Work Sanctioned
रा॰मा॰ स॰ 107 के कि॰मी॰ 62 से तरसाली तक मोटर मार्ग नव निर्माण कार्य से एन॰एच॰-107 पर हुई क्षतियों का सुधारीकरण कार्य।
on Friday, September 6th 2024, 6:30:00 pm
43.33%
Financial Progress
1st Expenditure
of ₹ 649999 (6.50 Lacs ) done.
Cummulative ₹ 6.50Lacs ( against 15Lacs )
on Thursday, September 19th 2024, 6:30:00 pm
43.33%
Financial Progress
2nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 6.50Lacs ( against 15Lacs )
on Thursday, February 6th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time