on Monday, November 14th 2016, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री जी की घोषणा सं0 432/2014 के अन्तर्गत जनपद अल्मोड़ा के विधानसभा क्षेत्र सल्ट में गगास उड़ी महादेव सैलापानी भिक्यिौण मरचूला मोटर मार्ग की पुनरीकि्षत स्वीकृति सेतु सहित।
on Tuesday, February 28th 2017, 6:30:00 pm
0.00%
Financial Progress
1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 2433.59Lacs )
on Friday, August 4th 2017, 6:30:00 pm
Technical Sanction
of ₹ 2433.59 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2547/535Yata-Aa/2016
on Tuesday, July 31st 2018, 6:30:00 pm
0.03%
Financial Progress
2nd Expenditure
of ₹ 52500 (0.53 Lacs ) done.
Cummulative ₹ 0.63Lacs ( against 2433.59Lacs )
on Monday, December 31st 2018, 6:30:00 pm
2.11%
Financial Progress
3rd Expenditure
of ₹ 5066776 (50.67 Lacs ) done.
Cummulative ₹ 51.29Lacs ( against 2433.59Lacs )
on Thursday, February 28th 2019, 6:30:00 pm
4.14%
Financial Progress
4th Expenditure
of ₹ 4937075 (49.37 Lacs ) done.
Cummulative ₹ 100.66Lacs ( against 2433.59Lacs )
on Wednesday, July 31st 2019, 6:30:00 pm
6.90%
Financial Progress
5th Expenditure
of ₹ 6713328 (67.13 Lacs ) done.
Cummulative ₹ 167.80Lacs ( against 2433.59Lacs )
on Monday, September 30th 2019, 6:30:00 pm
8.12%
Financial Progress
6th Expenditure
of ₹ 2980320 (29.80 Lacs ) done.
Cummulative ₹ 197.60Lacs ( against 2433.59Lacs )
on Friday, January 31st 2020, 6:30:00 pm
10.33%
Financial Progress
7th Expenditure
of ₹ 5384818 (53.85 Lacs ) done.
Cummulative ₹ 251.45Lacs ( against 2433.59Lacs )
on Saturday, February 29th 2020, 6:30:00 pm
14.12%
Financial Progress
8th Expenditure
of ₹ 9206400 (92.06 Lacs ) done.
Cummulative ₹ 343.51Lacs ( against 2433.59Lacs )
on Tuesday, June 30th 2020, 6:30:00 pm
14.15%
Financial Progress
9th Expenditure
of ₹ 84000 (0.84 Lacs ) done.
Cummulative ₹ 344.35Lacs ( against 2433.59Lacs )
on Friday, July 31st 2020, 6:30:00 pm
14.16%
Financial Progress
10th Expenditure
of ₹ 14810 (0.15 Lacs ) done.
Cummulative ₹ 344.50Lacs ( against 2433.59Lacs )
on Monday, August 31st 2020, 6:30:00 pm
14.22%
Financial Progress
11th Expenditure
of ₹ 165060 (1.65 Lacs ) done.
Cummulative ₹ 346.15Lacs ( against 2433.59Lacs )
on Sunday, January 31st 2021, 6:30:00 pm
15.38%
Financial Progress
12th Expenditure
of ₹ 2807978 (28.08 Lacs ) done.
Cummulative ₹ 374.23Lacs ( against 2433.59Lacs )
on Sunday, February 28th 2021, 6:30:00 pm
24.33%
Financial Progress
13th Expenditure
of ₹ 21797862 (217.98 Lacs ) done.
Cummulative ₹ 592.21Lacs ( against 2433.59Lacs )
on Tuesday, August 24th 2021, 6:30:00 pm
65%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, September 28th 2021, 6:30:00 pm
24.33%
Financial Progress
14th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 592.21Lacs ( against 2433.59Lacs )
on Wednesday, September 29th 2021, 6:30:00 pm
25.32%
Financial Progress
15th Expenditure
of ₹ 2393020 (23.93 Lacs ) done.
Cummulative ₹ 616.14Lacs ( against 2433.59Lacs )
on Monday, March 7th 2022, 7:48:39 am
PWD UttarakahndPhoto (ID 5195) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 32
Remark : KM 32
on Wednesday, March 30th 2022, 6:30:00 pm
23.59%
Financial Progress
16th Expenditure
of ₹ -4205942 (-42.06 Lacs ) done.
