on Tuesday, July 26th 2022, 6:30:00 pm
Work Sanctioned
जनपद उत्तरकाशी के विधानसभा पुरोला के विकासखण्ड मोरी में दिनांक 18.08.2019 को आयी प्राकृतिक आपदा के कारण आराकोट क्षेत्र के एस0आर0एच0 आराकोट के पहुंच मार्ग का पुर्ननिर्माण कार्य।
on Tuesday, January 24th 2023, 6:30:00 pm
0.35%
Financial Progress
1st Expenditure
of ₹ 9800 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 28.28Lacs )
on Tuesday, March 21st 2023, 6:30:00 pm
42.74%
Financial Progress
2nd Expenditure
of ₹ 1199000 (11.99 Lacs ) done.
Cummulative ₹ 12.09Lacs ( against 28.28Lacs )
on Wednesday, April 19th 2023, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, September 28th 2023, 6:30:00 pm
70%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, October 24th 2023, 6:30:00 pm
44.51%
Financial Progress
3rd Expenditure
of ₹ 50000 (0.50 Lacs ) done.
Cummulative ₹ 12.59Lacs ( against 28.28Lacs )
on Wednesday, January 3rd 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time
on Tuesday, February 27th 2024, 6:30:00 pm
80.28%
Financial Progress
4th Expenditure
of ₹ 1011653 (10.12 Lacs ) done.
Cummulative ₹ 22.70Lacs ( against 28.28Lacs )
on Thursday, October 24th 2024, 6:30:00 pm
86.93%
Financial Progress
5th Expenditure
of ₹ 188052 (1.88 Lacs ) done.
Cummulative ₹ 24.59Lacs ( against 28.28Lacs )
on Tuesday, November 19th 2024, 6:30:00 pm
88.59%
Financial Progress
6th Expenditure
of ₹ 46850 (0.47 Lacs ) done.
Cummulative ₹ 25.05Lacs ( against 28.28Lacs )
on Thursday, December 19th 2024, 6:30:00 pm
92.19%
Financial Progress
7th Expenditure
of ₹ 101810 (1.02 Lacs ) done.
Cummulative ₹ 26.07Lacs ( against 28.28Lacs )
on Monday, January 20th 2025, 6:30:00 pm
93.38%
Financial Progress
8th Expenditure
of ₹ 33615 (0.34 Lacs ) done.
Cummulative ₹ 26.41Lacs ( against 28.28Lacs )