Work Sanctioned
राज्य योजना के अन्तर्गत जनपद अल्मोड़ा के विधानसभा क्षेत्र जागेश्वर में खेती धूरागांव सेराघाट मोटर मार्ग का पुनःनिर्माण एवं सुधार कार्य।

a year ago

on Friday, March 29th 2024, 6:30:00 pm
0.04%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 280.91Lacs )

a year ago

on Tuesday, April 16th 2024, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Monday, June 17th 2024, 6:30:00 pm
0.35%
Financial Progress

2nd Expenditure
of ₹ 89000 (0.89 Lacs ) done.
Cummulative ₹ 0.99Lacs ( against 280.91Lacs )

a year ago

on Thursday, June 27th 2024, 11:24:56 am
<span class="4">Picture Id:47942</span>
PWD Uttarakahnd
Photo (ID 47942) from Site Received
Uploader : Virendra Kumar, JE Civil (Samvida) ,CD Askote
Landmark : 0.500
Remark : Improvement work

a year ago

on Thursday, June 27th 2024, 11:40:08 am
<span class="4">Picture Id:47959</span>
PWD Uttarakahnd
Photo (ID 47959) from Site Received
Uploader : Virendra Kumar, JE Civil (Samvida) ,CD Askote
Landmark : 1.50
Remark : Improvement work

a year ago

on Thursday, June 27th 2024, 11:59:56 am
<span class="4">Picture Id:47964</span>
PWD Uttarakahnd
Photo (ID 47964) from Site Received
Uploader : Virendra Kumar, JE Civil (Samvida) ,CD Askote
Landmark : 0.600
Remark : Retaining wall

a year ago

on Friday, June 28th 2024, 6:30:00 pm
3.22%
Financial Progress

3rd Expenditure
of ₹ 805894 (8.06 Lacs ) done.
Cummulative ₹ 9.05Lacs ( against 280.91Lacs )

a year ago

on Wednesday, July 24th 2024, 6:30:00 pm
4.13%
Financial Progress

4th Expenditure
of ₹ 255650 (2.56 Lacs ) done.
Cummulative ₹ 11.61Lacs ( against 280.91Lacs )

a year ago

on Thursday, August 1st 2024, 6:30:00 pm
15%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Tuesday, August 27th 2024, 6:30:00 pm
5.54%
Financial Progress

5th Expenditure
of ₹ 395384 (3.95 Lacs ) done.
Cummulative ₹ 15.56Lacs ( against 280.91Lacs )

a year ago

on Thursday, September 26th 2024, 6:30:00 pm
27.04%
Financial Progress

6th Expenditure
of ₹ 6039885 (60.40 Lacs ) done.
Cummulative ₹ 75.96Lacs ( against 280.91Lacs )

a year ago

on Friday, September 27th 2024, 6:30:00 pm
27.04%
Financial Progress

7th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 75.96Lacs ( against 280.91Lacs )

a year ago

on Tuesday, October 15th 2024, 6:30:00 pm
27.08%
Financial Progress

8th Expenditure
of ₹ 10497 (0.10 Lacs ) done.
Cummulative ₹ 76.06Lacs ( against 280.91Lacs )

a year ago

on Wednesday, October 23rd 2024, 6:30:00 pm
38.86%
Financial Progress

9th Expenditure
of ₹ 3309576 (33.10 Lacs ) done.
Cummulative ₹ 109.16Lacs ( against 280.91Lacs )

10 months ago

on Tuesday, November 5th 2024, 6:30:00 pm
55%

Physical Progress
Physical Progress Reported at 3rd time

9 months ago

on Sunday, December 29th 2024, 6:30:00 pm
53.61%
Financial Progress

11th Expenditure
of ₹ 3745075 (37.45 Lacs ) done.
Cummulative ₹ 150.60Lacs ( against 280.91Lacs )

9 months ago

on Sunday, December 29th 2024, 6:30:00 pm
40.28%
Financial Progress

10th Expenditure
of ₹ 398619 (3.99 Lacs ) done.
Cummulative ₹ 113.15Lacs ( against 280.91Lacs )

8 months ago

on Tuesday, January 21st 2025, 6:30:00 pm
53.74%
Financial Progress

12th Expenditure
of ₹ 35920 (0.36 Lacs ) done.
Cummulative ₹ 150.96Lacs ( against 280.91Lacs )

6 months ago

on Tuesday, March 11th 2025, 6:30:00 pm
57.73%
Financial Progress

13th Expenditure
of ₹ 1121081 (11.21 Lacs ) done.
Cummulative ₹ 162.17Lacs ( against 280.91Lacs )

6 months ago

on Thursday, March 20th 2025, 6:30:00 pm
69.13%
Financial Progress

14th Expenditure
of ₹ 3203682 (32.04 Lacs ) done.
Cummulative ₹ 194.20Lacs ( against 280.91Lacs )

5 months ago

on Monday, April 7th 2025, 6:30:00 pm
70%

Physical Progress
Physical Progress Reported at 4th time

3 months ago

on Monday, June 9th 2025, 6:30:00 pm
69.52%
Financial Progress

15th Expenditure
of ₹ 107994 (1.08 Lacs ) done.
Cummulative ₹ 195.28Lacs ( against 280.91Lacs )

3 months ago

on Sunday, June 15th 2025, 6:30:00 pm
83.33%
Financial Progress

16th Expenditure
of ₹ 3880901 (38.81 Lacs ) done.
Cummulative ₹ 234.09Lacs ( against 280.91Lacs )

25 days ago

on Sunday, August 24th 2025, 6:30:00 pm
95.88%
Financial Progress

17th Expenditure
of ₹ 3525840 (35.26 Lacs ) done.
Cummulative ₹ 269.35Lacs ( against 280.91Lacs )