Cummulative ₹ 574.08Lacs ( against 2433.59Lacs )
on Thursday, April 7th 2022, 9:34:37 am
PWD UttarakahndPhoto (ID 5194) from Site Received
Uploader : Bhuwan Chandra Bhatt, Assistant Engineer Civil ,TD Berinaag
Landmark : Km 32
Remark : Hill side cutting and wall check
on Thursday, April 7th 2022, 9:37:25 am
PWD UttarakahndPhoto (ID 5197) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 32
Remark : Measurement
on Thursday, April 7th 2022, 9:40:32 am
PWD UttarakahndPhoto (ID 5196) from Site Received
Uploader : Bhuwan Chandra Bhatt, Assistant Engineer Civil ,TD Berinaag
Landmark : Km 32
Remark : Inspection of road cutting
on Thursday, April 7th 2022, 9:40:41 am
PWD UttarakahndPhoto (ID 5198) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 32
Remark : Checking
on Thursday, April 7th 2022, 9:43:06 am
PWD UttarakahndPhoto (ID 5199) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 33
Remark : Checking
on Thursday, April 7th 2022, 9:57:00 am
PWD UttarakahndPhoto (ID 5205) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 35
Remark : Checking
on Tuesday, April 26th 2022, 6:02:43 am
PWD UttarakahndPhoto (ID 5418) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 34
Remark : Inspection
on Friday, May 6th 2022, 9:56:28 am
PWD UttarakahndPhoto (ID 5518) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM-23
Remark : Plane Table Work
on Friday, May 6th 2022, 10:26:28 am
PWD UttarakahndPhoto (ID 5519) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 23
Remark : Plane Table Work
on Sunday, May 8th 2022, 8:47:44 am
PWD UttarakahndPhoto (ID 5535) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM - 33
Remark : Survey work by Total Station
on Thursday, March 30th 2023, 6:30:00 pm
23.59%
Financial Progress
17th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 574.08Lacs ( against 2433.59Lacs )
on Friday, June 2nd 2023, 6:30:00 pm
70%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, July 4th 2023, 8:26:05 am
PWD UttarakahndPhoto (ID 22260) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 23
Remark : Gagas udi mhadev mr
on Tuesday, July 4th 2023, 8:34:52 am
PWD UttarakahndPhoto (ID 22263) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km28
Remark : Gagas udi mhadev
on Wednesday, July 5th 2023, 6:30:00 pm
26.71%
Financial Progress
18th Expenditure
of ₹ 7593522 (75.94 Lacs ) done.
Cummulative ₹ 650.02Lacs ( against 2433.59Lacs )
on Wednesday, July 19th 2023, 6:30:00 pm
26.72%
Financial Progress
19th Expenditure
of ₹ 17655 (0.18 Lacs ) done.
Cummulative ₹ 650.19Lacs ( against 2433.59Lacs )
on Tuesday, August 1st 2023, 8:35:00 am
PWD UttarakahndPhoto (ID 23176) from Site Received
Uploader : Satnam Singh, Assistant Engineer Civil ,CD Kashipur
Landmark : Chainage 12/7-8
Remark : Steel checking
on Thursday, August 3rd 2023, 6:30:00 pm
26.72%
Financial Progress
20th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 650.19Lacs ( against 2433.59Lacs )
on Thursday, August 3rd 2023, 6:30:00 pm
27.36%
Financial Progress
21st Expenditure
of ₹ 1561203 (15.61 Lacs ) done.
Cummulative ₹ 665.80Lacs ( against 2433.59Lacs )
on Wednesday, August 9th 2023, 9:50:26 am
PWD UttarakahndPhoto (ID 23427) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km25
Remark : Gagas udi mhadev
on Wednesday, August 9th 2023, 10:02:35 am
PWD UttarakahndPhoto (ID 23429) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km
Remark : Gagas udi mhadev
on Monday, August 21st 2023, 9:32:14 am
PWD UttarakahndPhoto (ID 23733) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 24
Remark : Gagas udi mhadev
on Monday, August 21st 2023, 9:57:05 am
PWD UttarakahndPhoto (ID 23734) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km24
Remark : Gagas udi mhadev
on Monday, August 21st 2023, 9:58:17 am
PWD UttarakahndPhoto (ID 23737) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 24
Remark : Gagas udi mhadev
on Monday, August 21st 2023, 10:56:18 am
PWD UttarakahndPhoto (ID 23738) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 23
Remark : Gagas udi mhadev
on Tuesday, August 29th 2023, 6:52:03 am
PWD UttarakahndPhoto (ID 23817) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 24
Remark : Gagas udi mhadev mr
on Tuesday, August 29th 2023, 7:16:44 am
PWD UttarakahndPhoto (ID 23818) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 24
Remark : Gagas udi mhadev
on Tuesday, August 29th 2023, 8:12:42 am
PWD UttarakahndPhoto (ID 23821) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 24
Remark : Gagas udi mhadev
on Friday, September 1st 2023, 6:30:00 pm
75%
Physical Progress
Physical Progress Reported at 3rd time
on Tuesday, September 5th 2023, 6:30:00 pm
28.81%
Financial Progress
22nd Expenditure
of ₹ 3528867 (35.29 Lacs ) done.
