Work Sanctioned
जनपद चमोली के विधानसभा क्षेत्र-कर्णप्रयाग के विकासखण्ड कर्णप्रयाग में भकुण्डा से ढंुग तक मोटर मार्ग के नव निर्माण कार्य।
on Thursday, February 28th 2019, 6:30:00 pm
0.67%
Financial Progress
1st Expenditure
of ₹ 14000 (0.14 Lacs ) done.
Cummulative ₹ 0.14Lacs ( against 20.8Lacs )
on Friday, February 16th 2024, 2:42:02 am
PWD UttarakahndPhoto (ID 35934) from Site Received
Uploader : Mohammad Rashid, Assistant Engineer Civil ,CD Gaucher
Landmark : 0.050
Remark : Hill side cutting inspection
on Friday, February 16th 2024, 2:43:56 am
PWD UttarakahndPhoto (ID 35935) from Site Received
Uploader : Mohammad Rashid, Assistant Engineer Civil ,CD Gaucher
Landmark : 0.025
Remark : Hsc
on Friday, February 16th 2024, 2:50:47 am
PWD UttarakahndPhoto (ID 35936) from Site Received
Uploader : Mohammad Rashid, Assistant Engineer Civil ,CD Gaucher
Landmark : 0.200
Remark : HP bend
on Friday, February 16th 2024, 2:57:01 am
PWD UttarakahndPhoto (ID 35937) from Site Received
Uploader : Mohammad Rashid, Assistant Engineer Civil ,CD Gaucher
Landmark : 0.250
Remark : HSC
on Thursday, January 30th 2025, 6:30:00 pm
65.72%
Financial Progress
2nd Expenditure
of ₹ 1353020 (13.53 Lacs ) done.
Cummulative ₹ 13.67Lacs ( against 20.8Lacs )
on Monday, February 24th 2025, 6:30:00 pm
76.40%
Financial Progress
3rd Expenditure
of ₹ 222000 (2.22 Lacs ) done.
Cummulative ₹ 15.89Lacs ( against 20.8Lacs )
on Sunday, March 23rd 2025, 6:30:00 pm
79.87%
Financial Progress
4th Expenditure
of ₹ 72239 (0.72 Lacs ) done.
Cummulative ₹ 16.61Lacs ( against 20.8Lacs )