Refresh data
on Sunday, January 14th 2024, 6:30:00 pm
Work Sanctioned
पी0एम0जी0एस0वाई0 से हस्तान्तरित जनपद टिहरी गढवाल के विधानसभा क्षेत्र प्रतापनगर में प्रतापनगर मो0 मार्ग के किमी0 33 से बुरन्ट मो0 मार्ग का नवीनीकरण एवं मरम्मत कार्य
on Monday, October 7th 2024, 7:55:26 am
PWD UttarakahndPhoto (ID 54678) from Site Received
Uploader : Ashok Chauhan, Assistant Engineer Civil ,PD New Tehri
Landmark : 6+600
Remark : Catchpit and Abutment walls of scupper
on Monday, October 7th 2024, 7:59:12 am
PWD UttarakahndPhoto (ID 54679) from Site Received
Uploader : Ashok Chauhan, Assistant Engineer Civil ,PD New Tehri
Landmark : 6+600
Remark : Curing work of Slab casted.
on Wednesday, November 6th 2024, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, December 4th 2024, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, December 24th 2024, 6:30:00 pm
0.00%
Financial Progress
1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 186.48Lacs )
on Sunday, December 29th 2024, 6:30:00 pm
19.49%
Financial Progress
2nd Expenditure
of ₹ 3634081 (36.34 Lacs ) done.
Cummulative ₹ 36.34Lacs ( against 186.48Lacs )
on Wednesday, March 19th 2025, 8:45:10 am
PWD UttarakahndPhoto (ID 66114) from Site Received
Uploader : Ashok Chauhan, Assistant Engineer Civil ,PD New Tehri
Landmark : KM10
Remark : PC work completed.
on Wednesday, March 19th 2025, 9:03:32 am
PWD UttarakahndPhoto (ID 66128) from Site Received
Uploader : Ashok Chauhan, Assistant Engineer Civil ,PD New Tehri
Landmark : KM8
Remark : Tack coat and PC work .
on Tuesday, April 8th 2025, 6:30:00 pm
95%
Physical Progress
Physical Progress Reported at 3rd time
on Tuesday, June 24th 2025, 6:30:00 pm
85.71%
Financial Progress
3rd Expenditure
of ₹ 12348928 (123.49 Lacs ) done.
Cummulative ₹ 159.83Lacs ( against 186.48Lacs )