@
Refresh data
Refresh data

9 years ago

on Sunday, March 20th 2016, 6:30:00 pm
Work Sanctioned
जनपद अल्मोड़ा के विधान सभा क्षेत्र सल्ट में पैसिया-पीपना मोटर मार्ग का झीपा-टनला-सीमलीतल-लछिगढ़-जाम्हिर खेत होते हुए डभरा तक विस्तार।

9 years ago

on Saturday, July 2nd 2016, 6:30:00 pm

Technical Sanction
of ₹ 486.12 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 3492/03Yata-Aa/2016

7 years ago

on Sunday, December 31st 2017, 6:30:00 pm
11.97%
Financial Progress

1st Expenditure
of ₹ 6171500 (61.72 Lacs ) done.
Cummulative ₹ 61.72Lacs ( against 515.52Lacs )

7 years ago

on Wednesday, January 31st 2018, 6:30:00 pm
26.61%
Financial Progress

2nd Expenditure
of ₹ 7548000 (75.48 Lacs ) done.
Cummulative ₹ 137.19Lacs ( against 515.52Lacs )

7 years ago

on Wednesday, February 28th 2018, 6:30:00 pm
38.32%
Financial Progress

3rd Expenditure
of ₹ 6033986 (60.34 Lacs ) done.
Cummulative ₹ 197.53Lacs ( against 515.52Lacs )

7 years ago

on Monday, April 30th 2018, 6:30:00 pm
46.64%
Financial Progress

4th Expenditure
of ₹ 4292303 (42.92 Lacs ) done.
Cummulative ₹ 240.46Lacs ( against 515.52Lacs )

7 years ago

on Thursday, May 31st 2018, 6:30:00 pm
49.71%
Financial Progress

5th Expenditure
of ₹ 1580000 (15.80 Lacs ) done.
Cummulative ₹ 256.26Lacs ( against 515.52Lacs )

7 years ago

on Tuesday, July 31st 2018, 6:30:00 pm
60.07%
Financial Progress

6th Expenditure
of ₹ 5340804 (53.41 Lacs ) done.
Cummulative ₹ 309.67Lacs ( against 515.52Lacs )

6 years ago

on Thursday, February 28th 2019, 6:30:00 pm
77.33%
Financial Progress

7th Expenditure
of ₹ 8898102 (88.98 Lacs ) done.
Cummulative ₹ 398.65Lacs ( against 515.52Lacs )

6 years ago

on Wednesday, July 31st 2019, 6:30:00 pm
88.30%
Financial Progress

8th Expenditure
of ₹ 5653638 (56.54 Lacs ) done.
Cummulative ₹ 455.18Lacs ( against 515.52Lacs )

5 years ago

on Saturday, October 31st 2020, 6:30:00 pm
89.43%
Financial Progress

9th Expenditure
of ₹ 587035 (5.87 Lacs ) done.
Cummulative ₹ 461.05Lacs ( against 515.52Lacs )

4 years ago

on Sunday, March 21st 2021, 6:30:00 pm

Technical Sanction
of ₹ 29.4 Lacs

2nd Technical Sanction of Work after survey,detailed design and analysis by Latter No. 876/101Yata-Aa/2021

4 years ago

on Wednesday, September 29th 2021, 6:30:00 pm
89.72%
Financial Progress

10th Expenditure
of ₹ 146189 (1.46 Lacs ) done.
Cummulative ₹ 462.52Lacs ( against 515.52Lacs )

4 years ago

on Sunday, October 31st 2021, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Wednesday, December 22nd 2021, 4:25:02 am
<span class="4">Picture Id:3846</span>
PWD Uttarakahnd
Photo (ID 3846) from Site Received
Uploader : Satnam Singh, Assistant Engineer Civil ,CD Kashipur
Landmark : Km 23
Remark : Measurement checking