Cummulative ₹ 701.09Lacs ( against 2433.59Lacs )
on Wednesday, September 27th 2023, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 4th time
on Friday, September 29th 2023, 6:30:00 pm
32.51%
Financial Progress
23rd Expenditure
of ₹ 9014015 (90.14 Lacs ) done.
Cummulative ₹ 791.23Lacs ( against 2433.59Lacs )
on Tuesday, October 10th 2023, 7:40:37 am
PWD UttarakahndPhoto (ID 28128) from Site Received
Uploader : Manoj Kumar, JE Civil (Samvida) ,CD Pokhari
Landmark : Km-17/3
Remark : Suupper
on Wednesday, October 11th 2023, 8:47:47 am
PWD UttarakahndPhoto (ID 24834) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 24
Remark : Gagas udi mhadev
on Wednesday, October 11th 2023, 10:53:15 am
PWD UttarakahndPhoto (ID 24835) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 25
Remark : Gagas udi mhadev
on Friday, October 13th 2023, 7:11:21 am
PWD UttarakahndPhoto (ID 25010) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km26
Remark : Gagas udi mhadev mr
on Friday, October 13th 2023, 7:14:10 am
PWD UttarakahndPhoto (ID 25011) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km26
Remark : Gagas udi mhadev
on Friday, October 13th 2023, 8:01:18 am
PWD UttarakahndPhoto (ID 25025) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 26
Remark : Gagas udi mhadev mr
on Sunday, October 29th 2023, 6:30:00 pm
36.24%
Financial Progress
24th Expenditure
of ₹ 9066000 (90.66 Lacs ) done.
Cummulative ₹ 881.89Lacs ( against 2433.59Lacs )
on Thursday, November 9th 2023, 6:30:00 pm
36.25%
Financial Progress
25th Expenditure
of ₹ 21000 (0.21 Lacs ) done.
Cummulative ₹ 882.10Lacs ( against 2433.59Lacs )
on Thursday, November 9th 2023, 6:30:00 pm
36.25%
Financial Progress
26th Expenditure
of ₹ 17700 (0.18 Lacs ) done.
Cummulative ₹ 882.28Lacs ( against 2433.59Lacs )
on Thursday, November 9th 2023, 6:30:00 pm
36.35%
Financial Progress
27th Expenditure
of ₹ 233640 (2.34 Lacs ) done.
Cummulative ₹ 884.62Lacs ( against 2433.59Lacs )
on Friday, December 1st 2023, 6:30:00 pm
36.34%
Financial Progress
28th Expenditure
of ₹ -17655 (-0.18 Lacs ) done.
Cummulative ₹ 884.44Lacs ( against 2433.59Lacs )
on Monday, December 25th 2023, 6:30:00 pm
36.39%
Financial Progress
29th Expenditure
of ₹ 114500 (1.15 Lacs ) done.
Cummulative ₹ 885.58Lacs ( against 2433.59Lacs )
on Thursday, January 4th 2024, 6:30:00 pm
36.60%
Financial Progress
30th Expenditure
of ₹ 518620 (5.19 Lacs ) done.
Cummulative ₹ 890.77Lacs ( against 2433.59Lacs )
on Saturday, January 6th 2024, 7:26:40 am
PWD UttarakahndPhoto (ID 34372) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 29
Remark : 4*4box curvert gagas udi Mahadev mr
on Tuesday, January 9th 2024, 7:02:07 am
PWD UttarakahndPhoto (ID 34494) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km29
Remark : 4*4 box culvert gagas udi Mahadev mr
on Wednesday, January 10th 2024, 6:30:00 pm
36.62%
Financial Progress
31st Expenditure
of ₹ 48599 (0.49 Lacs ) done.
