Refresh data
on Saturday, February 28th 2009, 6:30:00 pm
0.10%
Financial Progress
1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 105Lacs )
on Sunday, March 1st 2009, 6:30:00 pm
Work Sanctioned
रोड़धार कफलना मोटर मार्ग का नव निर्माण।
on Sunday, January 31st 2010, 6:30:00 pm
0.21%
Financial Progress
2nd Expenditure
of ₹ 12000 (0.12 Lacs ) done.
Cummulative ₹ 0.22Lacs ( against 105Lacs )
on Friday, December 31st 2010, 6:30:00 pm
0.21%
Financial Progress
3rd Expenditure
of ₹ 175 (0.00 Lacs ) done.
Cummulative ₹ 0.22Lacs ( against 105Lacs )
on Wednesday, February 28th 2024, 5:53:00 am
PWD UttarakahndPhoto (ID 36353) from Site Received
Uploader : Mukesh Singh Parmar, Chief Engineer Level-II ,NH Zone
Landmark : Andharethi
Remark : 0/23 3rd HP Bend ok
on Wednesday, February 28th 2024, 5:59:56 am
PWD UttarakahndPhoto (ID 36354) from Site Received
Uploader : Mukesh Singh Parmar, Chief Engineer Level-II ,NH Zone
Landmark : Hp bend 4
Remark : Ok
on Wednesday, February 28th 2024, 6:32:55 am
PWD UttarakahndPhoto (ID 36360) from Site Received
Uploader : Mukesh Singh Parmar, Chief Engineer Level-II ,NH Zone
Landmark : Hafalna
Remark : 2/17 hp bend 8
on Thursday, August 29th 2024, 4:49:29 am
PWD UttarakahndPhoto (ID 52292) from Site Received
Uploader : Deepak Kumar Agarawal, Assistant Engineer Civil ,PD New Tehri
Landmark : 0/1
Remark : Grade check work
on Sunday, September 1st 2024, 6:30:00 pm
42.30%
Financial Progress
4th Expenditure
of ₹ 4419100 (44.19 Lacs ) done.
Cummulative ₹ 44.41Lacs ( against 105Lacs )
on Sunday, September 29th 2024, 6:30:00 pm
42.39%
Financial Progress
5th Expenditure
of ₹ 9643 (0.10 Lacs ) done.
Cummulative ₹ 44.51Lacs ( against 105Lacs )
on Monday, October 28th 2024, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, December 5th 2024, 6:30:00 pm
72%
Physical Progress
Physical Progress Reported at 2nd time
on Sunday, December 29th 2024, 6:30:00 pm
46.23%
Financial Progress
6th Expenditure
of ₹ 403396 (4.03 Lacs ) done.
Cummulative ₹ 48.54Lacs ( against 105Lacs )
on Sunday, December 29th 2024, 6:30:00 pm
53.99%
Financial Progress
7th Expenditure
of ₹ 814200 (8.14 Lacs ) done.
Cummulative ₹ 56.69Lacs ( against 105Lacs )
on Wednesday, January 1st 2025, 9:59:17 am
PWD UttarakahndPhoto (ID 62121) from Site Received
Uploader : Deepak Kumar Agarawal, Assistant Engineer Civil ,PD New Tehri
Landmark : X Sex 2/32
Remark : Road construction work in progress
on Monday, March 3rd 2025, 6:30:00 pm
54.11%
Financial Progress
8th Expenditure
of ₹ 12870 (0.13 Lacs ) done.
Cummulative ₹ 56.81Lacs ( against 105Lacs )
on Thursday, May 22nd 2025, 6:30:00 pm
55.10%
Financial Progress
9th Expenditure
of ₹ 103986 (1.04 Lacs ) done.
Cummulative ₹ 57.85Lacs ( against 105Lacs )
on Monday, June 9th 2025, 7:15:59 am
PWD UttarakahndPhoto (ID 73766) from Site Received
Uploader : Satish Chandra Bhatt, Assistant Engineer Civil ,PD New Tehri
Landmark : 1
Remark : Work completed
on Monday, June 30th 2025, 6:30:00 pm
66.68%
Financial Progress
10th Expenditure
of ₹ 1215786 (12.16 Lacs ) done.
Cummulative ₹ 70.01Lacs ( against 105Lacs )
on Wednesday, July 16th 2025, 6:30:00 pm
67.20%
Financial Progress
11th Expenditure
of ₹ 54900 (0.55 Lacs ) done.
Cummulative ₹ 70.56Lacs ( against 105Lacs )
on Wednesday, October 22nd 2025, 6:30:00 pm
67.33%
Financial Progress
12th Expenditure
of ₹ 14003 (0.14 Lacs ) done.
Cummulative ₹ 70.70Lacs ( against 105Lacs )
on Monday, October 27th 2025, 6:30:00 pm
67.38%
Financial Progress
13th Expenditure
of ₹ 5340 (0.05 Lacs ) done.
Cummulative ₹ 70.75Lacs ( against 105Lacs )