on Sunday, March 23rd 2008, 6:30:00 pm
Work Sanctioned
खण्डोगी के निकट अन्देणी रा0इ0का0 भरेटीधार मो0 मार्ग
on Saturday, February 28th 2009, 6:30:00 pm
0.04%
Financial Progress
1st Expenditure
of ₹ 5000 (0.05 Lacs ) done.
Cummulative ₹ 0.05Lacs ( against 140Lacs )
on Thursday, February 28th 2013, 6:30:00 pm
3.51%
Financial Progress
2nd Expenditure
of ₹ 486128 (4.86 Lacs ) done.
Cummulative ₹ 4.91Lacs ( against 140Lacs )
on Tuesday, October 31st 2017, 6:30:00 pm
3.89%
Financial Progress
3rd Expenditure
of ₹ 52950 (0.53 Lacs ) done.
Cummulative ₹ 5.44Lacs ( against 140Lacs )
on Monday, December 2nd 2024, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, February 27th 2025, 6:30:00 pm
5.29%
Financial Progress
4th Expenditure
of ₹ 196448 (1.96 Lacs ) done.
Cummulative ₹ 7.41Lacs ( against 140Lacs )
on Tuesday, March 11th 2025, 7:11:39 am
PWD UttarakahndPhoto (ID 65752) from Site Received
Uploader : Deepak Kumar Agarawal, Assistant Engineer Civil ,PD New Tehri
Landmark : 0/27
Remark : Hill side cutting in progress
on Sunday, March 30th 2025, 6:30:00 pm
22.57%
Financial Progress
5th Expenditure
of ₹ 2419700 (24.20 Lacs ) done.
Cummulative ₹ 31.60Lacs ( against 140Lacs )
on Thursday, April 10th 2025, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 2nd time
on Monday, April 28th 2025, 6:58:44 am
PWD UttarakahndPhoto (ID 68528) from Site Received
Uploader : Satish Chandra Bhatt, Assistant Engineer Civil ,PD New Tehri
Landmark : 1.050
Remark : Work in progress
on Monday, April 28th 2025, 10:57:17 am
PWD UttarakahndPhoto (ID 68619) from Site Received
Uploader : Satish Chandra Bhatt, Assistant Engineer Civil ,PD New Tehri
Landmark : 1.400
Remark : Disputed work restarted
on Saturday, May 24th 2025, 8:24:08 am
PWD UttarakahndPhoto (ID 72012) from Site Received
Uploader : Deepak Kumar Agarawal, Assistant Engineer Civil ,PD New Tehri
Landmark : 1/15
Remark : Work inspection by E.E. Sir
on Saturday, May 24th 2025, 8:28:06 am
PWD UttarakahndPhoto (ID 72015) from Site Received
Uploader : Deepak Kumar Agarawal, Assistant Engineer Civil ,PD New Tehri
Landmark : 1/7
Remark : Site visit and discussion with contractor to increase the progress
on Thursday, May 29th 2025, 6:30:00 pm
24.22%
Financial Progress
6th Expenditure
of ₹ 230454 (2.30 Lacs ) done.
Cummulative ₹ 33.91Lacs ( against 140Lacs )
on Thursday, May 29th 2025, 6:30:00 pm
26.06%
Financial Progress
7th Expenditure
of ₹ 257358 (2.57 Lacs ) done.
Cummulative ₹ 36.48Lacs ( against 140Lacs )
on Sunday, June 29th 2025, 6:30:00 pm
26.06%
Financial Progress
8th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 36.48Lacs ( against 140Lacs )
on Friday, July 4th 2025, 6:30:00 pm
27.90%
Financial Progress
9th Expenditure
of ₹ 257358 (2.57 Lacs ) done.
Cummulative ₹ 39.05Lacs ( against 140Lacs )
on Friday, July 4th 2025, 6:30:00 pm
32.90%
Financial Progress
11th Expenditure
of ₹ 197532 (1.98 Lacs ) done.
Cummulative ₹ 46.07Lacs ( against 140Lacs )
on Friday, July 4th 2025, 6:30:00 pm
31.49%
Financial Progress
10th Expenditure
of ₹ 503596 (5.04 Lacs ) done.
Cummulative ₹ 44.09Lacs ( against 140Lacs )
on Sunday, July 6th 2025, 6:30:00 pm
36.09%
Financial Progress
13th Expenditure
of ₹ 158400 (1.58 Lacs ) done.
Cummulative ₹ 50.53Lacs ( against 140Lacs )
on Sunday, July 6th 2025, 6:30:00 pm
34.96%
Financial Progress
12th Expenditure
of ₹ 288000 (2.88 Lacs ) done.
Cummulative ₹ 48.95Lacs ( against 140Lacs )
on Wednesday, September 24th 2025, 6:30:00 pm
36.32%
Financial Progress
14th Expenditure
of ₹ 32085 (0.32 Lacs ) done.
Cummulative ₹ 50.85Lacs ( against 140Lacs )
on Friday, October 17th 2025, 6:30:00 pm
36.44%
Financial Progress
17th Expenditure
of ₹ 5458 (0.05 Lacs ) done.
Cummulative ₹ 51.01Lacs ( against 140Lacs )
on Friday, October 17th 2025, 6:30:00 pm
36.40%
Financial Progress
16th Expenditure
of ₹ 5458 (0.05 Lacs ) done.
Cummulative ₹ 50.96Lacs ( against 140Lacs )
on Friday, October 17th 2025, 6:30:00 pm
36.36%
Financial Progress
15th Expenditure
of ₹ 5458 (0.05 Lacs ) done.
Cummulative ₹ 50.90Lacs ( against 140Lacs )
on Wednesday, October 22nd 2025, 6:30:00 pm
39.75%
Financial Progress
18th Expenditure
of ₹ 464268 (4.64 Lacs ) done.
Cummulative ₹ 55.66Lacs ( against 140Lacs )
on Monday, October 27th 2025, 6:30:00 pm
40.23%
Financial Progress
19th Expenditure
of ₹ 66847 (0.67 Lacs ) done.
Cummulative ₹ 56.32Lacs ( against 140Lacs )