3 years ago

on Wednesday, May 10th 2023, 6:30:00 pm
Work Sanctioned
जनपद चमोली के विधानसभा क्षेत्र कर्णप्रयाग के अन्तर्गत विराजकुंज से जैंटी-भटकोटी-कण्डारा तक मोटर मार्ग नव निर्माण। (प्रथम चरण)

2 years ago

on Friday, February 16th 2024, 6:44:49 am
<span class="4">Picture Id:35921</span>
PWD Uttarakahnd
Photo (ID 35921) from Site Received
Uploader : Mohammad Rashid, Assistant Engineer Civil ,CD Gaucher
Landmark : Km1
Remark : Geologist revisit

2 years ago

on Friday, February 16th 2024, 6:48:10 am
<span class="4">Picture Id:35922</span>
PWD Uttarakahnd
Photo (ID 35922) from Site Received
Uploader : Mohammad Rashid, Assistant Engineer Civil ,CD Gaucher
Landmark : 0.500km
Remark : Geologist Revisit

2 years ago

on Friday, February 16th 2024, 7:19:50 am
<span class="4">Picture Id:35930</span>
PWD Uttarakahnd
Photo (ID 35930) from Site Received
Uploader : Mohammad Rashid, Assistant Engineer Civil ,CD Gaucher
Landmark : 0.000
Remark : Geologist Re-visit

a year ago

on Saturday, September 7th 2024, 6:13:45 am

Technical Sanction
of ₹ 7.06 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1322/1 C

9 months ago

on Friday, February 28th 2025, 6:30:00 pm
58.03%
Financial Progress

1st Expenditure
of ₹ 435250 (4.35 Lacs ) done.
Cummulative ₹ 4.35Lacs ( against 7.5Lacs )

2 months ago

on Monday, September 8th 2025, 6:30:00 pm
78.41%
Financial Progress

2nd Expenditure
of ₹ 152845 (1.53 Lacs ) done.
Cummulative ₹ 5.88Lacs ( against 7.5Lacs )