on Monday, March 20th 2023, 6:30:00 pm
Work Sanctioned
वित्तीय वर्ष 2022-23 में मा0 मुख्यमंत्री घोषणा संख्या 710/2021 के अन्तर्गत जनपद उधमसिंह नगर के विधानसभा क्षेत्र नानकमत्ता के अन्तर्गत साधूनगर से लामाखेड़ा मन्दिर की ओर मार्ग का डामरीकरण का नव निर्माण कार्य।
on Monday, April 24th 2023, 10:08:33 am
Technical Sanction
of ₹ 128.11 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1121/30C-04/2023
on Thursday, June 15th 2023, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, August 10th 2023, 4:46:06 am
PWD UttarakahndPhoto (ID 23521) from Site Received
Uploader : Rizvan, Additional Assistant Engineer Civil ,CD Khatima
Landmark : Chainage 2.000
Remark : Proposed for NABARD 29
on Thursday, August 10th 2023, 4:57:20 am
PWD UttarakahndPhoto (ID 23522) from Site Received
Uploader : Rizvan, Additional Assistant Engineer Civil ,CD Khatima
Landmark : Chainage-0.000
Remark : Proposed for NABARD 29
on Sunday, September 17th 2023, 6:30:00 pm
0.00%
Financial Progress
1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 128.11Lacs )
on Monday, September 18th 2023, 6:30:00 pm
26.96%
Financial Progress
2nd Expenditure
of ₹ 3454072 (34.54 Lacs ) done.
Cummulative ₹ 34.54Lacs ( against 128.11Lacs )
on Tuesday, October 3rd 2023, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 2nd time
on Monday, December 18th 2023, 6:30:00 pm
40.74%
Financial Progress
3rd Expenditure
of ₹ 1765306 (17.65 Lacs ) done.
Cummulative ₹ 52.19Lacs ( against 128.11Lacs )
on Monday, December 18th 2023, 6:30:00 pm
40.74%
Financial Progress
4th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 52.19Lacs ( against 128.11Lacs )
on Tuesday, January 2nd 2024, 6:30:00 pm
35%
Physical Progress
Physical Progress Reported at 3rd time
on Sunday, January 28th 2024, 6:30:00 pm
61.29%
Financial Progress
5th Expenditure
of ₹ 2632109 (26.32 Lacs ) done.
Cummulative ₹ 78.51Lacs ( against 128.11Lacs )
on Monday, February 26th 2024, 6:30:00 pm
77.58%
Financial Progress
6th Expenditure
of ₹ 2086995 (20.87 Lacs ) done.
Cummulative ₹ 99.38Lacs ( against 128.11Lacs )
on Tuesday, March 5th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 4th time
on Tuesday, March 26th 2024, 6:30:00 pm
99.04%
Financial Progress
7th Expenditure
of ₹ 2750165 (27.50 Lacs ) done.
Cummulative ₹ 126.89Lacs ( against 128.11Lacs )