Work Sanctioned
जनपद रुद्रप्रयाग के विधान सभा क्षेत्र केदारनाथ के अन्तर्गत ऊखीमठ-मनसूना- जगासू- राऊलैक-उनियाणा मोटर मार्ग के सुधारीकरण का कार्य।

2 years ago

on Wednesday, September 20th 2023, 6:30:00 pm
1.51%
Financial Progress

1st Expenditure
of ₹ 743000 (7.43 Lacs ) done.
Cummulative ₹ 7.43Lacs ( against 493.33Lacs )

2 years ago

on Monday, November 20th 2023, 6:30:00 pm
2.75%
Financial Progress

2nd Expenditure
of ₹ 613000 (6.13 Lacs ) done.
Cummulative ₹ 13.56Lacs ( against 493.33Lacs )

2 years ago

on Friday, December 15th 2023, 6:30:00 pm
24.73%
Financial Progress

3rd Expenditure
of ₹ 10843000 (108.43 Lacs ) done.
Cummulative ₹ 121.99Lacs ( against 493.33Lacs )

2 years ago

on Monday, December 18th 2023, 6:30:00 pm
20%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Thursday, February 8th 2024, 6:30:00 pm
38.07%
Financial Progress

4th Expenditure
of ₹ 6580000 (65.80 Lacs ) done.
Cummulative ₹ 187.79Lacs ( against 493.33Lacs )

2 years ago

on Thursday, February 15th 2024, 6:30:00 pm
39.83%
Financial Progress

5th Expenditure
of ₹ 872000 (8.72 Lacs ) done.
Cummulative ₹ 196.51Lacs ( against 493.33Lacs )

2 years ago

on Thursday, March 21st 2024, 6:30:00 pm
44.27%
Financial Progress

6th Expenditure
of ₹ 2189000 (21.89 Lacs ) done.
Cummulative ₹ 218.40Lacs ( against 493.33Lacs )

a year ago

on Monday, April 15th 2024, 6:30:00 pm
44.27%
Financial Progress

7th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 218.40Lacs ( against 493.33Lacs )

a year ago

on Monday, April 29th 2024, 6:30:00 pm
47.99%
Financial Progress

8th Expenditure
of ₹ 1835695 (18.36 Lacs ) done.
Cummulative ₹ 236.76Lacs ( against 493.33Lacs )

a year ago

on Saturday, May 4th 2024, 6:43:37 am
<span class="4">Picture Id:37852</span>
PWD Uttarakahnd
Photo (ID 37852) from Site Received
Uploader : Manoj Kumar Bhatt, Executive Engineer Civil ,TD Berinaag
Landmark : Ch 7.600 ukhimath Mansoona road
Remark : One time maintenance PC work

a year ago

on Saturday, May 4th 2024, 6:47:56 am
<span class="4">Picture Id:37847</span>
PWD Uttarakahnd
Photo (ID 37847) from Site Received
Uploader : Narendra Kumar, Assistant Engineer Civil ,CD Ukhimath
Landmark : 7.600
Remark : One time maintenance pc work

a year ago

on Saturday, May 4th 2024, 6:50:27 am
<span class="4">Picture Id:37857</span>
PWD Uttarakahnd
Photo (ID 37857) from Site Received
Uploader : Narendra Kumar, Assistant Engineer Civil ,CD Ukhimath
Landmark : 7.60 ukhimath mansuna uniyana road
Remark : Crash barrier thickness W metal beam. 3mm

a year ago

on Saturday, May 4th 2024, 6:59:39 am
<span class="4">Picture Id:37853</span>
PWD Uttarakahnd
Photo (ID 37853) from Site Received
Uploader : Manoj Kumar Bhatt, Executive Engineer Civil ,TD Berinaag
Landmark : 7.60 ukhimath mansuna road
Remark : Rolling of PC ukhimath mansoona ch 7.600 km

a year ago

on Sunday, May 5th 2024, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Tuesday, May 21st 2024, 7:28:55 am
<span class="4">Picture Id:39472</span>
PWD Uttarakahnd
Photo (ID 39472) from Site Received
Uploader : Manoj Kumar Bhatt, Executive Engineer Civil ,TD Berinaag
Landmark : Km10 Ch 9.730 to ch 9.740 km
Remark : Inspection of pc work (otm)

a year ago

on Tuesday, May 21st 2024, 7:35:56 am
<span class="4">Picture Id:39473</span>
PWD Uttarakahnd
Photo (ID 39473) from Site Received
Uploader : Manoj Kumar Bhatt, Executive Engineer Civil ,TD Berinaag
Landmark : Km 10 ch 9.730 to 9.740 Km
Remark : Inspection of pc work (otm)

a year ago

on Friday, May 31st 2024, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Sunday, June 9th 2024, 6:30:00 pm
48.06%
Financial Progress

