on Thursday, March 9th 2023, 6:30:00 pm
Work Sanctioned
जनपद उत्तरकाशी के विकासखण्ड भटवाड़ी के अन्तर्गत ग्राम भटवाड़ी के ढामक तोक में हैलिपैड विकसित किये जाने का कार्य।
on Monday, June 5th 2023, 6:01:44 am
Technical Sanction
of ₹ 144.65 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 3070/06(31) yata/2023
on Tuesday, September 5th 2023, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, October 17th 2023, 6:30:00 pm
42%
Physical Progress
Physical Progress Reported at 2nd time
on Sunday, November 5th 2023, 6:30:00 pm
55%
Physical Progress
Physical Progress Reported at 3rd time
on Sunday, December 3rd 2023, 6:30:00 pm
65%
Physical Progress
Physical Progress Reported at 4th time
on Saturday, December 9th 2023, 9:46:30 am
PWD UttarakahndPhoto (ID 31668) from Site Received
Uploader : Ashish Singh Panwar, JE Civil (Samvida) ,PD Bhatwari
Landmark : Dhamak
Remark : Leveling of Helipad ground work in progress
on Saturday, December 9th 2023, 9:50:21 am
PWD UttarakahndPhoto (ID 31669) from Site Received
Uploader : Ashish Singh Panwar, JE Civil (Samvida) ,PD Bhatwari
Landmark : Dhamak
Remark : Work in progress
on Sunday, December 10th 2023, 8:18:25 am
PWD UttarakahndPhoto (ID 31724) from Site Received
Uploader : Ashish Singh Panwar, JE Civil (Samvida) ,PD Bhatwari
Landmark : Dhamak
Remark : Wall work almost completed
on Monday, December 18th 2023, 5:35:00 am
PWD UttarakahndPhoto (ID 32566) from Site Received
Uploader : Ashish Singh Panwar, JE Civil (Samvida) ,PD Bhatwari
Landmark : Dhamak
Remark : Leveling work in progress
on Monday, December 18th 2023, 6:30:00 pm
30.99%
Financial Progress
1st Expenditure
of ₹ 4483087 (44.83 Lacs ) done.
Cummulative ₹ 44.83Lacs ( against 144.65Lacs )
on Monday, December 18th 2023, 6:30:00 pm
40.00%
Financial Progress
2nd Expenditure
of ₹ 1302913 (13.03 Lacs ) done.
Cummulative ₹ 57.86Lacs ( against 144.65Lacs )
on Thursday, December 28th 2023, 5:12:49 am
PWD UttarakahndPhoto (ID 33651) from Site Received
Uploader : Ashish Singh Panwar, JE Civil (Samvida) ,PD Bhatwari
Landmark : Dhamak
Remark : Hill side cutting work for helipad base in progress
on Monday, January 22nd 2024, 6:30:00 pm
75%
Physical Progress
Physical Progress Reported at 5th time
on Sunday, March 31st 2024, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 6th time
on Thursday, April 11th 2024, 8:35:15 am
PWD UttarakahndPhoto (ID 37422) from Site Received
Uploader : Ashish Singh Panwar, JE Civil (Samvida) ,PD Bhatwari
Landmark : Dhamak
Remark : Wbm work complete
on Thursday, April 11th 2024, 8:37:03 am
PWD UttarakahndPhoto (ID 37423) from Site Received
Uploader : Ashish Singh Panwar, JE Civil (Samvida) ,PD Bhatwari
Landmark : Dhamak
Remark : Wbm work complete in approch road
on Wednesday, June 12th 2024, 6:30:00 pm
44.20%
Financial Progress
3rd Expenditure
of ₹ 607380 (6.07 Lacs ) done.
Cummulative ₹ 63.93Lacs ( against 144.65Lacs )
on Wednesday, June 19th 2024, 6:30:00 pm
74.16%
Financial Progress
4th Expenditure
of ₹ 4333451 (43.33 Lacs ) done.
Cummulative ₹ 107.27Lacs ( against 144.65Lacs )
on Sunday, July 14th 2024, 7:00:31 am
PWD UttarakahndPhoto (ID 50734) from Site Received
Uploader : Ashish Singh Panwar, JE Civil (Samvida) ,PD Bhatwari
Landmark : Dhamak
Remark : Paint work
on Sunday, July 14th 2024, 7:01:37 am
PWD UttarakahndPhoto (ID 50735) from Site Received
Uploader : Ashish Singh Panwar, JE Civil (Samvida) ,PD Bhatwari
Landmark : Dhamak
Remark : Paint work
on Thursday, August 22nd 2024, 6:30:00 pm
74.17%
Financial Progress
5th Expenditure
of ₹ 2500 (0.03 Lacs ) done.
Cummulative ₹ 107.29Lacs ( against 144.65Lacs )
on Sunday, August 25th 2024, 6:30:00 pm
74.31%
Financial Progress
6th Expenditure
of ₹ 19499 (0.19 Lacs ) done.
Cummulative ₹ 107.49Lacs ( against 144.65Lacs )