on Sunday, March 23rd 2008, 6:30:00 pm
Work Sanctioned
नौला रेखलधार (मटेला) मोटर मार्ग
on Saturday, February 28th 2009, 6:30:00 pm
0.09%
Financial Progress
1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 117Lacs )
on Sunday, October 4th 2020, 6:30:00 pm
Technical Sanction
of ₹ 98.54 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2491/217C-01/2020
on Wednesday, February 16th 2022, 4:48:12 am
PWD UttarakahndPhoto (ID 4336) from Site Received
Uploader : Prakash Chandra Pant, Additional Assistant Engineer Civil ,PD Rudrapur
Landmark : Start point 0/0
Remark : New construction work under progress..
on Wednesday, March 30th 2022, 6:30:00 pm
3.86%
Financial Progress
2nd Expenditure
of ₹ 442120 (4.42 Lacs ) done.
Cummulative ₹ 4.52Lacs ( against 117Lacs )
on Thursday, March 31st 2022, 9:58:50 am
PWD UttarakahndPhoto (ID 5463) from Site Received
Uploader : Prakash Chandra Pant, Additional Assistant Engineer Civil ,PD Almora
Landmark : X Sec- 4/22
Remark : Road surface Levelling and superelevation
on Monday, June 6th 2022, 3:09:49 am
PWD UttarakahndPhoto (ID 5811) from Site Received
Uploader : Prakash Chandra Pant, Additional Assistant Engineer Civil ,PD Rudrapur
Landmark : X Sec- 4/35
Remark : Construction of 1 MTR. Span culvert
on Monday, June 6th 2022, 3:55:46 am
PWD UttarakahndPhoto (ID 5812) from Site Received
Uploader : Prakash Chandra Pant, Additional Assistant Engineer Civil ,PD Rudrapur
Landmark : X-Sec 4/19
Remark : T/wall of scupper
on Monday, June 20th 2022, 6:19:43 am
PWD UttarakahndPhoto (ID 6442) from Site Received
Uploader : Prakash Chandra Pant, Additional Assistant Engineer Civil ,PD Rudrapur
Landmark : X Sec 4/19
Remark : 1 MTR span culvert
on Sunday, July 31st 2022, 6:30:00 pm
13.69%
Financial Progress
3rd Expenditure
of ₹ 1149493 (11.49 Lacs ) done.
Cummulative ₹ 16.02Lacs ( against 117Lacs )
on Monday, September 26th 2022, 2:58:31 am
PWD UttarakahndPhoto (ID 8147) from Site Received
Uploader : Prakash Chandra Pant, Additional Assistant Engineer Civil ,PD Rudrapur
Landmark : X -Sec 3/38
Remark : Kachcha drain construction
on Monday, November 21st 2022, 5:36:49 am
PWD UttarakahndPhoto (ID 10748) from Site Received
Uploader : Prakash Chandra Pant, Additional Assistant Engineer Civil ,PD Rudrapur
Landmark : X Sec 3/34
Remark : Bed Block casting
on Saturday, December 31st 2022, 6:30:00 pm
18.93%
Financial Progress
4th Expenditure
of ₹ 613722 (6.14 Lacs ) done.
Cummulative ₹ 22.15Lacs ( against 117Lacs )
on Tuesday, February 28th 2023, 6:30:00 pm
39.60%
Financial Progress
5th Expenditure
of ₹ 2417821 (24.18 Lacs ) done.
Cummulative ₹ 46.33Lacs ( against 117Lacs )
on Wednesday, May 10th 2023, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, November 29th 2023, 6:30:00 pm
47.01%
Financial Progress
6th Expenditure
of ₹ 866631 (8.67 Lacs ) done.
Cummulative ₹ 55.00Lacs ( against 117Lacs )
on Sunday, September 29th 2024, 6:30:00 pm
48.40%
Financial Progress
7th Expenditure
of ₹ 163117 (1.63 Lacs ) done.
Cummulative ₹ 56.63Lacs ( against 117Lacs )
on Tuesday, October 29th 2024, 6:30:00 pm
54.30%
Financial Progress
8th Expenditure
of ₹ 690384 (6.90 Lacs ) done.
Cummulative ₹ 63.53Lacs ( against 117Lacs )
on Sunday, December 8th 2024, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 2nd time
on Sunday, February 23rd 2025, 6:30:00 pm
54.53%
Financial Progress
9th Expenditure
of ₹ 27259 (0.27 Lacs ) done.
Cummulative ₹ 63.81Lacs ( against 117Lacs )
on Sunday, February 23rd 2025, 6:30:00 pm
54.84%
Financial Progress
10th Expenditure
of ₹ 36146 (0.36 Lacs ) done.
Cummulative ₹ 64.17Lacs ( against 117Lacs )