Work Sanctioned
मा0 मुख्यमंत्री घोषणा सं0- 108/2019 के अन्तर्गत जनपद ऊधमसिंह नगर के विधानसभा क्षेत्र किच्छा के अन्तर्गत पाहा नहर की कवरिंग कर सड़क का निर्गाण कार्य। (फेज- प्)

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
47.16%
Financial Progress

1st Expenditure
of ₹ 50000000 (500.00 Lacs ) done.
Cummulative ₹ 500.00Lacs ( against 1060.26Lacs )

2 years ago

on Monday, April 10th 2023, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Monday, September 11th 2023, 6:30:00 pm
17%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Friday, September 29th 2023, 6:30:00 pm
56.59%
Financial Progress

2nd Expenditure
of ₹ 10000000 (100.00 Lacs ) done.
Cummulative ₹ 600.00Lacs ( against 1060.26Lacs )

2 years ago

on Thursday, October 12th 2023, 6:30:00 pm
25%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Wednesday, May 1st 2024, 6:30:00 pm
51%

Physical Progress
Physical Progress Reported at 4th time

a year ago

on Saturday, August 3rd 2024, 6:30:00 pm
55%

Physical Progress
Physical Progress Reported at 5th time

a year ago

on Sunday, September 22nd 2024, 6:30:00 pm
56.83%
Financial Progress

3rd Expenditure
of ₹ 249865 (2.50 Lacs ) done.
Cummulative ₹ 602.50Lacs ( against 1060.26Lacs )

a year ago

on Wednesday, October 23rd 2024, 6:30:00 pm
65%

Physical Progress
Physical Progress Reported at 6th time

9 months ago

on Tuesday, December 31st 2024, 6:30:00 pm
75.51%
Financial Progress

4th Expenditure
of ₹ 19805582 (198.06 Lacs ) done.
Cummulative ₹ 800.55Lacs ( against 1060.26Lacs )

5 months ago

on Tuesday, April 8th 2025, 6:30:00 pm
70%

Physical Progress
Physical Progress Reported at 7th time