on Tuesday, October 26th 2021, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा सं0 68/2021 के अन्तर्गत जनपद अल्मोड़ा के तहसील कार्यालय सल्ट खुमाड़ के आवासीय/अनावासीय भ्ज्ञवनों की रिपेयरिगं का कार्य।
on Friday, June 2nd 2023, 6:30:00 pm
5%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, July 25th 2023, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, November 29th 2023, 6:30:00 pm
24.14%
Financial Progress
1st Expenditure
of ₹ 4393776 (43.94 Lacs ) done.
Cummulative ₹ 43.94Lacs ( against 182.02Lacs )
on Saturday, December 30th 2023, 5:05:13 am
PWD UttarakahndPhoto (ID 34047) from Site Received
Uploader : Dharmendra Kumar Sharma, JE Civil (Samvida) ,PD Ranikhet
Landmark : Tehsil building khumad
Remark : Tehsil building khumad garrage work
on Saturday, March 30th 2024, 6:30:00 pm
52.79%
Financial Progress
2nd Expenditure
of ₹ 5214357 (52.14 Lacs ) done.
Cummulative ₹ 96.08Lacs ( against 182.02Lacs )
on Monday, April 8th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time