20 years ago

on Monday, March 27th 2006, 6:30:00 pm
Work Sanctioned
अनुसूचित बाहुल्य ग्रामों को जोडने हेतु पुरोला-जरमोला मार्ग के किमी0 7 से सुरानू की सेरी तक मोटर मार्ग निर्माण।

17 years ago

on Saturday, February 28th 2009, 6:30:00 pm
1.79%
Financial Progress

1st Expenditure
of ₹ 200000 (2.00 Lacs ) done.
Cummulative ₹ 2.00Lacs ( against 112Lacs )

16 years ago

on Saturday, October 31st 2009, 6:30:00 pm
2.25%
Financial Progress

2nd Expenditure
of ₹ 51900 (0.52 Lacs ) done.
Cummulative ₹ 2.52Lacs ( against 112Lacs )

14 years ago

on Tuesday, January 31st 2012, 6:30:00 pm
2.27%
Financial Progress

3rd Expenditure
of ₹ 2414 (0.02 Lacs ) done.
Cummulative ₹ 2.54Lacs ( against 112Lacs )

14 years ago

on Wednesday, February 29th 2012, 6:30:00 pm
3.14%
Financial Progress

4th Expenditure
of ₹ 97018 (0.97 Lacs ) done.
Cummulative ₹ 3.51Lacs ( against 112Lacs )

13 years ago

on Sunday, September 30th 2012, 6:30:00 pm
3.15%
Financial Progress

5th Expenditure
of ₹ 1600 (0.02 Lacs ) done.
Cummulative ₹ 3.53Lacs ( against 112Lacs )

12 years ago

on Friday, March 21st 2014, 6:30:00 pm

Technical Sanction
of ₹ 48.1 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 913-yata/552c-6/2013

11 years ago

on Sunday, August 31st 2014, 6:30:00 pm
6.85%
Financial Progress

6th Expenditure
of ₹ 413741 (4.14 Lacs ) done.
Cummulative ₹ 7.67Lacs ( against 112Lacs )

11 years ago

on Tuesday, September 30th 2014, 6:30:00 pm
19.52%
Financial Progress

7th Expenditure
of ₹ 1419620 (14.20 Lacs ) done.
Cummulative ₹ 21.86Lacs ( against 112Lacs )

11 years ago

on Friday, October 31st 2014, 6:30:00 pm
23.38%
Financial Progress

8th Expenditure
of ₹ 432792 (4.33 Lacs ) done.
Cummulative ₹ 26.19Lacs ( against 112Lacs )

11 years ago

on Saturday, February 28th 2015, 6:30:00 pm
30.82%
Financial Progress

9th Expenditure
of ₹ 832275 (8.32 Lacs ) done.
Cummulative ₹ 34.51Lacs ( against 112Lacs )

10 years ago

on Monday, August 31st 2015, 6:30:00 pm
32.34%
Financial Progress

10th Expenditure
of ₹ 170447 (1.70 Lacs ) done.
Cummulative ₹ 36.22Lacs ( against 112Lacs )

10 years ago

on Wednesday, September 30th 2015, 6:30:00 pm
40.43%
Financial Progress

11th Expenditure
of ₹ 906614 (9.07 Lacs ) done.
Cummulative ₹ 45.28Lacs ( against 112Lacs )

10 years ago

on Sunday, January 31st 2016, 6:30:00 pm
44.17%
Financial Progress

12th Expenditure
of ₹ 418814 (4.19 Lacs ) done.
Cummulative ₹ 49.47Lacs ( against 112Lacs )

10 years ago

on Monday, February 29th 2016, 6:30:00 pm
50.13%
Financial Progress

13th Expenditure
of ₹ 666777 (6.67 Lacs ) done.
Cummulative ₹ 56.14Lacs ( against 112Lacs )

8 years ago

on Wednesday, May 31st 2017, 6:30:00 pm
58.94%
Financial Progress

14th Expenditure
of ₹ 987226 (9.87 Lacs ) done.
Cummulative ₹ 66.01Lacs ( against 112Lacs )

7 years ago

on Tuesday, July 31st 2018, 6:30:00 pm
59.30%
Financial Progress

15th Expenditure
of ₹ 40376 (0.40 Lacs ) done.
Cummulative ₹ 66.42Lacs ( against 112Lacs )

5 years ago

on Sunday, January 31st 2021, 6:30:00 pm
67.53%
Financial Progress

16th Expenditure
of ₹ 921976 (9.22 Lacs ) done.
Cummulative ₹ 75.64Lacs ( against 112Lacs )

3 years ago

on Sunday, February 26th 2023, 6:30:00 pm
67.59%
Financial Progress

17th Expenditure
of ₹ 7000 (0.07 Lacs ) done.
Cummulative ₹ 75.71Lacs ( against 112Lacs )