Work Sanctioned
जनपद चमोली में गौचर-सिदोली मोटर मार्ग का विस्तार कि0मी0 24.500 से 27.500
on Monday, February 28th 2011, 6:30:00 pm
0.10%
Financial Progress
1st Expenditure
of ₹ 11000 (0.11 Lacs ) done.
Cummulative ₹ 0.11Lacs ( against 110.25Lacs )
on Sunday, November 22nd 2020, 6:30:00 pm
Technical Sanction
of ₹ 110.25 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 6261/99Yata-7/2020
on Thursday, July 22nd 2021, 8:23:07 am
PWD UttarakahndPhoto (ID 395) from Site Received
Uploader : Anup Singh, Executive Engineer Civil ,CD Gaucher
Landmark : Km1
Remark : Wall damage due to nh widening
on Thursday, July 22nd 2021, 8:23:56 am
PWD UttarakahndPhoto (ID 396) from Site Received
Uploader : Anup Singh, Executive Engineer Civil ,CD Gaucher
Landmark : Km1
Remark : Land settelment
on Saturday, August 7th 2021, 6:09:20 am
PWD UttarakahndPhoto (ID 516) from Site Received
Uploader : Narendra Kumar, Additional Assistant Engineer Civil ,CD Gaucher
Landmark : Km 24.500 Village: Obya Gwad
Remark : Chapan work Starting with Forest Department & PWD at Km 24.500 to Forward at Extension of Gauchar - Sidoli - Dhanpur Motor Road Today.(Km 24.500 - 27.500)
on Saturday, August 7th 2021, 6:59:01 am
PWD UttarakahndPhoto (ID 517) from Site Received
Uploader : Narendra Kumar, Additional Assistant Engineer Civil ,CD Gaucher
Landmark : 24.625 Village: Charkhil Gwad.
Remark : Chapan work running with Forest Department & Dhanpur Villagers.
on Saturday, August 7th 2021, 8:50:20 am
PWD UttarakahndPhoto (ID 518) from Site Received
Uploader : Narendra Kumar, Additional Assistant Engineer Civil ,CD Gaucher
Landmark : Km 25.375 Charkhil Gwad Village.
Remark : Chapan work Still on Progress (Van Panchayat Charkhil Gwad Village)
on Sunday, August 8th 2021, 6:09:20 am
PWD UttarakahndPhoto (ID 525) from Site Received
Uploader : Narendra Kumar, Additional Assistant Engineer Civil ,CD Gaucher
Landmark : Km 25.425 Rensh Dhar (Van Panchayat Dhanpur)
Remark : Chapan work in progress Km 25.425 on forward, Extension of Gauchar - Sidoli - Dhanpur M/R. Location: Rensh Dhar (Vanpanchayat Dhanpur)
on Sunday, August 8th 2021, 7:33:29 am
PWD UttarakahndPhoto (ID 19345) from Site Received
Uploader : Narendra Kumar, Additional Assistant Engineer Civil ,CD Gaucher
Landmark : Km 25.825 (Vanpanchayat Dhanpur)
Remark : Chapan work in progress (Seelapakh)
on Sunday, August 8th 2021, 7:46:47 am
PWD UttarakahndPhoto (ID 19346) from Site Received
Uploader : Narendra Kumar, Additional Assistant Engineer Civil ,CD Gaucher
Landmark : Km 25.825 (Vanpanchayat Dhanpur)
Remark : CD PWD Gauchar & Forest Department Chapan work in Progress (Vanpanchayat Dhanpur)
on Friday, August 27th 2021, 6:30:00 pm
0.47%
Financial Progress
2nd Expenditure
of ₹ 41283 (0.41 Lacs ) done.
Cummulative ₹ 0.52Lacs ( against 110.25Lacs )
on Monday, October 4th 2021, 6:30:00 pm
7.73%
Financial Progress
3rd Expenditure
of ₹ 800000 (8.00 Lacs ) done.
Cummulative ₹ 8.52Lacs ( against 110.25Lacs )
on Friday, November 26th 2021, 6:30:00 pm
8.52%
Financial Progress
4th Expenditure
of ₹ 86845 (0.87 Lacs ) done.
Cummulative ₹ 9.39Lacs ( against 110.25Lacs )
on Tuesday, January 18th 2022, 6:30:00 pm
9.19%
Financial Progress
6th Expenditure
of ₹ 14821 (0.15 Lacs ) done.