9th Expenditure
of ₹ 31500 (0.32 Lacs ) done.
Cummulative ₹ 237.07Lacs ( against 493.33Lacs )

a year ago

on Monday, June 10th 2024, 6:30:00 pm
60.52%
Financial Progress

10th Expenditure
of ₹ 6147383 (61.47 Lacs ) done.
Cummulative ₹ 298.55Lacs ( against 493.33Lacs )

a year ago

on Tuesday, June 18th 2024, 7:05:00 am
<span class="4">Picture Id:45762</span>
PWD Uttarakahnd
Photo (ID 45762) from Site Received
Uploader : Narendra Kumar, Assistant Engineer Civil ,CD Ukhimath
Landmark : 11.550
Remark : Pc work and crash barriers fix

a year ago

on Thursday, June 27th 2024, 10:33:37 am
<span class="4">Picture Id:47915</span>
PWD Uttarakahnd
Photo (ID 47915) from Site Received
Uploader : Narendra Kumar, Assistant Engineer Civil ,CD Ukhimath
Landmark : 13.400
Remark : Pc work balance area

a year ago

on Thursday, June 27th 2024, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 4th time

a year ago

on Friday, July 5th 2024, 5:24:24 am
<span class="4">Picture Id:50294</span>
PWD Uttarakahnd
Photo (ID 50294) from Site Received
Uploader : Narendra Kumar, Assistant Engineer Civil ,CD Ukhimath
Landmark : 6.125
Remark : Pc chacking

a year ago

on Wednesday, July 24th 2024, 6:30:00 pm
60.52%
Financial Progress

11th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 298.55Lacs ( against 493.33Lacs )

a year ago

on Thursday, July 25th 2024, 6:30:00 pm
60.92%
Financial Progress

12th Expenditure
of ₹ 199597 (2.00 Lacs ) done.
Cummulative ₹ 300.54Lacs ( against 493.33Lacs )

a year ago

on Monday, July 29th 2024, 6:30:00 pm
72.10%
Financial Progress

13th Expenditure
of ₹ 5512743 (55.13 Lacs ) done.
Cummulative ₹ 355.67Lacs ( against 493.33Lacs )

a year ago

on Wednesday, August 21st 2024, 6:30:00 pm
72.05%
Financial Progress

14th Expenditure
of ₹ -20921 (-0.21 Lacs ) done.
Cummulative ₹ 355.46Lacs ( against 493.33Lacs )

a year ago

on Thursday, August 22nd 2024, 6:30:00 pm
72.10%
Financial Progress

15th Expenditure
of ₹ 20921 (0.21 Lacs ) done.
Cummulative ₹ 355.67Lacs ( against 493.33Lacs )

a year ago

on Thursday, August 22nd 2024, 6:30:00 pm
72.14%
Financial Progress

16th Expenditure
of ₹ 20921 (0.21 Lacs ) done.
Cummulative ₹ 355.88Lacs ( against 493.33Lacs )

a year ago

on Tuesday, August 27th 2024, 6:30:00 pm
72.75%
Financial Progress

17th Expenditure
of ₹ 300426 (3.00 Lacs ) done.
Cummulative ₹ 358.88Lacs ( against 493.33Lacs )

a year ago

on Tuesday, August 27th 2024, 6:30:00 pm
72.81%
Financial Progress

18th Expenditure
of ₹ 29763 (0.30 Lacs ) done.
Cummulative ₹ 359.18Lacs ( against 493.33Lacs )

a year ago

on Tuesday, August 27th 2024, 6:30:00 pm
72.93%
Financial Progress

19th Expenditure
of ₹ 59029 (0.59 Lacs ) done.
Cummulative ₹ 359.77Lacs ( against 493.33Lacs )

