Work Sanctioned
सड़क सुरक्षा योजना वर्ष 2022-23 के अन्तर्गत जनपद अल्मोड़ा के विधानसभा क्षेत्र सल्ट के प्रा0ख0 लो0नि0वि0 रानीखेत में अन्य जिला मार्गो में सड़क सुरक्षा के अन्तर्गत कै्रश बैरियर, पैरापिट, साईनेज का कार्य।
on Thursday, January 18th 2024, 6:30:00 pm
51.42%
Financial Progress
1st Expenditure
of ₹ 4904927 (49.05 Lacs ) done.
Cummulative ₹ 49.05Lacs ( against 95.39Lacs )
on Sunday, February 11th 2024, 6:30:00 pm
75.50%
Financial Progress
2nd Expenditure
of ₹ 2297354 (22.97 Lacs ) done.
Cummulative ₹ 72.02Lacs ( against 95.39Lacs )
on Monday, February 12th 2024, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 1st time
on Monday, February 26th 2024, 12:02:16 pm
PWD UttarakahndPhoto (ID 36316) from Site Received
Uploader : Kundan Singh, Assistant Engineer Civil ,PD Bageshwar
Landmark : Km 1 of Chaubatia Kunelakhet Bamseu motor road
Remark : Checking thickness of W beam used in road safety work
on Wednesday, March 20th 2024, 6:30:00 pm
51.42%
Financial Progress
3rd Expenditure
of ₹ -2297354 (-22.97 Lacs ) done.
Cummulative ₹ 49.05Lacs ( against 95.39Lacs )
on Wednesday, March 27th 2024, 6:30:00 pm
94.87%
Financial Progress
4th Expenditure
of ₹ 4144493 (41.44 Lacs ) done.
Cummulative ₹ 90.49Lacs ( against 95.39Lacs )
on Saturday, June 1st 2024, 7:19:42 am
PWD UttarakahndPhoto (ID 47086) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : 3.550
Remark : Gauge checking of W Metal beqm Crash barrier & sign board under Road Safety work
on Friday, June 28th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, October 8th 2024, 12:02:38 pm
PWD UttarakahndPhoto (ID 54668) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km1(6-8)
Remark : Third party of quality control check deployed by HOD office for road safety work taking sample from Km1 hec.6-8of Ganiyadholi singoli amyadi Motor road.
on Wednesday, October 9th 2024, 10:20:15 am
PWD UttarakahndPhoto (ID 55056) from Site Received
Uploader : Chetan Rawal, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 4HM (4-6) Pasiya peepna Motor Road (ODR)
Remark : Third party of quality control check deployed by HOD office for road safety work.taking sample from KM 4(4-6) of Pasiya peepna Motor road.
on Thursday, October 10th 2024, 3:20:36 am
PWD UttarakahndPhoto (ID 55194) from Site Received
Uploader : Chetan Rawal, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 1(8-10)Block office syaldey road
Remark : Third party of quality control check deployed by HOD office for road safety work.taking sample from KM 1(8-10) of block office syaldey ODR road.
on Thursday, October 10th 2024, 4:23:36 am
PWD UttarakahndPhoto (ID 55213) from Site Received
Uploader : Chetan Rawal, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Deghat khldua motor road km 1(8-10)
Remark : Third party of quality control check deployed by HOD office for road safety work.taking sample from Deghat khldua motor road km 1(8-10)
on Wednesday, May 14th 2025, 6:30:00 pm
96.08%
Financial Progress
5th Expenditure
of ₹ 115286 (1.15 Lacs ) done.
Cummulative ₹ 91.65Lacs ( against 95.39Lacs )