on Sunday, November 5th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद टिहरी गढ़वाल के विधानसभा क्षेत्र प्रतापनगर में भेनगी से वाया कोलधार का मिसिंग लिंक मो0 मार्ग का नव निर्माण कार्य प्रथम चरण

a year ago

on Friday, March 29th 2024, 6:30:00 pm
2.71%
Financial Progress

1st Expenditure
of ₹ 20306 (0.20 Lacs ) done.
Cummulative ₹ 0.20Lacs ( against 7.5Lacs )

9 months ago

on Thursday, December 5th 2024, 6:30:00 pm
5%

Physical Progress
Physical Progress Reported at 1st time

8 months ago

on Thursday, January 9th 2025, 9:02:24 am
<span class="4">Picture Id:62523</span>
PWD Uttarakahnd
Photo (ID 62523) from Site Received
Uploader : Bipin Kumar, Additional Assistant Engineer Civil ,PD New Tehri
Landmark : Bhengi
Remark : Site visit for the feasible options of alignment of road. Dispute regarding NOC for land, as maximum land will be acquired of Bhengi(start point at KM 28 of SH 69)and benefit of road to Koldhar.