Refresh data
on Monday, January 29th 2024, 6:30:00 pm
Work Sanctioned
प्रधानमंत्री ग्राम सड़क योजना के अन्तर्गत वन टाइम मैंनटीनैन्स में जनपद चमोली के विधानसभा क्षेत्र थराली के विकासखण्ड नन्दानगर में मोलागाड़-मटई मोटर मार्ग के किमी॰ 1 से 11 के मध्य प्रीमिक्स कारपेट का कार्य, क्षतिग्रस्त दीवार निर्माण, क्रैश बैरियर, पैरापिट निर्माण का कार्य एवं मरम्मत कार्य।
on Thursday, February 8th 2024, 11:31:28 am
Technical Sanction
of ₹ 215.62 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS No. 425 Vide letter No. 641/604 Yatayat-7/2024 Dt 08.02.2024
on Thursday, April 25th 2024, 6:30:00 pm
6.54%
Financial Progress
1st Expenditure
of ₹ 1409628 (14.10 Lacs ) done.
Cummulative ₹ 14.10Lacs ( against 215.62Lacs )
on Monday, April 29th 2024, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, June 11th 2024, 3:30:38 am
PWD UttarakahndPhoto (ID 43111) from Site Received
Uploader : Amit Kumar, JE Civil (Samvida) ,PD Karnprayag
Landmark : Km 10 ch 9.200
Remark : Premix carpet work at molagad matai mr under one time maintenance
on Tuesday, June 11th 2024, 6:30:00 pm
18.10%
Financial Progress
2nd Expenditure
of ₹ 2492560 (24.93 Lacs ) done.
Cummulative ₹ 39.02Lacs ( against 215.62Lacs )
on Wednesday, June 12th 2024, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, June 13th 2024, 6:30:00 pm
33%
Physical Progress
Physical Progress Reported at 3rd time
on Thursday, June 20th 2024, 6:30:00 pm
21.26%
Financial Progress
3rd Expenditure
of ₹ 682546 (6.83 Lacs ) done.
Cummulative ₹ 45.85Lacs ( against 215.62Lacs )
on Monday, June 24th 2024, 6:30:00 pm
45%
Physical Progress
Physical Progress Reported at 4th time
on Sunday, July 21st 2024, 6:30:00 pm
51.01%
Financial Progress
4th Expenditure
of ₹ 6413114 (64.13 Lacs ) done.
Cummulative ₹ 109.98Lacs ( against 215.62Lacs )
on Friday, September 20th 2024, 6:30:00 pm
65.45%
Financial Progress
5th Expenditure
of ₹ 3115064 (31.15 Lacs ) done.
Cummulative ₹ 141.13Lacs ( against 215.62Lacs )
on Friday, October 4th 2024, 6:30:00 pm
51%
Physical Progress
Physical Progress Reported at 5th time
on Thursday, October 24th 2024, 6:30:00 pm
86.49%
Financial Progress
6th Expenditure
of ₹ 4536279 (45.36 Lacs ) done.
Cummulative ₹ 186.49Lacs ( against 215.62Lacs )
on Sunday, October 27th 2024, 6:30:00 pm
93.05%
Financial Progress
7th Expenditure
of ₹ 1414072 (14.14 Lacs ) done.
Cummulative ₹ 200.63Lacs ( against 215.62Lacs )
on Thursday, November 28th 2024, 6:30:00 pm
96.89%
Financial Progress
8th Expenditure
of ₹ 827901 (8.28 Lacs ) done.
Cummulative ₹ 208.91Lacs ( against 215.62Lacs )
on Tuesday, December 31st 2024, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 6th time
on Monday, February 17th 2025, 6:30:00 pm
97.23%
Financial Progress
9th Expenditure
of ₹ 72570 (0.73 Lacs ) done.
Cummulative ₹ 209.64Lacs ( against 215.62Lacs )