Work Sanctioned
ग्राम पंचायत सांदर में सड़क निर्माण से मकानों की सुरक्षा दीवार का निर्माण।
on Friday, September 6th 2024, 6:28:42 am
Technical Sanction
of ₹ 6 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 147/1C (Camp)
on Thursday, January 30th 2025, 6:30:00 pm
50.00%
Financial Progress
1st Expenditure
of ₹ 300000 (3.00 Lacs ) done.
Cummulative ₹ 3.00Lacs ( against 6Lacs )
on Thursday, March 27th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, September 24th 2025, 6:30:00 pm
83.19%
Financial Progress
2nd Expenditure
of ₹ 199113 (1.99 Lacs ) done.
Cummulative ₹ 4.99Lacs ( against 6Lacs )