Refresh data
on Thursday, February 16th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद उधमसिंह नगर के विधानसभा क्षेत्र सितारगंज के अन्तर्गत शक्तिफार्म मुख्यमार्ग से राजनगर होते हुए पालनगर में सितारगंज मुख्य मार्ग तक मार्ग का पुनः निर्माण कार्य।
on Wednesday, April 12th 2023, 11:24:59 am
Technical Sanction
of ₹ 36.84 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1241/EE
on Friday, June 16th 2023, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 1st time
on Monday, June 19th 2023, 6:30:00 pm
38.07%
Financial Progress
1st Expenditure
of ₹ 1402411 (14.02 Lacs ) done.
Cummulative ₹ 14.02Lacs ( against 36.84Lacs )
on Thursday, June 29th 2023, 6:30:00 pm
76.14%
Financial Progress
2nd Expenditure
of ₹ 1402411 (14.02 Lacs ) done.
Cummulative ₹ 28.05Lacs ( against 36.84Lacs )
on Monday, September 25th 2023, 6:30:00 pm
98.30%
Financial Progress
3rd Expenditure
of ₹ 816607 (8.17 Lacs ) done.
Cummulative ₹ 36.21Lacs ( against 36.84Lacs )
on Wednesday, September 27th 2023, 6:30:00 pm
127.22%
Financial Progress
4th Expenditure
of ₹ 1065298 (10.65 Lacs ) done.
Cummulative ₹ 46.87Lacs ( against 36.84Lacs )
on Thursday, October 5th 2023, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 2nd time
on Sunday, October 22nd 2023, 1:33:48 am
PWD UttarakahndPhoto (ID 25521) from Site Received
Uploader : Satyapal Singh, Additional Assistant Engineer Civil ,CD Khatima
Landmark : 1.400
Remark : PC Work with HMP plant
on Tuesday, December 5th 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time
on Monday, December 18th 2023, 6:30:00 pm
99.88%
Financial Progress
5th Expenditure
of ₹ -1007085 (-10.07 Lacs ) done.
Cummulative ₹ 36.80Lacs ( against 36.84Lacs )