5 years ago

on Tuesday, August 18th 2020, 6:30:00 pm
Work Sanctioned
जनपद उत्तरकाशी मे सामुदायिक मिलन केन्द्र रैथल /ग्रोेथ सेन्टर का निर्माण कार्य।

4 years ago

on Friday, November 6th 2020, 6:30:00 pm

Technical Sanction
of ₹ 49.28 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. EE No-329/1C

4 years ago

on Sunday, February 28th 2021, 6:30:00 pm
31.02%
Financial Progress

1st Expenditure
of ₹ 1528440 (15.28 Lacs ) done.
Cummulative ₹ 15.28Lacs ( against 49.28Lacs )

4 years ago

on Saturday, June 26th 2021, 2:50:23 am
<span class="4">Picture Id:112</span>
PWD Uttarakahnd
Photo (ID 112) from Site Received
Uploader : Rajender Singh Khatri, Assistant Engineer Civil ,ENC office
Landmark : Village Raithal
Remark : Inspection of growth centre at village Raithal

4 years ago

on Sunday, June 27th 2021, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Monday, November 29th 2021, 6:30:00 pm
31.45%
Financial Progress

2nd Expenditure
of ₹ 21599 (0.22 Lacs ) done.
Cummulative ₹ 15.50Lacs ( against 49.28Lacs )

3 years ago

on Sunday, January 30th 2022, 6:30:00 pm
31.52%
Financial Progress

3rd Expenditure
of ₹ 3325 (0.03 Lacs ) done.
Cummulative ₹ 15.53Lacs ( against 49.28Lacs )

3 years ago

on Sunday, February 27th 2022, 6:30:00 pm
31.83%
Financial Progress

4th Expenditure
of ₹ 15000 (0.15 Lacs ) done.
Cummulative ₹ 15.68Lacs ( against 49.28Lacs )

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
93.31%
Financial Progress

5th Expenditure
of ₹ 3029972 (30.30 Lacs ) done.
Cummulative ₹ 45.98Lacs ( against 49.28Lacs )

3 years ago

on Wednesday, June 29th 2022, 6:30:00 pm
93.90%
Financial Progress

6th Expenditure
of ₹ 28969 (0.29 Lacs ) done.
Cummulative ₹ 46.27Lacs ( against 49.28Lacs )

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
94.97%
Financial Progress

7th Expenditure
of ₹ 52643 (0.53 Lacs ) done.
Cummulative ₹ 46.80Lacs ( against 49.28Lacs )

10 months ago

on Monday, May 20th 2024, 6:30:00 pm
95.53%
Financial Progress

8th Expenditure
of ₹ 27900 (0.28 Lacs ) done.
Cummulative ₹ 47.08Lacs ( against 49.28Lacs )

10 months ago

on Monday, May 20th 2024, 6:30:00 pm
95.75%
Financial Progress

9th Expenditure
of ₹ 10793 (0.11 Lacs ) done.
Cummulative ₹ 47.19Lacs ( against 49.28Lacs )

9 months ago

on Monday, June 17th 2024, 6:30:00 pm
95.98%
Financial Progress

10th Expenditure
of ₹ 11186 (0.11 Lacs ) done.
Cummulative ₹ 47.30Lacs ( against 49.28Lacs )