2 years ago

on Monday, March 20th 2023, 6:30:00 pm
Work Sanctioned
वित्तीय वर्ष 2022-23 में मा0 मुख्यमंत्री घोषणा संख्या 710/2021 के अन्तर्गत जनपद उधमसिंह नगर के विधानसभा क्षेत्र नानकमत्ता के अन्तर्गत साधूनगर से लामाखेड़ा मन्दिर की ओर मार्ग का डामरीकरण का नव निर्माण कार्य।

2 years ago

on Monday, April 24th 2023, 10:08:33 am

Technical Sanction
of ₹ 128.11 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1121/30C-04/2023

2 years ago

on Thursday, June 15th 2023, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Thursday, August 10th 2023, 4:46:06 am
<span class="4">Picture Id:23521</span>
PWD Uttarakahnd
Photo (ID 23521) from Site Received
Uploader : Rizvan, Additional Assistant Engineer Civil ,CD Khatima
Landmark : Chainage 2.000
Remark : Proposed for NABARD 29

2 years ago

on Thursday, August 10th 2023, 4:57:20 am
<span class="4">Picture Id:23522</span>
PWD Uttarakahnd
Photo (ID 23522) from Site Received
Uploader : Rizvan, Additional Assistant Engineer Civil ,CD Khatima
Landmark : Chainage-0.000
Remark : Proposed for NABARD 29

a year ago

on Sunday, September 17th 2023, 6:30:00 pm
0.00%
Financial Progress

1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 128.11Lacs )

a year ago

on Monday, September 18th 2023, 6:30:00 pm
26.96%
Financial Progress

2nd Expenditure
of ₹ 3454072 (34.54 Lacs ) done.
Cummulative ₹ 34.54Lacs ( against 128.11Lacs )

a year ago

on Tuesday, October 3rd 2023, 6:30:00 pm
20%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Monday, December 18th 2023, 6:30:00 pm
40.74%
Financial Progress

3rd Expenditure
of ₹ 1765306 (17.65 Lacs ) done.
Cummulative ₹ 52.19Lacs ( against 128.11Lacs )

a year ago

on Monday, December 18th 2023, 6:30:00 pm
40.74%
Financial Progress

4th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 52.19Lacs ( against 128.11Lacs )

a year ago

on Tuesday, January 2nd 2024, 6:30:00 pm
35%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Sunday, January 28th 2024, 6:30:00 pm
61.29%
Financial Progress

5th Expenditure
of ₹ 2632109 (26.32 Lacs ) done.
Cummulative ₹ 78.51Lacs ( against 128.11Lacs )

a year ago

on Monday, February 26th 2024, 6:30:00 pm
77.58%
Financial Progress

6th Expenditure
of ₹ 2086995 (20.87 Lacs ) done.
Cummulative ₹ 99.38Lacs ( against 128.11Lacs )

a year ago

on Tuesday, March 5th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 4th time

a year ago

on Tuesday, March 26th 2024, 6:30:00 pm
99.04%
Financial Progress

7th Expenditure
of ₹ 2750165 (27.50 Lacs ) done.
Cummulative ₹ 126.89Lacs ( against 128.11Lacs )