Cummulative ₹ 891.26Lacs ( against 2433.59Lacs )
on Wednesday, January 10th 2024, 6:30:00 pm
36.65%
Financial Progress
32nd Expenditure
of ₹ 65513 (0.66 Lacs ) done.
Cummulative ₹ 891.91Lacs ( against 2433.59Lacs )
on Monday, January 15th 2024, 6:30:00 pm
36.83%
Financial Progress
33rd Expenditure
of ₹ 426046 (4.26 Lacs ) done.
Cummulative ₹ 896.17Lacs ( against 2433.59Lacs )
on Monday, January 15th 2024, 6:30:00 pm
36.83%
Financial Progress
34th Expenditure
of ₹ 7138 (0.07 Lacs ) done.
Cummulative ₹ 896.24Lacs ( against 2433.59Lacs )
on Monday, January 15th 2024, 6:30:00 pm
36.83%
Financial Progress
35th Expenditure
of ₹ 12423 (0.12 Lacs ) done.
Cummulative ₹ 896.37Lacs ( against 2433.59Lacs )
on Monday, January 15th 2024, 6:30:00 pm
36.84%
Financial Progress
36th Expenditure
of ₹ 5955 (0.06 Lacs ) done.
Cummulative ₹ 896.43Lacs ( against 2433.59Lacs )
on Monday, January 15th 2024, 6:30:00 pm
36.84%
Financial Progress
37th Expenditure
of ₹ 6370 (0.06 Lacs ) done.
Cummulative ₹ 896.49Lacs ( against 2433.59Lacs )
on Monday, January 15th 2024, 6:30:00 pm
36.84%
Financial Progress
38th Expenditure
of ₹ 9528 (0.10 Lacs ) done.
Cummulative ₹ 896.59Lacs ( against 2433.59Lacs )
on Wednesday, January 17th 2024, 6:30:00 pm
39.70%
Financial Progress
39th Expenditure
of ₹ 6946087 (69.46 Lacs ) done.
Cummulative ₹ 966.05Lacs ( against 2433.59Lacs )
on Wednesday, January 17th 2024, 6:30:00 pm
41.35%
Financial Progress
40th Expenditure
of ₹ 4026882 (40.27 Lacs ) done.
Cummulative ₹ 1006.32Lacs ( against 2433.59Lacs )
on Tuesday, February 13th 2024, 9:03:29 am
PWD UttarakahndPhoto (ID 35816) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 26
Remark : Gagas udi Mahadev
on Monday, February 19th 2024, 9:51:33 am
PWD UttarakahndPhoto (ID 36251) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 25
Remark : Gagas udi
on Tuesday, February 20th 2024, 8:32:36 am
PWD UttarakahndPhoto (ID 36099) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 18
Remark : RHS abutment foundation concrete casting work in progress
on Tuesday, March 5th 2024, 10:50:55 am
PWD UttarakahndPhoto (ID 36565) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 36
Remark : Gagas udi mahadev
on Sunday, March 17th 2024, 6:30:00 pm
42.93%
Financial Progress
41st Expenditure
of ₹ 3834983 (38.35 Lacs ) done.
Cummulative ₹ 1044.67Lacs ( against 2433.59Lacs )
on Saturday, March 30th 2024, 6:30:00 pm
47.57%
Financial Progress
42nd Expenditure
of ₹ 11307635 (113.08 Lacs ) done.
Cummulative ₹ 1157.74Lacs ( against 2433.59Lacs )
on Sunday, May 26th 2024, 6:30:00 pm
48.21%
Financial Progress
43rd Expenditure
of ₹ 1553717 (15.54 Lacs ) done.
Cummulative ₹ 1173.28Lacs ( against 2433.59Lacs )
on Monday, May 27th 2024, 6:30:00 pm
49.23%
Financial Progress
44th Expenditure
of ₹ 2487545 (24.88 Lacs ) done.
Cummulative ₹ 1198.15Lacs ( against 2433.59Lacs )
on Monday, June 3rd 2024, 6:30:00 pm
51.07%
Financial Progress
45th Expenditure
of ₹ 4467308 (44.67 Lacs ) done.
Cummulative ₹ 1242.83Lacs ( against 2433.59Lacs )
on Thursday, June 13th 2024, 9:43:30 am
PWD UttarakahndPhoto (ID 43993) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 18
Remark : RCC bridge
on Thursday, June 20th 2024, 6:30:00 pm
51.86%
Financial Progress
46th Expenditure
of ₹ 1921572 (19.22 Lacs ) done.
