Work Sanctioned
अल्मोड़ा-शहरफाटक मोटर मार्ग के लमगड़ा नाम स्थान पर पक्की नाली का निर्माण
on Friday, September 6th 2019, 6:30:00 pm
Technical Sanction
of ₹ 7 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1514/11C
on Saturday, February 29th 2020, 6:30:00 pm
10.03%
Financial Progress
1st Expenditure
of ₹ 150502 (1.51 Lacs ) done.
Cummulative ₹ 1.51Lacs ( against 15Lacs )
on Wednesday, September 30th 2020, 6:30:00 pm
20.66%
Financial Progress
2nd Expenditure
of ₹ 159455 (1.59 Lacs ) done.
Cummulative ₹ 3.10Lacs ( against 15Lacs )
on Saturday, October 31st 2020, 6:30:00 pm
46.78%
Financial Progress
3rd Expenditure
of ₹ 391721 (3.92 Lacs ) done.
Cummulative ₹ 7.02Lacs ( against 15Lacs )
on Friday, November 27th 2020, 6:30:00 pm
Technical Sanction
of ₹ 8 Lacs
2nd Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2265/Ji Yo
on Sunday, February 28th 2021, 6:30:00 pm
58.37%
Financial Progress
4th Expenditure
of ₹ 173918 (1.74 Lacs ) done.
Cummulative ₹ 8.76Lacs ( against 15Lacs )
on Friday, October 29th 2021, 6:30:00 pm
90.25%
Financial Progress
5th Expenditure
of ₹ 478207 (4.78 Lacs ) done.
Cummulative ₹ 13.54Lacs ( against 15Lacs )
on Monday, May 30th 2022, 6:30:00 pm
93.37%
Financial Progress
6th Expenditure
of ₹ 46781 (0.47 Lacs ) done.
Cummulative ₹ 14.01Lacs ( against 15Lacs )
on Wednesday, August 31st 2022, 6:30:00 pm
94.65%
Financial Progress
7th Expenditure
of ₹ 19155 (0.19 Lacs ) done.
Cummulative ₹ 14.20Lacs ( against 15Lacs )
on Saturday, October 29th 2022, 6:30:00 pm
95.51%
Financial Progress
8th Expenditure
of ₹ 12936 (0.13 Lacs ) done.
Cummulative ₹ 14.33Lacs ( against 15Lacs )
on Thursday, July 4th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, March 30th 2025, 6:30:00 pm
99.25%
Financial Progress
9th Expenditure
of ₹ 56000 (0.56 Lacs ) done.
Cummulative ₹ 14.89Lacs ( against 15Lacs )