Work Sanctioned
मा0 मुख्यमंत्री जी घोषणा सं0 178/2020 के अन्तर्गत जनपद टिहरी गढ़वाल के विधानसभा क्षेत्र प्रतापनगर में पिलानीधार से ओणेश्वर महादेव मोटर मार्ग का चैडीकरण एवं डामरीकरण कार्य
on Friday, February 9th 2024, 11:24:44 am
Technical Sanction
of ₹ 143.18 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 756/666c-8/2022 dt 09-02-2024
on Saturday, March 30th 2024, 6:30:00 pm
25.21%
Financial Progress
1st Expenditure
of ₹ 3608963 (36.09 Lacs ) done.
Cummulative ₹ 36.09Lacs ( against 143.18Lacs )
on Monday, April 22nd 2024, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, April 30th 2024, 6:30:00 pm
25.21%
Financial Progress
2nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 36.09Lacs ( against 143.18Lacs )
on Tuesday, May 7th 2024, 6:30:00 pm
53.44%
Financial Progress
3rd Expenditure
of ₹ 4043045 (40.43 Lacs ) done.
Cummulative ₹ 76.52Lacs ( against 143.18Lacs )
on Tuesday, May 28th 2024, 6:30:00 pm
54.00%
Financial Progress
5th Expenditure
of ₹ 27900 (0.28 Lacs ) done.
Cummulative ₹ 77.32Lacs ( against 143.18Lacs )
on Tuesday, May 28th 2024, 6:30:00 pm
53.81%
Financial Progress
4th Expenditure
of ₹ 51938 (0.52 Lacs ) done.
Cummulative ₹ 77.04Lacs ( against 143.18Lacs )
on Monday, June 3rd 2024, 6:30:00 pm
54.14%
Financial Progress
6th Expenditure
of ₹ 19436 (0.19 Lacs ) done.
Cummulative ₹ 77.51Lacs ( against 143.18Lacs )
on Tuesday, June 25th 2024, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 2nd time
on Friday, June 28th 2024, 11:46:10 am
PWD UttarakahndPhoto (ID 48372) from Site Received
Uploader : Yogesh Kumar N, Executive Engineer Civil ,PD New Tehri
Landmark : Km1.00
Remark : PC work completed
on Friday, June 28th 2024, 6:30:00 pm
95%
Physical Progress
Physical Progress Reported at 3rd time
on Monday, August 5th 2024, 6:30:00 pm
54.14%
Financial Progress
7th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 77.51Lacs ( against 143.18Lacs )
on Tuesday, August 13th 2024, 6:30:00 pm
54.55%
Financial Progress
9th Expenditure
of ₹ 43753 (0.44 Lacs ) done.
Cummulative ₹ 78.10Lacs ( against 143.18Lacs )
on Tuesday, August 13th 2024, 6:30:00 pm
79.28%
Financial Progress
10th Expenditure
of ₹ 3542157 (35.42 Lacs ) done.
Cummulative ₹ 113.52Lacs ( against 143.18Lacs )
on Tuesday, August 13th 2024, 6:30:00 pm
54.24%
Financial Progress
8th Expenditure
of ₹ 14737 (0.15 Lacs ) done.
Cummulative ₹ 77.66Lacs ( against 143.18Lacs )
on Thursday, August 15th 2024, 6:30:00 pm
79.51%
Financial Progress
12th Expenditure
of ₹ 3986 (0.04 Lacs ) done.
Cummulative ₹ 113.84Lacs ( against 143.18Lacs )
on Thursday, August 15th 2024, 6:30:00 pm
79.48%
Financial Progress
11th Expenditure
of ₹ 27900 (0.28 Lacs ) done.
Cummulative ₹ 113.80Lacs ( against 143.18Lacs )
on Sunday, September 29th 2024, 6:30:00 pm
79.58%
Financial Progress
13th Expenditure
of ₹ 9912 (0.10 Lacs ) done.
Cummulative ₹ 113.94Lacs ( against 143.18Lacs )
on Wednesday, October 23rd 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 4th time
on Thursday, December 19th 2024, 6:30:00 pm
87.32%
Financial Progress
14th Expenditure
of ₹ 1108649 (11.09 Lacs ) done.
Cummulative ₹ 125.02Lacs ( against 143.18Lacs )
on Sunday, December 29th 2024, 6:30:00 pm
95.02%
Financial Progress
15th Expenditure
of ₹ 1102072 (11.02 Lacs ) done.
Cummulative ₹ 136.04Lacs ( against 143.18Lacs )
on Wednesday, February 12th 2025, 8:25:44 am
PWD UttarakahndPhoto (ID 64327) from Site Received
Uploader : Satish Chandra Bhatt, Assistant Engineer Civil ,PD New Tehri
Landmark : 2.100
Remark : Work in progress
on Wednesday, February 12th 2025, 8:26:51 am
PWD UttarakahndPhoto (ID 64329) from Site Received
Uploader : Satish Chandra Bhatt, Assistant Engineer Civil ,PD New Tehri
Landmark : 2.050
Remark : Work in progress
on Monday, February 24th 2025
PWD UttarakahndPhoto (ID 2269) from Site Received
null
on Monday, February 24th 2025
PWD UttarakahndPhoto (ID 2270) from Site Received
null
on Monday, February 24th 2025, 6:30:00 pm
95.24%
Financial Progress
16th Expenditure
of ₹ 32085 (0.32 Lacs ) done.
Cummulative ₹ 136.37Lacs ( against 143.18Lacs )
on Monday, March 17th 2025, 6:30:00 pm
95.68%
Financial Progress
17th Expenditure
of ₹ 62577 (0.63 Lacs ) done.
Cummulative ₹ 136.99Lacs ( against 143.18Lacs )
on Wednesday, March 19th 2025, 6:30:00 pm
95.74%
Financial Progress
18th Expenditure
of ₹ 8496 (0.08 Lacs ) done.
Cummulative ₹ 137.08Lacs ( against 143.18Lacs )