2 years ago

on Tuesday, January 9th 2024, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री जी घोषणा सं0 178/2020 के अन्तर्गत जनपद टिहरी गढ़वाल के विधानसभा क्षेत्र प्रतापनगर में पिलानीधार से ओणेश्वर महादेव मोटर मार्ग का चैडीकरण एवं डामरीकरण कार्य

2 years ago

on Friday, February 9th 2024, 11:24:44 am

Technical Sanction
of ₹ 143.18 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 756/666c-8/2022 dt 09-02-2024

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
25.21%
Financial Progress

1st Expenditure
of ₹ 3608963 (36.09 Lacs ) done.
Cummulative ₹ 36.09Lacs ( against 143.18Lacs )

a year ago

on Monday, April 22nd 2024, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Tuesday, April 30th 2024, 6:30:00 pm
25.21%
Financial Progress

2nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 36.09Lacs ( against 143.18Lacs )

a year ago

on Tuesday, May 7th 2024, 6:30:00 pm
53.44%
Financial Progress

3rd Expenditure
of ₹ 4043045 (40.43 Lacs ) done.
Cummulative ₹ 76.52Lacs ( against 143.18Lacs )

a year ago

on Tuesday, May 28th 2024, 6:30:00 pm
54.00%
Financial Progress

5th Expenditure
of ₹ 27900 (0.28 Lacs ) done.
Cummulative ₹ 77.32Lacs ( against 143.18Lacs )

a year ago

on Tuesday, May 28th 2024, 6:30:00 pm
53.81%
Financial Progress

4th Expenditure
of ₹ 51938 (0.52 Lacs ) done.
Cummulative ₹ 77.04Lacs ( against 143.18Lacs )

a year ago

on Monday, June 3rd 2024, 6:30:00 pm
54.14%
Financial Progress

6th Expenditure
of ₹ 19436 (0.19 Lacs ) done.
Cummulative ₹ 77.51Lacs ( against 143.18Lacs )

a year ago

on Tuesday, June 25th 2024, 6:30:00 pm
25%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Friday, June 28th 2024, 11:46:10 am
<span class="4">Picture Id:48372</span>
PWD Uttarakahnd
Photo (ID 48372) from Site Received
Uploader : Yogesh Kumar N, Executive Engineer Civil ,PD New Tehri
Landmark : Km1.00
Remark : PC work completed

a year ago

on Friday, June 28th 2024, 6:30:00 pm
95%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Monday, August 5th 2024, 6:30:00 pm
54.14%
Financial Progress

7th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 77.51Lacs ( against 143.18Lacs )

a year ago

on Tuesday, August 13th 2024, 6:30:00 pm
54.55%
Financial Progress

9th Expenditure
of ₹ 43753 (0.44 Lacs ) done.
Cummulative ₹ 78.10Lacs ( against 143.18Lacs )

a year ago

on Tuesday, August 13th 2024, 6:30:00 pm
79.28%
Financial Progress

10th Expenditure
of ₹ 3542157 (35.42 Lacs ) done.
Cummulative ₹ 113.52Lacs ( against 143.18Lacs )

a year ago

on Tuesday, August 13th 2024, 6:30:00 pm
54.24%
Financial Progress

8th Expenditure
of ₹ 14737 (0.15 Lacs ) done.
Cummulative ₹ 77.66Lacs ( against 143.18Lacs )

a year ago

on Thursday, August 15th 2024, 6:30:00 pm
79.51%
Financial Progress

12th Expenditure
of ₹ 3986 (0.04 Lacs ) done.
Cummulative ₹ 113.84Lacs ( against 143.18Lacs )

a year ago

on Thursday, August 15th 2024, 6:30:00 pm
79.48%
Financial Progress

11th Expenditure
of ₹ 27900 (0.28 Lacs ) done.
Cummulative ₹ 113.80Lacs ( against 143.18Lacs )

a year ago

on Sunday, September 29th 2024, 6:30:00 pm
79.58%
Financial Progress

13th Expenditure
of ₹ 9912 (0.10 Lacs ) done.
Cummulative ₹ 113.94Lacs ( against 143.18Lacs )

10 months ago

on Wednesday, October 23rd 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 4th time

9 months ago

on Thursday, December 19th 2024, 6:30:00 pm
87.32%
Financial Progress

14th Expenditure
of ₹ 1108649 (11.09 Lacs ) done.
Cummulative ₹ 125.02Lacs ( against 143.18Lacs )

8 months ago

on Sunday, December 29th 2024, 6:30:00 pm
95.02%
Financial Progress

15th Expenditure
of ₹ 1102072 (11.02 Lacs ) done.
Cummulative ₹ 136.04Lacs ( against 143.18Lacs )

7 months ago

on Wednesday, February 12th 2025, 8:25:44 am
<span class="4">Picture Id:64327</span>
PWD Uttarakahnd
Photo (ID 64327) from Site Received
Uploader : Satish Chandra Bhatt, Assistant Engineer Civil ,PD New Tehri
Landmark : 2.100
Remark : Work in progress

7 months ago

on Wednesday, February 12th 2025, 8:26:51 am
<span class="4">Picture Id:64329</span>
PWD Uttarakahnd
Photo (ID 64329) from Site Received
Uploader : Satish Chandra Bhatt, Assistant Engineer Civil ,PD New Tehri
Landmark : 2.050
Remark : Work in progress

6 months ago

on Monday, February 24th 2025
<span class="4">Picture Id: doc2269</span>
PWD Uttarakahnd
Photo (ID 2269) from Site Received
null

6 months ago

on Monday, February 24th 2025
<span class="4">Picture Id: doc2270</span>
PWD Uttarakahnd
Photo (ID 2270) from Site Received
null

6 months ago

on Monday, February 24th 2025, 6:30:00 pm
95.24%
Financial Progress

16th Expenditure
of ₹ 32085 (0.32 Lacs ) done.
Cummulative ₹ 136.37Lacs ( against 143.18Lacs )

6 months ago

on Monday, March 17th 2025, 6:30:00 pm
95.68%
Financial Progress

17th Expenditure
of ₹ 62577 (0.63 Lacs ) done.
Cummulative ₹ 136.99Lacs ( against 143.18Lacs )

6 months ago

on Wednesday, March 19th 2025, 6:30:00 pm
95.74%
Financial Progress

18th Expenditure
of ₹ 8496 (0.08 Lacs ) done.
Cummulative ₹ 137.08Lacs ( against 143.18Lacs )