Cummulative ₹ 1262.04Lacs ( against 2433.59Lacs )
on Friday, June 21st 2024, 7:42:57 am
PWD UttarakahndPhoto (ID 46199) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : 17.800 Tarad villeage
Remark : RCC slab casting work in progress
on Monday, July 1st 2024, 6:30:00 pm
52.94%
Financial Progress
47th Expenditure
of ₹ 2623078 (26.23 Lacs ) done.
Cummulative ₹ 1288.27Lacs ( against 2433.59Lacs )
on Wednesday, July 3rd 2024, 6:30:00 pm
85%
Physical Progress
Physical Progress Reported at 5th time
on Monday, July 29th 2024, 6:30:00 pm
53.79%
Financial Progress
48th Expenditure
of ₹ 2077370 (20.77 Lacs ) done.
Cummulative ₹ 1309.05Lacs ( against 2433.59Lacs )
on Friday, August 9th 2024, 6:30:00 pm
54.57%
Financial Progress
49th Expenditure
of ₹ 1888396 (18.88 Lacs ) done.
Cummulative ₹ 1327.93Lacs ( against 2433.59Lacs )
on Wednesday, August 14th 2024, 7:23:55 am
PWD UttarakahndPhoto (ID 51907) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : 17.300
Remark : प्रोटेक्शन वर्क एवं पहुंच मार्ग का कार्य प्रगति है
on Thursday, August 15th 2024, 6:30:00 pm
54.58%
Financial Progress
50th Expenditure
of ₹ 24500 (0.24 Lacs ) done.
Cummulative ₹ 1328.18Lacs ( against 2433.59Lacs )
on Tuesday, August 20th 2024, 6:30:00 pm
54.67%
Financial Progress
51st Expenditure
of ₹ 224400 (2.24 Lacs ) done.
Cummulative ₹ 1330.42Lacs ( against 2433.59Lacs )
on Thursday, August 22nd 2024, 6:30:00 pm
54.67%
Financial Progress
52nd Expenditure
of ₹ 13965 (0.14 Lacs ) done.
Cummulative ₹ 1330.56Lacs ( against 2433.59Lacs )
on Monday, September 2nd 2024
Photo (ID 1068) from Site Received
Site Visit By SE Sir
on Wednesday, September 18th 2024, 6:30:00 pm
56.54%
Financial Progress
53rd Expenditure
of ₹ 4551039 (45.51 Lacs ) done.
Cummulative ₹ 1376.07Lacs ( against 2433.59Lacs )
on Monday, September 23rd 2024, 6:30:00 pm
58.22%
Financial Progress
54th Expenditure
of ₹ 4075502 (40.76 Lacs ) done.
Cummulative ₹ 1416.83Lacs ( against 2433.59Lacs )
on Sunday, September 29th 2024, 6:30:00 pm
58.34%
Financial Progress
55th Expenditure
of ₹ 282170 (2.82 Lacs ) done.
Cummulative ₹ 1419.65Lacs ( against 2433.59Lacs )
on Tuesday, October 1st 2024, 11:11:54 am
PWD UttarakahndPhoto (ID 53704) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 20
Remark : Gagas udi Mahadev
on Tuesday, October 1st 2024, 11:28:44 am
PWD UttarakahndPhoto (ID 53705) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 18
Remark : 18 m span bridge
on Tuesday, October 22nd 2024, 6:30:00 pm
59.93%
Financial Progress
56th Expenditure
of ₹ 3878298 (38.78 Lacs ) done.
Cummulative ₹ 1458.43Lacs ( against 2433.59Lacs )
on Friday, November 29th 2024, 6:30:00 pm
60.31%
Financial Progress
57th Expenditure
of ₹ 925955 (9.26 Lacs ) done.
Cummulative ₹ 1467.69Lacs ( against 2433.59Lacs )
on Thursday, December 26th 2024, 6:30:00 pm
62.06%
Financial Progress
58th Expenditure
of ₹ 4260379 (42.60 Lacs ) done.
Cummulative ₹ 1510.29Lacs ( against 2433.59Lacs )
on Monday, December 30th 2024, 6:30:00 pm
65.04%
Financial Progress
59th Expenditure
of ₹ 7253269 (72.53 Lacs ) done.
Cummulative ₹ 1582.83Lacs ( against 2433.59Lacs )
on Monday, January 27th 2025, 6:30:00 pm
63.29%
Financial Progress
60th Expenditure
of ₹ -4260379 (-42.60 Lacs ) done.
