on Monday, May 15th 2023, 6:30:00 pm
Work Sanctioned
जनपद अल्मोड़ा के विधान सभा क्षेत्र रानीखेत के अन्तर्गत भुजान-चापड़-हिह़ाम मोटर मार्ग का अनुरक्षण का कार्य।
on Monday, June 5th 2023, 7:29:15 am
Technical Sanction
of ₹ 420.25 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 3128/15Yata-Aa/2023 Date 05.06.2023
on Monday, July 24th 2023, 6:32:01 am
PWD UttarakahndPhoto (ID 24581) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 17
Remark : Premix Carpet work in progress
on Monday, September 25th 2023, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, September 26th 2023, 6:30:00 pm
14%
Physical Progress
Physical Progress Reported at 2nd time
on Saturday, October 7th 2023, 10:17:26 pm
PWD UttarakahndPhoto (ID 24580) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 17
Remark : Premix Carpet work under progress
on Sunday, October 8th 2023, 2:16:03 am
PWD UttarakahndPhoto (ID 24582) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 17
Remark : Premix Carpet work in progress
on Sunday, October 8th 2023, 2:38:31 am
PWD UttarakahndPhoto (ID 24585) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 19
Remark : PC work
on Sunday, October 8th 2023, 2:50:50 am
PWD UttarakahndPhoto (ID 24587) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 19
Remark : Premix Carpet work in progress
on Sunday, October 8th 2023, 5:07:20 am
PWD UttarakahndPhoto (ID 24603) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 20
Remark : Premix Carpet work in progress
on Tuesday, October 10th 2023, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 3rd time
on Friday, October 13th 2023, 2:46:01 am
PWD UttarakahndPhoto (ID 25030) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 17.500
Remark : Premix Carpet
on Friday, October 13th 2023, 2:56:33 am
PWD UttarakahndPhoto (ID 25032) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 16.500
Remark : Tack coat testing
on Friday, October 13th 2023, 2:59:47 am
PWD UttarakahndPhoto (ID 25042) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 16.500
Remark : Premix Carpet
on Friday, October 13th 2023, 3:00:14 am
PWD UttarakahndPhoto (ID 25039) from Site Received
Uploader : Kundan Singh, Assistant Engineer Civil ,PD Bageshwar
Landmark : Km 17
Remark : PC work in Km 17 is in progress
on Thursday, October 19th 2023, 1:36:49 am
PWD UttarakahndPhoto (ID 25531) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 20
Remark : Premix Carpet work in progress
on Sunday, October 22nd 2023, 4:52:48 am
PWD UttarakahndPhoto (ID 25532) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 20
Remark : Premix Carpet work in progress
on Monday, October 23rd 2023, 4:08:46 am
PWD UttarakahndPhoto (ID 25595) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 12
Remark : Measurements work
on Monday, October 23rd 2023, 4:10:38 am
PWD UttarakahndPhoto (ID 25596) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 12
Remark : Measurements
on Monday, October 23rd 2023, 6:24:04 am
PWD UttarakahndPhoto (ID 25604) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 17
Remark : Premix Carpet Measurements
on Thursday, October 26th 2023, 12:32:12 am
PWD UttarakahndPhoto (ID 25687) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 8
Remark : Premix Carpet work
on Thursday, October 26th 2023, 1:08:49 am
PWD UttarakahndPhoto (ID 25693) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 1
Remark : Premix Carpet work in progress
on Thursday, October 26th 2023, 1:42:19 am
PWD UttarakahndPhoto (ID 25696) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 5
Remark : Retaining Wall work in progress
on Thursday, October 26th 2023, 2:13:45 am
PWD UttarakahndPhoto (ID 25701) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 8
Remark : Premix Carpet work in progress
on Thursday, October 26th 2023, 3:35:04 am
PWD UttarakahndPhoto (ID 25721) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 19
Remark : Measurements Work
on Thursday, October 26th 2023, 3:37:16 am
PWD UttarakahndPhoto (ID 25723) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : K.m.19
Remark : Measurements Work
on Thursday, October 26th 2023, 4:23:02 am
PWD UttarakahndPhoto (ID 25726) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : K.M.21
Remark : Measurements Work
on Thursday, October 26th 2023, 4:25:09 am
PWD UttarakahndPhoto (ID 25727) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : K.M.21
Remark : Measurements Work
on Tuesday, October 31st 2023, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 4th time
on Wednesday, November 29th 2023, 6:30:00 pm
28.21%
Financial Progress
1st Expenditure
of ₹ 11854503 (118.55 Lacs ) done.