Cummulative ₹ 10.13Lacs ( against 110.25Lacs )
on Tuesday, January 18th 2022, 6:30:00 pm
9.05%
Financial Progress
5th Expenditure
of ₹ 59160 (0.59 Lacs ) done.
Cummulative ₹ 9.98Lacs ( against 110.25Lacs )
on Tuesday, March 29th 2022, 6:30:00 pm
18.26%
Financial Progress
7th Expenditure
of ₹ 1000000 (10.00 Lacs ) done.
Cummulative ₹ 20.13Lacs ( against 110.25Lacs )
on Wednesday, September 28th 2022, 6:30:00 pm
23.31%
Financial Progress
8th Expenditure
of ₹ 556620 (5.57 Lacs ) done.
Cummulative ₹ 25.70Lacs ( against 110.25Lacs )
on Sunday, October 30th 2022, 6:30:00 pm
24.21%
Financial Progress
9th Expenditure
of ₹ 99974 (1.00 Lacs ) done.
Cummulative ₹ 26.70Lacs ( against 110.25Lacs )
on Saturday, February 11th 2023, 6:30:00 pm
24.37%
Financial Progress
10th Expenditure
of ₹ 17169 (0.17 Lacs ) done.
Cummulative ₹ 26.87Lacs ( against 110.25Lacs )
on Sunday, February 19th 2023, 6:30:00 pm
31.30%
Financial Progress
11th Expenditure
of ₹ 764400 (7.64 Lacs ) done.
Cummulative ₹ 34.51Lacs ( against 110.25Lacs )
on Thursday, February 23rd 2023, 6:30:00 pm
31.51%
Financial Progress
12th Expenditure
of ₹ 23058 (0.23 Lacs ) done.
Cummulative ₹ 34.74Lacs ( against 110.25Lacs )
on Thursday, July 13th 2023, 6:30:00 pm
31.60%
Financial Progress
14th Expenditure
of ₹ 9980 (0.10 Lacs ) done.
Cummulative ₹ 34.84Lacs ( against 110.25Lacs )
on Thursday, July 13th 2023, 6:30:00 pm
31.51%
Financial Progress
13th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 34.74Lacs ( against 110.25Lacs )
on Wednesday, August 23rd 2023, 6:30:00 pm
42.72%
Financial Progress
15th Expenditure
of ₹ 1225319 (12.25 Lacs ) done.
Cummulative ₹ 47.10Lacs ( against 110.25Lacs )
on Thursday, August 24th 2023, 6:30:00 pm
42.72%
Financial Progress
16th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 47.10Lacs ( against 110.25Lacs )
on Sunday, September 24th 2023, 6:30:00 pm
50.65%
Financial Progress
17th Expenditure
of ₹ 874910 (8.75 Lacs ) done.
Cummulative ₹ 55.85Lacs ( against 110.25Lacs )
on Wednesday, September 27th 2023, 6:30:00 pm
50.65%
Financial Progress
18th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 55.85Lacs ( against 110.25Lacs )
on Thursday, January 11th 2024, 6:30:00 pm
56.00%
Financial Progress
19th Expenditure
of ₹ 589243 (5.89 Lacs ) done.
Cummulative ₹ 61.74Lacs ( against 110.25Lacs )
on Friday, April 26th 2024, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 1st time
on Friday, May 17th 2024, 6:30:00 pm
56.24%
Financial Progress
20th Expenditure
of ₹ 27000 (0.27 Lacs ) done.
Cummulative ₹ 62.01Lacs ( against 110.25Lacs )
on Sunday, May 26th 2024, 6:30:00 pm
58.19%
Financial Progress
21st Expenditure
of ₹ 214816 (2.15 Lacs ) done.
Cummulative ₹ 64.16Lacs ( against 110.25Lacs )
on Friday, June 28th 2024, 6:30:00 pm
58.24%
Financial Progress
22nd Expenditure
of ₹ 5000 (0.05 Lacs ) done.
Cummulative ₹ 64.21Lacs ( against 110.25Lacs )
on Thursday, September 26th 2024, 6:30:00 pm
65.29%
Financial Progress
23rd Expenditure
of ₹ 777137 (7.77 Lacs ) done.
Cummulative ₹ 71.98Lacs ( against 110.25Lacs )
on Wednesday, August 13th 2025, 6:30:00 pm
65.90%
Financial Progress
24th Expenditure
of ₹ 67836 (0.68 Lacs ) done.
Cummulative ₹ 72.66Lacs ( against 110.25Lacs )