Cummulative ₹ 1540.22Lacs ( against 2433.59Lacs )
on Monday, January 27th 2025, 6:30:00 pm
65.33%
Financial Progress
61st Expenditure
of ₹ 4968856 (49.69 Lacs ) done.
Cummulative ₹ 1589.91Lacs ( against 2433.59Lacs )
on Friday, February 21st 2025, 11:57:39 am
PWD UttarakahndPhoto (ID 64869) from Site Received
Uploader : Ram Singh Bhandari, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 17
Remark : Work in progress
on Friday, February 21st 2025, 12:45:49 pm
PWD UttarakahndPhoto (ID 68159) from Site Received
Uploader : Ram Singh Bhandari, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 8
Remark : Box culvert in progress
on Friday, February 21st 2025, 12:47:45 pm
PWD UttarakahndPhoto (ID 68160) from Site Received
Uploader : Ram Singh Bhandari, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 8
Remark : Box culvert in progress
on Sunday, February 23rd 2025, 6:57:51 am
PWD UttarakahndPhoto (ID 68161) from Site Received
Uploader : Ram Singh Bhandari, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 8
Remark : Box culvert slab casting
on Sunday, February 23rd 2025, 6:59:52 am
PWD UttarakahndPhoto (ID 68162) from Site Received
Uploader : Ram Singh Bhandari, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 8
Remark : Box culvert slab casting
on Sunday, February 23rd 2025, 7:02:17 am
PWD UttarakahndPhoto (ID 68163) from Site Received
Uploader : Ram Singh Bhandari, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 8
Remark : Box culvert slab casting
on Sunday, February 23rd 2025, 8:46:04 am
PWD UttarakahndPhoto (ID 68164) from Site Received
Uploader : Ram Singh Bhandari, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 8
Remark : Box culvert slab casting
on Monday, February 24th 2025, 5:42:04 am
PWD UttarakahndPhoto (ID 68165) from Site Received
Uploader : Ram Singh Bhandari, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Box culvert slab casting
Remark : बॉक्स कल्वर्ट की स्लैब कास्टिंग का कार्य प्रगति में है
on Monday, February 24th 2025, 5:44:03 am
PWD UttarakahndPhoto (ID 68166) from Site Received
Uploader : Ram Singh Bhandari, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 8
Remark : Box culvert slab casting
on Monday, February 24th 2025, 10:54:19 am
PWD UttarakahndPhoto (ID 68167) from Site Received
Uploader : Ram Singh Bhandari, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 8
Remark : Box culvert slab casting
on Monday, March 3rd 2025, 6:30:00 pm
66.68%
Financial Progress
62nd Expenditure
of ₹ 3282242 (32.82 Lacs ) done.
Cummulative ₹ 1622.73Lacs ( against 2433.59Lacs )
on Wednesday, March 5th 2025, 6:30:00 pm
67.51%
Financial Progress
63rd Expenditure
of ₹ 2025516 (20.26 Lacs ) done.
Cummulative ₹ 1642.99Lacs ( against 2433.59Lacs )
on Sunday, March 30th 2025, 6:30:00 pm
69.20%
Financial Progress
64th Expenditure
of ₹ 4114275 (41.14 Lacs ) done.
Cummulative ₹ 1684.13Lacs ( against 2433.59Lacs )
on Wednesday, May 28th 2025, 6:30:00 pm
71.14%
Financial Progress
65th Expenditure
of ₹ 4720431 (47.20 Lacs ) done.
Cummulative ₹ 1731.34Lacs ( against 2433.59Lacs )
on Friday, June 20th 2025, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 6th time
on Wednesday, July 2nd 2025, 6:30:00 pm
71.19%
Financial Progress
66th Expenditure
of ₹ 121244 (1.21 Lacs ) done.
Cummulative ₹ 1732.55Lacs ( against 2433.59Lacs )
on Wednesday, July 30th 2025, 6:30:00 pm
71.25%
Financial Progress
67th Expenditure
of ₹ 141673 (1.42 Lacs ) done.
Cummulative ₹ 1733.97Lacs ( against 2433.59Lacs )
on Friday, August 29th 2025, 6:30:00 pm
71.39%
Financial Progress
68th Expenditure
of ₹ 327500 (3.27 Lacs ) done.
Cummulative ₹ 1737.24Lacs ( against 2433.59Lacs )