Cummulative ₹ 118.55Lacs ( against 420.25Lacs )
on Wednesday, December 6th 2023, 6:30:00 pm
45.16%
Financial Progress
2nd Expenditure
of ₹ 7125312 (71.25 Lacs ) done.
Cummulative ₹ 189.80Lacs ( against 420.25Lacs )
on Wednesday, December 13th 2023, 6:30:00 pm
99%
Physical Progress
Physical Progress Reported at 5th time
on Friday, January 26th 2024, 6:30:00 pm
53.70%
Financial Progress
3rd Expenditure
of ₹ 3589686 (35.90 Lacs ) done.
Cummulative ₹ 225.70Lacs ( against 420.25Lacs )
on Sunday, February 11th 2024, 6:30:00 pm
72.23%
Financial Progress
4th Expenditure
of ₹ 7783090 (77.83 Lacs ) done.
Cummulative ₹ 303.53Lacs ( against 420.25Lacs )
on Thursday, June 6th 2024, 12:28:04 am
PWD UttarakahndPhoto (ID 41819) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 28
Remark : One Time Maintenence
on Thursday, June 6th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 6th time
on Wednesday, July 31st 2024, 12:33:18 am
PWD UttarakahndPhoto (ID 51408) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 8 (750)
Remark : Measurements
on Wednesday, July 31st 2024, 1:50:39 am
PWD UttarakahndPhoto (ID 51430) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 11(150)
Remark : Measurements
on Wednesday, July 31st 2024, 4:23:19 am
PWD UttarakahndPhoto (ID 51431) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 14 (2-4)
Remark : Measurements
on Saturday, August 3rd 2024, 12:28:53 am
PWD UttarakahndPhoto (ID 51560) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 17 (4-6)
Remark : Measurements
on Saturday, August 3rd 2024, 12:36:45 am
PWD UttarakahndPhoto (ID 51558) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 17(8-10)
Remark : Measurements
on Saturday, August 3rd 2024, 5:28:40 am
PWD UttarakahndPhoto (ID 51561) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 26 (2-4)
Remark : Measurements
on Saturday, August 3rd 2024, 5:29:41 am
PWD UttarakahndPhoto (ID 51563) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 27 (2-4)
Remark : Measurements
on Saturday, August 3rd 2024, 5:50:22 am
PWD UttarakahndPhoto (ID 51577) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : 27 (4-6)
Remark : Measurements
on Saturday, August 3rd 2024, 6:08:27 am
PWD UttarakahndPhoto (ID 51578) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 28 (0-2)
Remark : Measurements
on Saturday, August 3rd 2024, 6:18:13 am
PWD UttarakahndPhoto (ID 51579) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 28(4-5)
Remark : Measurements
on Wednesday, August 21st 2024, 12:38:43 am
PWD UttarakahndPhoto (ID 52195) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 90(0-2)
Remark : Measurements
on Wednesday, August 21st 2024, 1:05:28 am
PWD UttarakahndPhoto (ID 52196) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 12(0-2)
Remark : Measurements
on Sunday, September 22nd 2024, 6:30:00 pm
72.23%
Financial Progress
5th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 303.53Lacs ( against 420.25Lacs )
on Monday, September 23rd 2024, 6:30:00 pm
84.00%
Financial Progress
6th Expenditure
of ₹ 4950168 (49.50 Lacs ) done.
Cummulative ₹ 353.03Lacs ( against 420.25Lacs )
on Sunday, September 29th 2024, 6:30:00 pm
84.03%
Financial Progress
7th Expenditure
of ₹ 8800 (0.09 Lacs ) done.
Cummulative ₹ 353.12Lacs ( against 420.25Lacs )
on Saturday, October 12th 2024, 3:07:57 am
PWD UttarakahndPhoto (ID 55871) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 14(0-2)
Remark : Cross Warrier work
on Friday, November 29th 2024, 6:30:00 pm
84.07%
Financial Progress
8th Expenditure
of ₹ 19812 (0.20 Lacs ) done.
Cummulative ₹ 353.31Lacs ( against 420.25Lacs )
on Sunday, December 15th 2024, 6:30:00 pm
97.26%
Financial Progress
9th Expenditure
of ₹ 5542486 (55.42 Lacs ) done.
Cummulative ₹ 408.74Lacs ( against 420.25Lacs )
on Monday, December 30th 2024, 6:30:00 pm
97.26%
Financial Progress
10th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 408.74Lacs ( against 420.25Lacs )
on Sunday, March 30th 2025, 6:30:00 pm
98.95%
Financial Progress
11th Expenditure
of ₹ 709346 (7.09 Lacs ) done.
Cummulative ₹ 415.83Lacs ( against 420.25Lacs )