2 years ago

on Thursday, September 7th 2023, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा सं0 1799ध्2021 के अन्तर्गत जनपद उत्तरकाशी के विधानसभा क्षेत्र पुरोला के विकासखण्ड मोरी के अन्तर्गत देवरा हल्टाडी मोटर मार्ग के कि0मी0 6 से 7 में डामरीकरण कार्य।

2 years ago

on Tuesday, October 10th 2023, 6:55:20 am

Technical Sanction
of ₹ 169.02 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 4517/6c(V)-6/2023-24

2 years ago

on Tuesday, January 23rd 2024, 6:30:00 pm
32.09%
Financial Progress

1st Expenditure
of ₹ 5423261 (54.23 Lacs ) done.
Cummulative ₹ 54.23Lacs ( against 169.02Lacs )

2 years ago

on Monday, February 5th 2024, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Friday, February 23rd 2024, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Thursday, February 29th 2024, 6:30:00 pm
44.65%
Financial Progress

2nd Expenditure
of ₹ 2124000 (21.24 Lacs ) done.
Cummulative ₹ 75.47Lacs ( against 169.02Lacs )

2 years ago

on Thursday, March 21st 2024, 6:30:00 pm
47.91%
Financial Progress

3rd Expenditure
of ₹ 550264 (5.50 Lacs ) done.
Cummulative ₹ 80.98Lacs ( against 169.02Lacs )

2 years ago

on Tuesday, March 26th 2024, 6:30:00 pm
85%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Tuesday, March 26th 2024, 6:30:00 pm
47.91%
Financial Progress

4th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 80.98Lacs ( against 169.02Lacs )

2 years ago

on Wednesday, April 3rd 2024, 6:30:00 pm
95%

Physical Progress
Physical Progress Reported at 4th time

2 years ago

on Thursday, May 9th 2024, 6:30:00 pm
81.54%
Financial Progress

5th Expenditure
of ₹ 5685208 (56.85 Lacs ) done.
Cummulative ₹ 137.83Lacs ( against 169.02Lacs )

a year ago

on Sunday, June 30th 2024, 2:13:09 am
<span class="4">Picture Id:48924</span>
PWD Uttarakahnd
Photo (ID 48924) from Site Received
Uploader : Anita Bhandari, Additional Assistant Engineer Civil ,TD Kirtinagar
Landmark : 5/39 devta haltari road
Remark : Work complete

a year ago

on Sunday, June 30th 2024, 2:18:37 am
<span class="4">Picture Id:48925</span>
PWD Uttarakahnd
Photo (ID 48925) from Site Received
Uploader : Anita Bhandari, Additional Assistant Engineer Civil ,TD Kirtinagar
Landmark : 5/39 devta haltari
Remark : Work complete

a year ago

on Sunday, June 30th 2024, 2:28:39 am
<span class="4">Picture Id:48926</span>
PWD Uttarakahnd
Photo (ID 48926) from Site Received
Uploader : Anita Bhandari, Additional Assistant Engineer Civil ,TD Kirtinagar
Landmark : 5/18 devta haltari road
Remark : Work complete

a year ago

on Friday, July 26th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 5th time

a year ago

on Thursday, August 15th 2024, 6:30:00 pm
82.48%
Financial Progress

6th Expenditure
of ₹ 157530 (1.58 Lacs ) done.
Cummulative ₹ 139.40Lacs ( against 169.02Lacs )

a year ago

on Wednesday, September 25th 2024, 6:30:00 pm
89.34%
Financial Progress

7th Expenditure
of ₹ 1159591 (11.60 Lacs ) done.
Cummulative ₹ 151.00Lacs ( against 169.02Lacs )

a year ago

on Sunday, October 27th 2024, 6:30:00 pm
89.53%
Financial Progress

8th Expenditure
of ₹ 31860 (0.32 Lacs ) done.
Cummulative ₹ 151.32Lacs ( against 169.02Lacs )

a year ago

on Sunday, October 27th 2024, 6:30:00 pm
89.69%
Financial Progress

9th Expenditure
of ₹ 27000 (0.27 Lacs ) done.
Cummulative ₹ 151.59Lacs ( against 169.02Lacs )

10 months ago

on Tuesday, January 7th 2025, 6:30:00 pm
89.95%
Financial Progress

10th Expenditure
of ₹ 44285 (0.44 Lacs ) done.
Cummulative ₹ 152.03Lacs ( against 169.02Lacs )

9 months ago

on Thursday, February 13th 2025, 6:30:00 pm
90.24%
Financial Progress

11th Expenditure
of ₹ 50000 (0.50 Lacs ) done.
Cummulative ₹ 152.53Lacs ( against 169.02Lacs )

9 months ago

on Sunday, February 23rd 2025, 6:30:00 pm
90.48%
Financial Progress

13th Expenditure
of ₹ 25000 (0.25 Lacs ) done.
Cummulative ₹ 152.92Lacs ( against 169.02Lacs )

9 months ago

on Sunday, February 23rd 2025, 6:30:00 pm
90.33%
Financial Progress

12th Expenditure
of ₹ 14500 (0.14 Lacs ) done.
Cummulative ₹ 152.67Lacs ( against 169.02Lacs )

5 months ago

on Thursday, June 26th 2025, 6:30:00 pm
91.97%
Financial Progress

14th Expenditure
of ₹ 251612 (2.52 Lacs ) done.
Cummulative ₹ 155.44Lacs ( against 169.02Lacs )

5 months ago

on Sunday, June 29th 2025, 6:30:00 pm
93.61%
Financial Progress

18th Expenditure
of ₹ 120062 (1.20 Lacs ) done.
Cummulative ₹ 158.23Lacs ( against 169.02Lacs )

5 months ago

on Sunday, June 29th 2025, 6:30:00 pm
92.40%
Financial Progress

15th Expenditure
of ₹ 73478 (0.73 Lacs ) done.
Cummulative ₹ 156.18Lacs ( against 169.02Lacs )

5 months ago

on Sunday, June 29th 2025, 6:30:00 pm
92.79%
Financial Progress

16th Expenditure
of ₹ 66585 (0.67 Lacs ) done.
Cummulative ₹ 156.84Lacs ( against 169.02Lacs )

5 months ago

on Sunday, June 29th 2025, 6:30:00 pm
92.90%
Financial Progress

17th Expenditure
of ₹ 18565 (0.19 Lacs ) done.
Cummulative ₹ 157.03Lacs ( against 169.02Lacs )