Work Sanctioned
मा0 मुख्यमंत्री घोषणा सं0 1470/2021 के अन्तर्गत जनपद उत्तरकाशी के विधानसभा क्षेत्र पुरोला के मोरी नैटवाड सांकरी परिवर्तित समरेखण(वरुणावत) मोटर मार्ग के कि0मी0 10 से पैंसर गांव को जोडने हेतु मोटर मार्ग के कि0मी01 से 4 तक क्षतिग्रस्त भाग का मरम्मत एवं पुनःनिर्माण कार्य।

2 years ago

on Tuesday, October 10th 2023, 6:56:55 am

Technical Sanction
of ₹ 213.74 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 4517/6c(V)-6/2023-24

a year ago

on Wednesday, April 3rd 2024, 6:30:00 pm
5%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Sunday, June 30th 2024, 3:56:02 am
<span class="4">Picture Id:48942</span>
PWD Uttarakahnd
Photo (ID 48942) from Site Received
Uploader : Anita Bhandari, Additional Assistant Engineer Civil ,TD Kirtinagar
Landmark : Km. 0/29 gurari painsar road
Remark : Work is progress

a year ago

on Sunday, June 30th 2024, 4:09:05 am
<span class="4">Picture Id:48945</span>
PWD Uttarakahnd
Photo (ID 48945) from Site Received
Uploader : Anita Bhandari, Additional Assistant Engineer Civil ,TD Kirtinagar
Landmark : Km. 2/24 gurari painsar road
Remark : Work is progress

a year ago

on Tuesday, July 9th 2024, 10:19:06 am
<span class="4">Picture Id:50585</span>
PWD Uttarakahnd
Photo (ID 50585) from Site Received
Uploader : Anita Bhandari, Additional Assistant Engineer Civil ,TD Kirtinagar
Landmark : 2.90Km at painsar Road
Remark : WBM work in progress

a year ago

on Monday, July 22nd 2024, 6:30:00 pm
25%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Thursday, August 15th 2024, 6:30:00 pm
17.48%
Financial Progress

1st Expenditure
of ₹ 3735985 (37.36 Lacs ) done.
Cummulative ₹ 37.36Lacs ( against 213.74Lacs )

a year ago

on Tuesday, September 24th 2024, 6:30:00 pm
17.99%
Financial Progress

2nd Expenditure
of ₹ 108350 (1.08 Lacs ) done.
Cummulative ₹ 38.44Lacs ( against 213.74Lacs )

a year ago

on Sunday, October 27th 2024, 6:30:00 pm
28.71%
Financial Progress

3rd Expenditure
of ₹ 2292331 (22.92 Lacs ) done.
Cummulative ₹ 61.37Lacs ( against 213.74Lacs )

a year ago

on Sunday, October 27th 2024, 6:30:00 pm
40%

Physical Progress
Physical Progress Reported at 3rd time

10 months ago

on Sunday, December 1st 2024, 6:30:00 pm
28.98%
Financial Progress

4th Expenditure
of ₹ 57761 (0.58 Lacs ) done.
Cummulative ₹ 61.94Lacs ( against 213.74Lacs )

9 months ago

on Wednesday, December 4th 2024, 10:21:14 am
<span class="4">Picture Id:60409</span>
PWD Uttarakahnd
Photo (ID 60409) from Site Received
Uploader : Govind Singh Rawat, Assistant Engineer Civil ,CD Purola
Landmark : 1/18
Remark : SE sir visit on pasa pancer mr

9 months ago

on Wednesday, December 4th 2024, 10:42:15 am
<span class="4">Picture Id:60416</span>
PWD Uttarakahnd
Photo (ID 60416) from Site Received
Uploader : Govind Singh Rawat, Assistant Engineer Civil ,CD Purola
Landmark : 2/21
Remark : Ok

9 months ago

on Wednesday, December 4th 2024, 10:43:35 am
<span class="4">Picture Id:60419</span>
PWD Uttarakahnd
Photo (ID 60419) from Site Received
Uploader : Govind Singh Rawat, Assistant Engineer Civil ,CD Purola
Landmark : 2/21
Remark : SE sir visit

9 months ago

on Wednesday, December 4th 2024, 10:47:50 am
<span class="4">Picture Id:60538</span>
PWD Uttarakahnd
Photo (ID 60538) from Site Received
Uploader : Govind Singh Rawat, Assistant Engineer Civil ,CD Purola
Landmark : End point
Remark : SE sir visit

9 months ago

on Monday, December 9th 2024, 6:30:00 pm
43.33%
Financial Progress

5th Expenditure
of ₹ 3066973 (30.67 Lacs ) done.
Cummulative ₹ 92.61Lacs ( against 213.74Lacs )

9 months ago

on Wednesday, December 25th 2024, 6:30:00 pm
53.26%
Financial Progress

6th Expenditure
of ₹ 2121764 (21.22 Lacs ) done.
Cummulative ₹ 113.83Lacs ( against 213.74Lacs )

9 months ago

on Sunday, December 29th 2024, 6:30:00 pm
62.02%
Financial Progress

7th Expenditure
of ₹ 1872896 (18.73 Lacs ) done.
Cummulative ₹ 132.56Lacs ( against 213.74Lacs )

9 months ago

on Thursday, January 2nd 2025, 6:30:00 pm
55%

Physical Progress
Physical Progress Reported at 4th time

8 months ago

on Wednesday, January 15th 2025, 6:30:00 pm
62.07%
Financial Progress

8th Expenditure
of ₹ 9800 (0.10 Lacs ) done.
Cummulative ₹ 132.66Lacs ( against 213.74Lacs )

8 months ago

on Sunday, January 26th 2025, 6:30:00 pm
62.39%
Financial Progress

9th Expenditure
of ₹ 68499 (0.68 Lacs ) done.
Cummulative ₹ 133.34Lacs ( against 213.74Lacs )

7 months ago

on Thursday, February 13th 2025, 6:30:00 pm
62.62%
Financial Progress

10th Expenditure
of ₹ 50000 (0.50 Lacs ) done.
Cummulative ₹ 133.84Lacs ( against 213.74Lacs )

7 months ago

on Sunday, March 2nd 2025, 6:30:00 pm
71.57%
Financial Progress

11th Expenditure
of ₹ 1913356 (19.13 Lacs ) done.
Cummulative ₹ 152.98Lacs ( against 213.74Lacs )

6 months ago

on Tuesday, March 18th 2025, 6:30:00 pm
81.68%
Financial Progress

12th Expenditure
of ₹ 2160155 (21.60 Lacs ) done.
Cummulative ₹ 174.58Lacs ( against 213.74Lacs )

5 months ago

on Thursday, April 3rd 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 5th time

4 months ago

on Friday, May 30th 2025, 6:30:00 pm
82.08%
Financial Progress

13th Expenditure
of ₹ 86037 (0.86 Lacs ) done.
Cummulative ₹ 175.44Lacs ( against 213.74Lacs )

3 months ago

on Monday, June 9th 2025, 6:30:00 pm
91.97%
Financial Progress

14th Expenditure
of ₹ 2113837 (21.14 Lacs ) done.
Cummulative ₹ 196.58Lacs ( against 213.74Lacs )