 2021, 6:30:00 pm
80.64%
Financial Progress

26th Expenditure
of ₹ 47269 (0.47 Lacs ) done.
Cummulative ₹ 423.36Lacs ( against 525Lacs )

3 years ago

on Wednesday, August 31st 2022, 6:30:00 pm
84.32%
Financial Progress

27th Expenditure
of ₹ 1931170 (19.31 Lacs ) done.
Cummulative ₹ 442.67Lacs ( against 525Lacs )

3 years ago

on Thursday, September 8th 2022, 4:39:24 am
<span class="4">Picture Id:7841</span>
PWD Uttarakahnd
Photo (ID 7841) from Site Received
Uploader : Kamal Goyal, Assistant Engineer Civil ,PD Almora
Landmark : 5/23-24
Remark : Checking by SE Almora sir

3 years ago

on Wednesday, November 16th 2022, 4:30:07 am
<span class="4">Picture Id:9377</span>
PWD Uttarakahnd
Photo (ID 9377) from Site Received
Uploader : Prakash Chandra Pant, Additional Assistant Engineer Civil ,PD Rudrapur
Landmark : Km 05
Remark : Foundation of Box Culvert

2 years ago

on Friday, December 9th 2022, 5:46:45 am
<span class="4">Picture Id:13789</span>
PWD Uttarakahnd
Photo (ID 13789) from Site Received
Uploader : Prakash Chandra Pant, Additional Assistant Engineer Civil ,PD Rudrapur
Landmark : X Sec 3/21-3/22
Remark : Levelling for Box Culvert

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
94.02%
Financial Progress

28th Expenditure
of ₹ 5090856 (50.91 Lacs ) done.
Cummulative ₹ 493.58Lacs ( against 525Lacs )

2 years ago

on Wednesday, May 10th 2023, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Wednesday, June 14th 2023, 3:26:59 am
<span class="4">Picture Id:21113</span>
PWD Uttarakahnd
Photo (ID 21113) from Site Received
Uploader : Prakash Chandra Pant, Additional Assistant Engineer Civil ,PD Rudrapur
Landmark : 0.400
Remark : Motor Road

2 years ago

on Wednesday, June 14th 2023, 3:32:45 am
<span class="4">Picture Id:21115</span>
PWD Uttarakahnd
Photo (ID 21115) from Site Received
Uploader : Prakash Chandra Pant, Additional Assistant Engineer Civil ,PD Rudrapur
Landmark : Ch 1.200
Remark : Motor Road

2 years ago

on Wednesday, June 14th 2023, 3:43:40 am
<span class="4">Picture Id:21117</span>
PWD Uttarakahnd
Photo (ID 21117) from Site Received
Uploader : Prakash Chandra Pant, Additional Assistant Engineer Civil ,PD Rudrapur
Landmark : Ch. 4.240
Remark : Box Culvert

2 years ago

on Thursday, August 17th 2023, 6:30:00 pm
94.18%
Financial Progress

29th Expenditure
of ₹ 88410 (0.88 Lacs ) done.
Cummulative ₹ 494.47Lacs ( against 525Lacs )

2 years ago

on Wednesday, August 30th 2023, 6:30:00 pm
94.35%
Financial Progress

30th Expenditure
of ₹ 88410 (0.88 Lacs ) done.
Cummulative ₹ 495.35Lacs ( against 525Lacs )

2 years ago

on Tuesday, September 12th 2023, 6:30:00 pm
94.84%
Financial Progress

31st Expenditure
of ₹ 257779 (2.58 Lacs ) done.
Cummulative ₹ 497.93Lacs ( against 525Lacs )

2 years ago

on Tuesday, September 12th 2023, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Tuesday, September 19th 2023, 6:30:00 pm
96.86%
Financial Progress

32nd Expenditure
of ₹ 1059678 (10.60 Lacs ) done.
Cummulative ₹ 508.52Lacs ( against 525Lacs )

a year ago

on Wednesday, November 29th 2023, 6:30:00 pm
96.86%
Financial Progress

33rd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 508.52Lacs ( against 525Lacs )

a year ago

on Tuesday, March 19th 2024, 6:30:00 pm
96.86%
Financial Progress

34th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 508.52Lacs ( against 525Lacs )

a year ago

on Monday, March 25th 2024, 6:30:00 pm
96.86%
Financial Progress

36th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 508.52Lacs ( against 525Lacs )

a year ago

on Monday, March 25th 2024, 6:30:00 pm
96.86%
Financial Progress

35th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 508.52Lacs ( against 525Lacs )

a year ago

on Tuesday, March 26th 2024, 6:30:00 pm
97.19%
Financial Progress

38th Expenditure
of ₹ 173984 (1.74 Lacs ) done.
Cummulative ₹ 510.26Lacs ( against 525Lacs )

a year ago

on Tuesday, March 26th 2024, 6:30:00 pm
96.86%
Financial Progress

37th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 508.52Lacs ( against 525Lacs )

9 months ago

on Wednesday, August 21st 2024, 6:30:00 pm
97.36%
Financial Progress

39th Expenditure
of ₹ 89658 (0.90 Lacs ) done.
Cummulative ₹ 511.16Lacs ( against 525Lacs )

4 months ago

on Sunday, January 26th 2025, 6:30:00 pm
97.39%
Financial Progress

40th Expenditure
of ₹ 16116 (0.16 Lacs ) done.
Cummulative ₹ 511.32Lacs ( against 525Lacs )

2 months ago

on Tuesday, March 25th 2025, 6:30:00 pm
98.39%
Financial Progress

41st Expenditure
of ₹ 520956 (5.21 Lacs ) done.
Cummulative ₹ 516.53Lacs ( against 525Lacs )

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable