on Sunday, September 19th 2021, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री जी की घोषणा सं0 477/2018 के अन्र्तगत विधानसभा क्षेत्र गदरपुर में बाजपुर बेरियादौलत मार्ग के किमी0 3 से ब्रिगेडियर फार्म होते हुए शहीद अंग्रेज सिंह की समाधि से कुलवीर सिंह हुडडा फार्म तक मार्ग का पुनः निर्माण कार्य। (तृतीय भाग चै0 9.830 से 12.210)
on Monday, June 20th 2022, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, June 23rd 2022, 6:30:00 pm
58.79%
Financial Progress
1st Expenditure
of ₹ 6244000 (62.44 Lacs ) done.
Cummulative ₹ 62.44Lacs ( against 106.21Lacs )
on Saturday, July 23rd 2022, 5:58:01 am
PWD UttarakahndPhoto (ID 6787) from Site Received
Uploader : Rajesh Paintola, Additional Assistant Engineer Civil ,PD Pithoragarh
Landmark : 1.800
Remark : PC work completed
on Monday, July 25th 2022, 8:58:21 am
PWD UttarakahndPhoto (ID 6933) from Site Received
Uploader : Rajesh Paintola, Additional Assistant Engineer Civil ,PD Pithoragarh
Landmark : 0.00
Remark : PC work completed
on Thursday, July 28th 2022, 10:55:58 am
PWD UttarakahndPhoto (ID 6934) from Site Received
Uploader : Rajesh Paintola, Additional Assistant Engineer Civil ,PD Pithoragarh
Landmark : 0.300
Remark : PC work completed
on Thursday, July 28th 2022, 10:57:46 am
PWD UttarakahndPhoto (ID 6936) from Site Received
Uploader : Rajesh Paintola, Additional Assistant Engineer Civil ,PD Pithoragarh
Landmark : 0.550
Remark : PC work completed
on Thursday, July 28th 2022, 10:59:27 am
PWD UttarakahndPhoto (ID 6937) from Site Received
Uploader : Rajesh Paintola, Additional Assistant Engineer Civil ,PD Pithoragarh
Landmark : 0.800
Remark : PC work completed
on Thursday, July 28th 2022, 11:01:09 am
PWD UttarakahndPhoto (ID 6938) from Site Received
Uploader : Rajesh Paintola, Additional Assistant Engineer Civil ,PD Pithoragarh
Landmark : 1.300
Remark : Pc work completed
on Thursday, July 28th 2022, 11:03:15 am
PWD UttarakahndPhoto (ID 6961) from Site Received
Uploader : Rajesh Paintola, Additional Assistant Engineer Civil ,PD Pithoragarh
Landmark : 1.800
Remark : PC work completed
on Saturday, August 27th 2022, 6:30:00 pm
68.43%
Financial Progress
2nd Expenditure
of ₹ 1023831 (10.24 Lacs ) done.
Cummulative ₹ 72.68Lacs ( against 106.21Lacs )
on Tuesday, March 21st 2023, 6:30:00 pm
75.03%
Financial Progress
3rd Expenditure
of ₹ 701141 (7.01 Lacs ) done.
Cummulative ₹ 79.69Lacs ( against 106.21Lacs )