Work Sanctioned
राज्य योजना के अन्तर्गत जनपद उत्तरकाशी के विधानसभा क्षेत्र गंगोत्री के अन्तर्गत के विकासखण्ड भटवाड़ी के अन्तर्गत ग्राम सुनगर के झाया से सुनगर तक मोटर मार्ग का निर्माण कार्य।(प्रथम चरण)
on Thursday, May 7th 2020, 6:30:00 pm
Technical Sanction
of ₹ 46.07 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. EE No 316/1C
on Sunday, June 27th 2021, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, June 30th 2021, 7:49:08 am
PWD UttarakahndPhoto (ID 181) from Site Received
Uploader : Rakesh Singh Negi, Assistant Engineer Civil ,PD Bhatwari
Landmark : Nh34 km64
Remark : Alignment inspection
on Tuesday, June 20th 2023, 6:30:00 pm
0.85%
Financial Progress
1st Expenditure
of ₹ 39294 (0.39 Lacs ) done.
Cummulative ₹ 0.39Lacs ( against 46.07Lacs )
on Tuesday, June 20th 2023, 6:30:00 pm
1.46%
Financial Progress
2nd Expenditure
of ₹ 27900 (0.28 Lacs ) done.
Cummulative ₹ 0.67Lacs ( against 46.07Lacs )
on Tuesday, June 20th 2023, 6:30:00 pm
2.34%
Financial Progress
3rd Expenditure
of ₹ 40604 (0.41 Lacs ) done.
Cummulative ₹ 1.08Lacs ( against 46.07Lacs )
on Thursday, June 29th 2023, 6:30:00 pm
4.68%
Financial Progress
4th Expenditure
of ₹ 107798 (1.08 Lacs ) done.
Cummulative ₹ 2.16Lacs ( against 46.07Lacs )
on Wednesday, November 29th 2023, 6:30:00 pm
2.34%
Financial Progress
5th Expenditure
of ₹ -107798 (-1.08 Lacs ) done.
Cummulative ₹ 1.08Lacs ( against 46.07Lacs )
on Monday, January 15th 2024, 6:30:00 pm
2.93%
Financial Progress
6th Expenditure
of ₹ 27000 (0.27 Lacs ) done.
Cummulative ₹ 1.35Lacs ( against 46.07Lacs )
on Thursday, November 6th 2025, 6:30:00 pm
55%
Physical Progress
Physical Progress Reported at 2nd time