7 years ago

on Thursday, February 28th 2019, 6:30:00 pm
0.11%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 94.96Lacs )

7 years ago

on Wednesday, March 6th 2019, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद उधमसिंह नगर के विधानसभा क्षेत्र नानकमत्ता के झनकट में इण्डिया ईट भट्टे से पूर्णागिरी काॅलेज होते हुए प्रतापपुर रोड तक मोटर मार्ग का निर्माण कार्य। (दि्वतीय चरण)

6 years ago

on Sunday, April 14th 2019, 6:30:00 pm

Technical Sanction
of ₹ 94.96 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 949/EE

6 years ago

on Sunday, June 30th 2019, 6:30:00 pm
3.51%
Financial Progress

2nd Expenditure
of ₹ 323580 (3.24 Lacs ) done.
Cummulative ₹ 3.34Lacs ( against 94.96Lacs )

5 years ago

on Sunday, February 28th 2021, 6:30:00 pm
33.00%
Financial Progress

3rd Expenditure
of ₹ 2800000 (28.00 Lacs ) done.
Cummulative ₹ 31.34Lacs ( against 94.96Lacs )

3 years ago

on Thursday, June 9th 2022, 5:56:44 am
<span class="4">Picture Id:5927</span>
PWD Uttarakahnd
Photo (ID 5927) from Site Received
Uploader : Girish Chandra Lohani, Additional Assistant Engineer Civil ,CD Khatima
Landmark : Km1.00
Remark : Work completed

3 years ago

on Wednesday, July 6th 2022, 6:30:00 pm
69.27%
Financial Progress

4th Expenditure
of ₹ 3444744 (34.45 Lacs ) done.
Cummulative ₹ 65.78Lacs ( against 94.96Lacs )

3 years ago

on Sunday, August 28th 2022, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Sunday, November 6th 2022, 6:30:00 pm
100.53%
Financial Progress

5th Expenditure
of ₹ 2968000 (29.68 Lacs ) done.
Cummulative ₹ 95.46Lacs ( against 94.96Lacs )