a year ago

on Thursday, October 24th 2024, 6:30:00 pm
73.15%
Financial Progress

20th Expenditure
of ₹ 112100 (1.12 Lacs ) done.
Cummulative ₹ 360.89Lacs ( against 493.33Lacs )

a year ago

on Sunday, October 27th 2024, 6:30:00 pm
73.57%
Financial Progress

21st Expenditure
of ₹ 207308 (2.07 Lacs ) done.
Cummulative ₹ 362.96Lacs ( against 493.33Lacs )

a year ago

on Tuesday, November 12th 2024, 6:30:00 pm
76.61%
Financial Progress

22nd Expenditure
of ₹ 1500000 (15.00 Lacs ) done.
Cummulative ₹ 377.96Lacs ( against 493.33Lacs )

a year ago

on Friday, November 22nd 2024, 6:30:00 pm
76.61%
Financial Progress

23rd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 377.96Lacs ( against 493.33Lacs )

10 months ago

on Wednesday, November 27th 2024, 6:30:00 pm
76.95%
Financial Progress

24th Expenditure
of ₹ 165071 (1.65 Lacs ) done.
Cummulative ₹ 379.62Lacs ( against 493.33Lacs )

10 months ago

on Wednesday, November 27th 2024, 6:30:00 pm
77.00%
Financial Progress

25th Expenditure
of ₹ 25245 (0.25 Lacs ) done.
Cummulative ₹ 379.87Lacs ( against 493.33Lacs )

10 months ago

on Monday, December 2nd 2024, 6:30:00 pm
95%

Physical Progress
Physical Progress Reported at 5th time

9 months ago

on Wednesday, December 25th 2024, 6:30:00 pm
77.60%
Financial Progress

26th Expenditure
of ₹ 293389 (2.93 Lacs ) done.
Cummulative ₹ 382.80Lacs ( against 493.33Lacs )

9 months ago

on Sunday, December 29th 2024, 6:30:00 pm
77.70%
Financial Progress

27th Expenditure
of ₹ 52061 (0.52 Lacs ) done.
Cummulative ₹ 383.32Lacs ( against 493.33Lacs )

9 months ago

on Sunday, December 29th 2024, 6:30:00 pm
81.00%
Financial Progress

28th Expenditure
of ₹ 1625942 (16.26 Lacs ) done.
Cummulative ₹ 399.58Lacs ( against 493.33Lacs )

9 months ago

on Tuesday, January 21st 2025, 6:30:00 pm
81.05%
Financial Progress

29th Expenditure
of ₹ 23880 (0.24 Lacs ) done.
Cummulative ₹ 399.82Lacs ( against 493.33Lacs )

8 months ago

on Tuesday, January 28th 2025, 6:30:00 pm
81.19%
Financial Progress

30th Expenditure
of ₹ 70067 (0.70 Lacs ) done.
Cummulative ₹ 400.52Lacs ( against 493.33Lacs )

7 months ago

on Monday, March 17th 2025, 6:30:00 pm
81.31%
Financial Progress

31st Expenditure
of ₹ 59021 (0.59 Lacs ) done.
Cummulative ₹ 401.11Lacs ( against 493.33Lacs )

7 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
92.02%
Financial Progress

32nd Expenditure
of ₹ 5287067 (52.87 Lacs ) done.
Cummulative ₹ 453.98Lacs ( against 493.33Lacs )

6 months ago

on Friday, March 28th 2025, 6:30:00 pm
95.48%
Financial Progress

34th Expenditure
of ₹ 5760 (0.06 Lacs ) done.
Cummulative ₹ 471.04Lacs ( against 493.33Lacs )

6 months ago

on Friday, March 28th 2025, 6:30:00 pm
95.47%
Financial Progress

33rd Expenditure
of ₹ 1700000 (17.00 Lacs ) done.
Cummulative ₹ 470.98Lacs ( against 493.33Lacs )

6 months ago

on Friday, April 11th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 6th time

a month ago

on Monday, August 25th 2025, 6:30:00 pm
97.31%
Financial Progress

35th Expenditure
of ₹ 903945 (9.04 Lacs ) done.
Cummulative ₹ 480.08Lacs ( against 493.33Lacs )