Work Sanctioned
मा0 मुख्यमंत्री घोषणा सं0 1470/2021 के अन्तर्गत जनपद उत्तरकाशी के विधानसभा क्षेत्र पुरोला के मोरी नैटवाड सांकरी परिवर्तित समरेखण(वरुणावत) मोटर मार्ग के कि0मी0 10 से पैंसर गांव को जोडने हेतु मोटर मार्ग के कि0मी01 से 4 तक क्षतिग्रस्त भाग का मरम्मत एवं पुनःनिर्माण कार्य।
on Tuesday, October 10th 2023, 6:56:55 am
Technical Sanction
of ₹ 213.74 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 4517/6c(V)-6/2023-24
on Wednesday, April 3rd 2024, 6:30:00 pm
5%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, June 30th 2024, 3:56:02 am
PWD UttarakahndPhoto (ID 48942) from Site Received
Uploader : Anita Bhandari, Additional Assistant Engineer Civil ,TD Kirtinagar
Landmark : Km. 0/29 gurari painsar road
Remark : Work is progress
on Sunday, June 30th 2024, 4:09:05 am
PWD UttarakahndPhoto (ID 48945) from Site Received
Uploader : Anita Bhandari, Additional Assistant Engineer Civil ,TD Kirtinagar
Landmark : Km. 2/24 gurari painsar road
Remark : Work is progress
on Tuesday, July 9th 2024, 10:19:06 am
PWD UttarakahndPhoto (ID 50585) from Site Received
Uploader : Anita Bhandari, Additional Assistant Engineer Civil ,TD Kirtinagar
Landmark : 2.90Km at painsar Road
Remark : WBM work in progress
on Monday, July 22nd 2024, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, August 15th 2024, 6:30:00 pm
17.48%
Financial Progress
1st Expenditure
of ₹ 3735985 (37.36 Lacs ) done.
Cummulative ₹ 37.36Lacs ( against 213.74Lacs )
on Tuesday, September 24th 2024, 6:30:00 pm
17.99%
Financial Progress
2nd Expenditure
of ₹ 108350 (1.08 Lacs ) done.
Cummulative ₹ 38.44Lacs ( against 213.74Lacs )
on Sunday, October 27th 2024, 6:30:00 pm
28.71%
Financial Progress
3rd Expenditure
of ₹ 2292331 (22.92 Lacs ) done.
Cummulative ₹ 61.37Lacs ( against 213.74Lacs )
on Sunday, October 27th 2024, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 3rd time
on Sunday, December 1st 2024, 6:30:00 pm
28.98%
Financial Progress
4th Expenditure
of ₹ 57761 (0.58 Lacs ) done.
Cummulative ₹ 61.94Lacs ( against 213.74Lacs )
on Wednesday, December 4th 2024, 10:21:14 am
PWD UttarakahndPhoto (ID 60409) from Site Received
Uploader : Govind Singh Rawat, Assistant Engineer Civil ,CD Purola
Landmark : 1/18
Remark : SE sir visit on pasa pancer mr
on Wednesday, December 4th 2024, 10:42:15 am
PWD UttarakahndPhoto (ID 60416) from Site Received
Uploader : Govind Singh Rawat, Assistant Engineer Civil ,CD Purola
Landmark : 2/21
Remark : Ok
on Wednesday, December 4th 2024, 10:43:35 am
PWD UttarakahndPhoto (ID 60419) from Site Received
Uploader : Govind Singh Rawat, Assistant Engineer Civil ,CD Purola
Landmark : 2/21
Remark : SE sir visit
on Wednesday, December 4th 2024, 10:47:50 am
PWD UttarakahndPhoto (ID 60538) from Site Received
Uploader : Govind Singh Rawat, Assistant Engineer Civil ,CD Purola
Landmark : End point
Remark : SE sir visit
on Monday, December 9th 2024, 6:30:00 pm
43.33%
Financial Progress
5th Expenditure
of ₹ 3066973 (30.67 Lacs ) done.
Cummulative ₹ 92.61Lacs ( against 213.74Lacs )
on Wednesday, December 25th 2024, 6:30:00 pm
53.26%
Financial Progress
6th Expenditure
of ₹ 2121764 (21.22 Lacs ) done.
Cummulative ₹ 113.83Lacs ( against 213.74Lacs )
on Sunday, December 29th 2024, 6:30:00 pm
62.02%
Financial Progress
7th Expenditure
of ₹ 1872896 (18.73 Lacs ) done.
Cummulative ₹ 132.56Lacs ( against 213.74Lacs )
on Thursday, January 2nd 2025, 6:30:00 pm
55%
Physical Progress
Physical Progress Reported at 4th time
on Wednesday, January 15th 2025, 6:30:00 pm
62.07%
Financial Progress
8th Expenditure
of ₹ 9800 (0.10 Lacs ) done.
Cummulative ₹ 132.66Lacs ( against 213.74Lacs )
on Sunday, January 26th 2025, 6:30:00 pm
62.39%
Financial Progress
9th Expenditure
of ₹ 68499 (0.68 Lacs ) done.
Cummulative ₹ 133.34Lacs ( against 213.74Lacs )
on Thursday, February 13th 2025, 6:30:00 pm
62.62%
Financial Progress
10th Expenditure
of ₹ 50000 (0.50 Lacs ) done.
Cummulative ₹ 133.84Lacs ( against 213.74Lacs )
on Sunday, March 2nd 2025, 6:30:00 pm
71.57%
Financial Progress
11th Expenditure
of ₹ 1913356 (19.13 Lacs ) done.
Cummulative ₹ 152.98Lacs ( against 213.74Lacs )
on Tuesday, March 18th 2025, 6:30:00 pm
81.68%
Financial Progress
12th Expenditure
of ₹ 2160155 (21.60 Lacs ) done.
Cummulative ₹ 174.58Lacs ( against 213.74Lacs )
on Thursday, April 3rd 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 5th time
on Friday, May 30th 2025, 6:30:00 pm
82.08%
Financial Progress
13th Expenditure
of ₹ 86037 (0.86 Lacs ) done.
Cummulative ₹ 175.44Lacs ( against 213.74Lacs )
on Monday, June 9th 2025, 6:30:00 pm
91.97%
Financial Progress
14th Expenditure
of ₹ 2113837 (21.14 Lacs ) done.
Cummulative ₹ 196.58Lacs ( against 213.74Lacs )