3 years ago

on Tuesday, January 4th 2022, 3:28:39 am
<span class="4">Picture Id:4014</span>
PWD Uttarakahnd
Photo (ID 4014) from Site Received
Uploader : Dharmendra Kumar Sharma, JE Civil (Samvida) ,PD Ranikhet
Landmark : Km1
Remark : Road cutting at pipnakola rankuna m/marg

3 years ago

on Tuesday, January 4th 2022, 3:33:25 am
<span class="4">Picture Id:4016</span>
PWD Uttarakahnd
Photo (ID 4016) from Site Received
Uploader : Satnam Singh, Assistant Engineer Civil ,CD Kashipur
Landmark : Km 1
Remark : Site inspection

3 years ago

on Wednesday, February 2nd 2022, 12:33:37 am
<span class="4">Picture Id:4264</span>
PWD Uttarakahnd
Photo (ID 4264) from Site Received
Uploader : Dharmendra Kumar Sharma, JE Civil (Samvida) ,PD Ranikhet
Landmark : Km 1 ch 0.00
Remark : R/wall at pipna kola rankuna motar marg

3 years ago

on Wednesday, February 2nd 2022, 1:04:39 am
<span class="4">Picture Id:4265</span>
PWD Uttarakahnd
Photo (ID 4265) from Site Received
Uploader : Dharmendra Kumar Sharma, JE Civil (Samvida) ,PD Ranikhet
Landmark : Km.1 ch.0/30
Remark : Pipnakola rankuna marg

3 years ago

on Wednesday, February 2nd 2022, 2:43:42 am
<span class="4">Picture Id:4267</span>
PWD Uttarakahnd
Photo (ID 4267) from Site Received
Uploader : Lalit Mohan Bisht, Additional Assistant Engineer Civil ,PD Almora
Landmark : Km 22
Remark : Jheepa tanla Road wall work

3 years ago

on Saturday, March 26th 2022, 3:09:33 am
<span class="4">Picture Id:5033</span>
PWD Uttarakahnd
Photo (ID 5033) from Site Received
Uploader : Lalit Mohan Bisht, Additional Assistant Engineer Civil ,PD Almora
Landmark : Km 25
Remark : R/wall work Jheepa tanla Road

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
92.38%
Financial Progress

11th Expenditure
of ₹ 1373033 (13.73 Lacs ) done.
Cummulative ₹ 476.25Lacs ( against 515.52Lacs )

3 years ago

on Wednesday, April 6th 2022, 1:36:49 am
<span class="4">Picture Id:5186</span>
PWD Uttarakahnd
Photo (ID 5186) from Site Received
Uploader : Satnam Singh, Assistant Engineer Civil ,CD Kashipur
Landmark : Chainage 0/32
Remark : Site inspection by SE sir

3 years ago

on Wednesday, April 6th 2022, 3:58:44 am
<span class="4">Picture Id:5187</span>
PWD Uttarakahnd
Photo (ID 5187) from Site Received
Uploader : Satnam Singh, Assistant Engineer Civil ,CD Kashipur
Landmark : Km 2.800
Remark : Site inspection by SE sir

3 years ago

on Thursday, September 29th 2022, 6:30:00 pm
93.82%
Financial Progress

12th Expenditure
of ₹ 739853 (7.40 Lacs ) done.
Cummulative ₹ 483.64Lacs ( against 515.52Lacs )

5 months ago

on Monday, December 30th 2024, 6:30:00 pm
101.96%
Financial Progress

13th Expenditure
of ₹ 4200000 (42.00 Lacs ) done.
Cummulative ₹ 525.64Lacs ( against 515.52Lacs )

2 months ago

on Tuesday, March 25th 2025, 6:30:00 pm
93.82%
Financial Progress

14th Expenditure
of ₹ -4200000 (-42.00 Lacs ) done.
Cummulative ₹ 483.64Lacs ( against 515.52Lacs )

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable
refresh data by PWD Uttarakhand Engineeres | View code by HandsOnDataViz with Leaflet | © OpenStreetMap contributors